Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 16

Substation Design Specification

Scheme Number 20004


Scheme Title Rayleigh 4th SGT – EDF Works

Table of Revisions

Revision Date of
Reason for Revision Revised by
Number Revision
0 14/08/05 Draft Issue for Client Comments P.Kendrew /
J.Isaac
1 05/09/05 Modified in line with clients comments P.Kendrew /
J.Isaac
2 14/02/06 Modified in line with clients comments P.Kendrew

Notes for Completion:

1. Please complete the above table each time a revision is made.

2. This document is referenced by the PDP and must be completed as far as possible at both the time of obtaining
agreement from the Senior Project Manager (Construction) and at scheme handover to Construction.

3. This document will be transferred directly to the contract tender document and will be part of the contract
specification.

4. When required Construction must update the document to make suitable for the tender process.

5. Where resanction as a result in design changes, this document must be reissued by Network Design.

6. The document specifies substation HV and protection and control equipment, layout, accommodation, installation
and commissioning requirements. It also defines ancillary equipment not appropriate to the SDS. The content
should include under key requirements and issues, specific requirements, information and areas of novelty,
complexity, hazard or risk, of which Construction and later a Contractor needs to be informed.

Form TP146.08
SUBSTATION DESIGN SPECIFICATION

(Scheme specific layout, accommodation, installation and commissioning requirements for HV and protection and control
equipment)

1. SUMMARY OF WORK

Item Key Requirements and Issues


1.1 A modification application has been placed by EDF with NG to provide a fourth 240MVA
400/132kV SGT (SGT3) at Rayleigh Main and take the opportunity to replace the existing
132kV AIS substation at Rayleigh local with a new 20 Bay GIS substation located at Rayleigh
Main Substation.

The new 240MVA SGT (SGT3) will be installed within the spare bay at Rayleigh main
adjacent to SGT1 bay and connected into one of the bay’s of the new 132kV GIS Substation.
(supplied and installed by others)

The works will also include the replacement of the existing SGT2 transformer with a new
240MVA SGT. The existing transformer foundation will require modification to accommodate
the new SGT2. (supplied and installed by others)

NG shall carry out the new SGT3 & SGT2 installation, 400kV bay works and secondary
equipment modifications at Rayleigh Main 400kV substation under a separate contract.

SGT3 and SGT2 together with the existing SGT circuits SGT1and SGT4 will be connected to
the new GIS substation via new 132kV XLPE cables to be installed by EDF.

On completion of the works, EDF will be responsible for the decommissioning of the existing
Rayleigh Local site together with removal of redundant OHL and towers.

This Specification details the works to be undertaken by EDF associated with NG’s SGT
circuits at Rayleigh Main 132kV substation.

1.2 The required works are summarised as follows:-

132kV Equipment

 4 Off NG bays within 20 Bay 132kV GIS substation.


 Installation of new 132kV XLPE power cables from SGT3 to new GIS switchgear.
 Installation of new 132kV XLPE power cables from SGT1, SGT2 and SGT4 to new
GIS switchgear.
 All 132kV protection works including substation control system and I/O indications
 HAM equipment.
 Provision of civil works as detailed in the Civil Design Specification
 Decommissioning and removal of redundant switchgear and equipment, including
multicore cables, compressed air system, cable sealing ends etc at Rayleigh Local
Substation.

1.3 All works shall be carried out in accordance with the following generic requirements:-

 Commissioning / decommissioning in accordance with TP 106.


 The Supplier to produce a Design Intent Document for the complete scope of works.
 Full compliance with TP documentation.
 Provision of NGT Asset Register information as TP 104.
 Update cable route records including bonding arrangements and provide records for
new cables.
 All relevant existing drawings in NG drawing record system to be updated.
 All new drawings, equipment manuals etc shall be indexed and entered on the NG
drawing record system.
 Photographic record of cable works to be provided.
 All equipment installed shall be Type Registered and compliant with current NGTS’s.
 The following NSI’s shall be applicable to the site for which suitably authorised
operatives / persons will be required: UK BP/SE/NSI 5 , NSI 6, NSI 8, UK BP/SE/NSI
9, UK BP/SE/NSI 12, UK BP/SE/NSI 24,UK BP/SE/NSI 33.
 Any switching of NG bays must comply with NG safety rules and be carried out by
NG Authorised Personnel.

1.4 Associated Drawings:

Overall Site Plan Drawing No. 5038600/09.01/0001


Typical Section SGT3 Bay Drawing No. 5038600/09.01/0002
Key Line Diagram for SGT3 Drawing No. 5038600/09.02/2000
Site Plan SGT3 & SGT2 Roads and Drawing No. 5038600/09.01/0003
Drainage

2. SITE INFORMATION

Item Key Requirements and Issues

2.1 Rayleigh 400kV Main site is located off the A129 London Road, in Rawreth, Wickford in
Essex.

The existing Rayleigh Main 400kV Substation is of AIS outdoor switchgear design, owned,
and operated by NG and comprises of 7 full bays and one spare bay to be utilised for new
SGT3.

The existing Rayleigh 132kV substation is located remotely from Rayleigh main and is of AIS
outdoor switchgear design, owned and operated by EDF.

2.2 There is only one main site access to Rayleigh Main located off the A129 London Road.

The site access is shared with NG gas and therefore access to the site during construction
will have to be co ordinated .

2.3 The site safety clearance height is 2.1m. Vehicles above this height can only be moved on
site as directed by an NG Senior Authorised Person. There are height barriers on site to
enforce this.

2.4 Ground investigations /reports are to be carried out by the contractor prior to the start of any
civil works to identify the location of existing services.

3. PLANNING REQUIREMENTS

Item Key Requirements and Issues


3.1 No potential planning issues are anticipated with 132kV cable routes, as works will be
confined within NG / EDF ownership boundary. However, the Contractor will be required to
confirm this.

3.2 All planning consents associated with the Construction of the new GIS building are the
responsibility of EDF.
4. LAYOUT AND STAGE BY STAGE REQUIREMENTS

Item Key Requirements and Issues


4.1 The proposed location for the new 132kV GIS substation compound is within a green field
site (see drawing No. 5038600/09.01/0001). Works associated with the construction of the
GIS compound can be substantially completed, outside of NG Safety Rules without the need
for outages.

4.2 The envisaged stage by stage requirements of the project are set out within the proposed
construction and outage programme. The Contractor shall highlight with his tender any
proposed change to the sequence of tasks and strategy included in the construction
Programme taking into account NG’s works running concurrently. .

Supplier design: We assume that the above is given for information and all associated works is
the responsibility of EDF.

5. ELECTRICAL CLEARANCES

Item Key Requirements and Issues


5.1 All substation layout designs to be in accordance with NG technical specifications and
guidelines accounting for all necessary maintenance requirements.

5.2 The control and ownership boundary between the NG’s assets and the EDF’s assets is
dependent on the configuration of the switchgear and the gas zone boundaries relating to the
busbar disconnectors. In general, control responsibility will follow ownership and the
application of NG or EDF Safety Rules will align with ownership.

Supplier design: We assume that the above is given for information and all associated works is
the responsibility of EDF.
6. HIGH VOLTAGE EQUIPMENT

Item Key Requirements and Issues


6.1
132kV GIS Substation

General Requirements

Design and build of 132kV gas insulated switchgear substations, including all associated
equipment, designed to the relevant TS/NGTS and the specific requirements detailed
within the Scheme Design Specification (SDS).

A double busbar GIS switch bay complete with local control and interface marshalling
cubicle is required for each NG circuit incorporating:
 Circuit breaker
 2 x three position bus selector disconnector / earthing device
 Feeder three position disconnector / earthing device
 Feeder earthing switch (high speed earthing switch) on incoming circuit
 Protection CTs
 Single phase synchronising VT
 Cable box capable of accepting 240MVA rated XLPE cable.
 Provision for installation of HAM CTs and VTs
The allocation of bays to the individual substation sections shall be as follows:

Rayleigh – SGT3, Rayleigh – SGT1, Rayleigh – SGT2, Rayleigh – SGT4, Bradwell


circuit.

The GIS NG bays shall be designed such that modifications can be carried out with the
minimum outage requirements as specified in NGTS 2.1 item 3.1. The contractor shall
provide a method statement, with the tender response, describing the procedure to modify,
maintain and HV test the new NG bays.
The bays shall be designed such that there are Effective Points of Separation (EPOS)
available to allow extension, maintenance and testing to be carried out with the minimal
disturbance to the overall system. One example of this is the requirement for two points of
isolation between the HV test point and any existing equipment live at system voltage. This
is necessary during installation and extension where testing is required in stages.
The scope of work is also to include provision of all auxiliary plant and equipment such as
LV

VT Synchronising
AC/DC supplies, earthing etc. as deemed necessary by the tenderer to ensure fully
operational NG SGT bays within the GIS substation are provided.
All equipment shall be compliant with the relevant NGTS, TS and IEC requirements.

If GIS switchgear utilising a combined disconnector / earthing device is offered, compliance


with NGC Safety Rules and operational procedures must be demonstrated. These require
independent locking facilities for the disconnector and earthing device function.

SF6 density alarms for the disconnector compartments shall be designed to facilitate
testing (this is required prior to each use of the disconnector as a point of isolation).

The GIS design shall take account of the following NGC Safety Documentation relevant to
SF6:

 NSI 10 Equipment containing sulphur hexafluoride (SF6)


 NS-C2 Sulphur hexafluoride (SF6) filled equipment
 SN-SR20 Work adjacent to SF6 gas barriers pressurised above atmospheric pressure

6.1.2 Circuit Breakers


These shall be of a design rated as per SDS and to the relevant NGTS, TS and IEC
requirements

6.1.3 Disconnectors

These shall be of a design rated as per SDS and to the relevant NGTS, TS and IEC
requirements. The bus transfer duties specified in IEC 1128 shall be complied with.

6.1.4 Earth Switches / Earthing Devices

These shall be of a design rated as per SDS and to the relevant NGTS, TS and IEC
requirements.

6.1.5 Current Transformers


These shall be of a design rated as per SDS and to the relevant NGTS, TS and IEC
requirements. Reference shall be made to the Protection section of this document for any
site specific CT core requirements.

6.1.6 GIS Surge Arresters


The Supplier shall carry out an insulation co-ordination study to establish whether surge
arrestors are required at the 132kV GIS end of 132kV cables. If required, GIS surge
arrestors shall be installed in accordance with TGN (T) 27.
6.1.7 Voltage Transformers
The voltage transformers shall be of a design rated as per SDS and to the relevant NGTS,
TS and IEC requirements. Reference shall be made to the Protection section of this
document for any site-specific requirements.

6.1.8 Busbars, Connections and Enclosures


These shall be of a design rated as per SDS and to the relevant NGTS, TS and IEC
requirements.

6.1.9 Interlocking
See Protection and Control section.

6.1.10 Settlement Metering


The Contractor shall provide a Settlement Metering system for SGT3 in compliance with
Metering Code of Practice One, NGTS 2.9 plus all NG Specifications referenced therein.
The equipment shall be installed as shown on the SLD 5036355/09.02/2000

6.1.11 Support Structures


Any support structures supplied shall be designed for all static and dynamic loading
conditions and detailed calculations to prove suitability will be required for assessment.

For detailed requirements, refer to Civil Design Specification

132kV Power Cables


6.2
The Installation of new 132kV XLPE power cables associated with SGT3 from 132kV
sealing ends located on 400kV site to the new GIS substation.
Please refer to Cable Design Specification document.

6.3 OHL Modifications

Please refer to OHL design Specification

6.4 132kV AIS Busbars, Connectors and Fittings

The 132kV busbar conductor and connectors shall be designed for use on a system rated
for :

 a maximum system voltage of 145kV, 50Hz.


 a normal rated current of 2,000A.
 a short circuit breaking capacity of 40kA for 3 seconds, three phase and single-phase
(rms.) rated short circuit and short time withstand current.

The busbar conductor and connectors would be in accordance with the relevant NGTS, TS
and IEC requirements.
6.5 SF6 Gas Handling Cart

A mobile SF6 gas-handling cart is to be provided by EDF as part of the GIS Substation
works.

6.6 Earthing

The earthing system for the new Rayleigh 132kV GIS substation is to be provided by EDF
as part of the GIS substation works. EDF will be responsible for connecting the new
earthing system to the existing earthing system at Rayleigh, including the provision of
isolation links. The earthing system shall be designed in accordance with NGTS 3.1.2 and
meet the rating requirements specified in the SDS.

The existing site earthing system will be tied into as appropriate for the connection of the
new equipment (including structures). All new conductors will be rated to carry the specified
fault current.

The new earthing (including the joints to the existing earthing) will be tested in accordance
with NGTS 3.1.2 to prove the integrity.

Where equipment support structures form part of the current path to earth, calculations will
be provided to prove the adequacy of the structural sections to carry the full fault current
(as per BS7430).

‘D’ loops will be provided on AIS support structures, suitable for the connection of standard
portable earth clamps. The locations of the ‘D’ loops will be agreed with National Grid Co.
at the design stage.

Upon completion of the new 132kV GIS substation the Contractor shall carry out an earth
resistance measurement on the combined 132/400 kV grid and perform calculations to
confirm the step and touch potentials and Ground Potential Rise at the site.

Supplier design: We assume that the above is given for information and all associated works is
the responsibility of EDF.

7. PROTECTION AND CONTROL

Item Key Requirements and Issues


7.1 This contract includes for the supply, installation, testing and commissioning of the following
work packages :-
New fully equipped SGT LV protection panels. These shall be located in the new EDF 132kV
relay/control room.

Extension / modification of the existing Substation Control System at Rayleigh 400kV


substation to facilitate control of new SGT 132kV GIS bays. The new RTU’s shall be installed
in the new EDF 132kV relay/control room
Interfacing as required to EDF’s new Telecontrol Equipment.
Removal of redundant 132kV relay panels and SCS equipment.
7.2 The modification of all existing NG drawings to show the new equipments and their cabling
for the packages shown above shall be included. The existing NG drawings shall be modified
to remove all references to equipment, cables and ancillaries made redundant under this
scheme.

All costs for auditing Schematic Diagrams via an independent source shall be included for;
the methodology and certification shall be in line with NG’s existing framework agreement.

7.4 Current Transformers (NGTS 3.2.4)


7.4.1 SGT3

The following CT classes and ratios are required for the current transformers in the GIS:-

Core 1 Class X 1000/500/1


Core 2 Class X 1000/500/1
Core 3 Class 1 30VA 5P20 1200/600/1
Core 4 Class X 1000/1 *
Core 5 Class X 1000/1 *

Note: CT's marked thus '*' are for EDF’s 132kV busbar protection and the CT
characteristics and ratio are to be confirmed by EDF.

Core 1, 2 and 3 should be situated on the busbar side of the circuit breaker if possible, with
cores 4 and 5 on the line side.

At the transformer end, the CTs are located in the SGT bushings. The existing CT
arrangements shall be retained.

7.5 Settlement Metering

The settlement metering associated with the existing SGTs is presently located in the
metering room on the 400kV site.

The Contractor shall provide a Settlement Metering system for SGT3 in compliance with
Metering Code of Practice One, NGTS 2.9 plus all NG Specifications referenced therein. The
equipment shall be installed as shown on the SLD 5036355/09.02/2000

Installation shall be in accordance with TGN(E) 56


7.5.1 Operational Metering
Operational metering functions shall be provided for SGT3 to give indication to the
Substation Control System of:
System Voltage, Phase Current, Active Power, Reactive Power, Winding Temperatures,
Voltage Phase Angle. Some of these are provided at 132kV and therefore EDF
responsibility.

7.6 Protection
7.6.1 General Requirements:-

All protection schemes and equipment will be specified to the relevant NGTS and all
associated level 3 specifications. All new protection equipment to be provided will be Type
Registered. Should non-type registered equipment be offered the contractor shall outline a
timetable for the registration, and provide a named approved alternative should the new
equipments not be available in the timescales required.
As far as possible, standard bay solutions, in accordance with relevant NGTS shall be
adopted, interfacing with existing HV protection equipment on SGT1, SGT2 and SGT4
circuits, and with the new HV protection equipment being installed by NG on the SGT2 and
SGT3 circuit.

The contractor is responsible for providing protection setting calculations for all new, modified
and affected protection schemes. This shall include checking, issue, application and update
of NG databases as appropriate, in the timescales outlined in TP106

Self-reset trip relays are to be provided.


All protections to be provided must have a thermal withstand to relevant NGTS requirements.

The contractor shall include for new Standard Bay Solution equipments to be incorporated
into the PDSA framework agreements already in place between the manufacturers and NG.

7.6.2 132kV Busbar Protection:-

New 132kV busbar protection for Rayleigh GIS substations shall be provided by EDF as part
of the GIS substation works.

The Contractor shall provide CT inputs to the busbar protection as required for each SGT
circuit, and connect trip output initiations from the busbar protection to each NG bay. The
Contractor shall also provide busbar protection alarms as required to NG’s SCS equipment.

At 132kV, it is not normal practice to install separate circuit breaker fail protection. If the CTs
are not located, either side of the CB, then an Interlocked Overcurrent relay will be required.

Should a numerical busbar protection with integral circuit breaker fail (CBF) be installed, then
the CBF maybe enabled with the agreement of NG. This would negate the need for a
separate Interlocked overcurrent relay.

7.6.3 Transformer LV Protection:-

Transformer LV protection in accordance with Section 7 of NGTS 3.24.8 shall be provided on


each NG SGT circuit. The LV protection shall interface with existing HV protection equipment
on SGT1, SGT2 and SGT4 circuits, and with the new HV protection equipment being
installed by NG on the SGT2 and SGT3 circuit. Any modifications required to the existing HV
protection arrangements on SGT1 and SGT4 shall be carried out as part of these works.

LV connections protection will be required on the relocated 132kV cable connections as


cable length exceeds 50 metres. It should be noted that no LV connections protection
presently exists on SGT circuits.

The contractor shall show a preliminary evaluation in the tender submission to confirm that
charging currents for the cable circuits do not prohibit the application of LV connections
protection in accordance with NGT policy PS(T) 010. If LV connections protection cannot be
applied, a suitable cable differential protection scheme shall be specified for the 132kV cable
circuits.

7.6.4 Ancillary Equipment


Equipment (with particular reference to laptops, software and leads) and other proprietary
equipment, which is required to enable the user to access information (settings/fault records)
from protection and control equipment provided, shall be supplied under the scope of this
contract. Details of the extent of such provision shall be given in the tender.

7.6.5 Automatic Tap Change Control


Automatic Tap Change Control (ATCC) of transformers SGT1, SGT2, SGT4 at Rayleigh
substation is at present integral to the Capula SCS. The Capula SCS shall be modified and
extended to incorporate the addition of SGT3 and the new 132kV GIS arrangements. (By
Others)

The Supplier shall be responsible for any required modifications to the SCS including supply
of hardware/software and re-commissioning. Where appropriate, the integrity of modified
software algorithms shall be confirmed by factory testing prior to installation on site.

7.6.7 Substation Control System

New SCADA interface cubicle(s) as per NGTS 2.7 shall be provided in the new EDF 132kV
relay/control room, which should contain all necessary RTU & interface equipments
necessary for the transfer of the controls, analogues, indications and alarms generated by
the new 132kV switchgear into the existing 400kV SCS control system located in the control
room on the 400kV site.

All SCS database modifications and data set switches shall be carried out under this
contract, including the provision of facility schedules and 300 sheets. The supplier is required
to advise of projected dates to ensure correct and efficient co-ordination with NG database
changes in accordance with TP106 timescales.

All NG owned equipment shall be controlled by the NG SCS with indication of circuit breaker
and busbar selector disconnectors (where applicable) provided to the UU SCS. If the busbar
selector disconnectors are EDF owned, then indication of these shall be provided to the NG
SCS and control will be the responsibility of EDF. Plant state indications will be provided
from all 132kV bus-sections and bus-couplers to NGC’s SCS equipment.
The ownership boundaries will be dependent on the switchgear gas zone arrangements.

The above needs to be confirmed correct.

7.6.8 Fault Recording:

Fault recording facilities shall be provided in accordance with NGTS 3.24.71.

7.6.9 Automatic Switching, Synchronising and Voltage Selection

The NG SGT circuits at Rayleigh 132kV substations shall be provided with voltage selection
and synchronising equipment to NGTS 3.24.60.

Equipment is to be installed on the LV circuit breakers of SGT’s 1, 2, 3 and 4, with the facility
to check synchronise, dead bar charge, dead line charge, and dead line/dead bar close and
manual override close in line with NGT setting policy.

There is no Delayed AutoReclose(DAR) requirement on NG’s SGT circuits at Rayleigh


132kV substations.

7.6.10 Autoclose:
The existing Rayleigh local 132kV autoclose scheme will require modification to take account
of the new relocated GIS 132kV substation and the additional new 400/132 SGT.

New equipment is to be installed in the GIS132kV common protection and control room.

The scope of works envisaged at this time, is to divert the existing circuit initiations (LV CB
and protection for SGT1, SGT2 & SGT4) from the existing 132kV substation to the new
132kV GIS substation. Provision of facilities for the additional SGT are to be made. (By
Others)

7.6.11 Cable Monitoring

The contractor shall make provision for a 600 X 600mm floor mounted cubicle located within
the NG control/relay room, for a HV Cable Temperature Monitoring (CTM) system to be
provided and installed by others

7.6.12 Interlocking

The NG bays shall be provided with mechanical/electrical interlocking to NGTS 3.1.1, all
modifications / interfaces to the existing electrical & mechanical interlocking systems on the
NG system are to be included for.

Supplier design: We assume that the above is given for information and all associated works is
the responsibility of EDF.

8. PROTECTION & CONTROL RELAY SETTINGS

8.1 The Contractor shall prepare Protection & Control Relay Settings for all new and/or existing relays as
follows: [The requirement shall be defined in terms of substation bays or relay function if a more specific
definition is required and shall be specified by authorised Settings Engineers (Employer) at time of tender
preparation].

Substation Voltage Name of Substation Bay or Relay Function


Rayleigh 132 SGT1 LV Conns & Bay Protection
SGT2 LV Conns & Bay Protection
SGT4 LV Conns & Bay Protection
SGT3 LV Conns & Bay Protection
Rayleigh 132 132kV Busbar protection

8.2 Power system changes or considerations either inside or outside the boundary of the contract,
relevant to the settings to be undertaking (e.g. fault levels, changes to feeder OHL or cable).
……………………………………………………………………………………………………………

Supplier design: We assume that the above is given for information and all associated works is
the responsibility of EDF.

The Contractor shall confirm whether the settings defined in 8.1 comprise a full and complete listing with
reference to the tender specification by completing the following (delete as appropriate):

1. The settings listing defined in 8.1 is complete


OR
2. The settings listing defined in 8.1 needs to be added to as follows:

Substation Voltage Name of Substation Bay or Relay Function


9. MARSHALLING CUBICLES, KIOSKS AND SUPPLIES PILLARS

Item Key Requirements and Issues


9.1 Multicore cables shall be marshalled on a bay-by-bay basis. Where practicable, multicore
cables between transformer hv and lv bays shall be routed via a single marshalling points.

9.2 All external marshalling kiosks and cabinets shall be designed to BS EN60529 with a degree
of protection to minimum of IP54, after all labels, glands, fittings etc have been fitted.

Supplier design: We assume that the above is given for information and all associated works is
the responsibility of EDF.

10. FACILITY SCHEDULES AND 300 SHEETS

Item Key Requirements and Issues


10.1 Modifications to 300 sheets and facility schedules will be required to accommodate the inputs
from the new 132kV equipment covered within the scope of these works. This will include all
controls, alarms, indications and analogues to be added to the instem SCS.

10.2 Redundant points to be identified and re-allocated to new equipment as required.

Supplier design: We assume that the above is given for information and all associated works is
the responsibility of EDF.

11. PROTECTION AND CONTROL ACCOMMODATION REQUIREMENTS

Item Key Requirements and Issues


11.1 The control and protection equipment associated with the 132kV end of SGT1, SGT2, SGT4
circuits is presently installed in the relay room on the 132kV site.
The HV control and protection equipment for SGT’s 1, 2 and 4 are installed in blockhouses on
the 400kV site.

11.2 All new 132kV protection and control equipment associated with NG’s circuits at Rayleigh
substation is to be housed in a new control / relay room within the new GIS building.

11.3 All protection relays shall be accommodated in floor mounted relay panels of suitable
construction for installation in the relay/control room of the new EDF GIS substation.

11.4 All accommodation, terminal blocks etc shall be in accordance with relevant NGTS
documentation.

Supplier design: We assume that the above is given for information and all associated works is
the responsibility of EDF.

12. ENERGIS AND TELECOMMUNICATIONS

Item Key Requirements and Issues


12.1 No modifications to existing offsite telecoms arrangements are required as part of these
works.

12.2 CTN and PSTN telephones shall be provided in the relay/control room in the new GIS
substation.

Supplier design: We assume that the above is given for information and all associated works is
the responsibility of EDF.

13. SITE SUPPLIES AND BATTERIES (110V AND 48V)

Item Key Requirements and Issues


13.1 New LVAC supplies will be installed in the new Rayleigh 132kV GIS sustation by EDF.
Connections shall be provided from the 400V LVAC switchboard, the 48V battery/distribution
board and the 110V battery/distribution board to each NG SGT 132kV bay.
As far as practicable, the NG supplies shall meet the relevant NGTS requirements. The
following shall be met as a minimum:
 Isolation Facilities compliant with NG Safety Rule requirements shall be provided.
 The fuses and links associated with dc supplies to NG’s SGT circuits shall be marshalled
on a discrete section of the Distribution Board.
 The 48V and 110V battery systems shall meet the operational requirements identified in
relevant NGTS documentation.

Supplier design: We assume that the above is given for information and all associated works is
the responsibility of EDF.

14. MULTICORES AND SITE FIBRE

Item Key Requirements and Issues


14.1 General
All new ducts and multicore trenches between the new 132kV substation and the existing NG
site shall be installed under this contract. Where existing cable trenches need to be modified
to install new cables, this shall be included for.

The Contractor shall include for disconnection/removal of all multicore cabling made
redundant because of these works. The cables shall be dropped off the existing terminals.
Where practicable, the cables will be removed from the existing trench work. Otherwise, they
will cut back to prevent future re-connection.

14.2 Multicore cables

New multicore cabling shall meet the relevant NGTS requirements.

For indoor and confined applications, multi-core, multi-pair and auxiliary cables would be of
an armoured design and of low smoke / low fume, zero halogen type to relevant BS.

For outdoor and unconfined applications, multi-core, multi-pair and auxiliary cables would be
of an armoured design to the relevant EATS requirements.

Cable colours and numbering would be in accordance with the relevant EATS requirements.

All LVAC and DC cables shall be sized for volt drop and current carrying capacity.

14.3 Fibre optic cables

All fibre optic cables shall be supplied in accordance with the relevant NGTS requirements.

Jointing and Testing of fibre optic cables shall be carried out in accordance with the relevant
NGTS requirements.
Supplier design: We assume that the above is given for information and all associated works is
the responsibility of EDF.

15. SHARED SITE REQUIREMENTS

Item Key Requirements and Issues


15.1 The 132kV site will be an operational site for the duration of the works and access will be
required at all times.

Supplier design: We assume that the above is given for information and all associated works is
the responsibility of EDF.

16. REDUNDANT EQUIPMENT

Item Key Requirements and Issues


16.1 EDF will be responsible for the decommissioning of the existing Rayleigh Local 132kV
substation site. All redundant equipment to be removed to scrap and disposed of in line with
current legislation. Transfer notes to be provided for all equipment taken off site to the
satisfaction of NG.

16.2 Some equipment does contain asbestos. Refer to pre-tender H&S plan for specific
information.

16.3 Oil containing equipment may contain PCB’s. The most recent oil sampling results are
included within the Pre-Tender H&S plan for information. Where information is not available,
the contractor shall arrange for samples to be taken and analysed.

Oil PCB details and asbestos reports are included within the pre-tender H&S plan.
Appropriate risk assessment and method statements are required to be produced for all
equipment dismantlement and removal.

16.4 Compressed air system to be de-commissioned in stages consistent with the removal from
the system of the OB14 air blast circuit breakers. Air lines to be stripped back to the air
compressor room. On completion of all circuit breaker removal, all air compressor equipment
to be de-commissioned and removed to scrap.
16.5 A suitably licensed waste contractor would remove redundant equipment from site.

Solid waste would be temporarily stored in covered skips to prevent wind-blown debris.
Liquid waste would be temporarily stored in drums or tanks, having the contents identified,
and situated in a suitably sized containment bund.

Before waste is removed from site, the Contractor would: -

 Ensure the waste carrier is registered and that a copy of their certificate is held on site
 Ensure that the disposal site is identified, and a copy of the site license and schedules
are held on site
 Ensure that a Controlled Waste Transfer Note is completed and a copy retained on site.
 Any Special Waste (identified in the Special Waste Regulations) will require a Special
Waste Consignment Note.

Waste Transfer Notes would be handed over to National Grid Company on completion. A list
of all Waste Transfer Notes would be recorded, and held by Siemens Q, HS&E Manager.

Supplier design: We assume that the above is given for information and all associated works is
the responsibility of EDF.

17. MAINTENANCE

Item Key Requirements and Issues


17.1 All design must take into account maintenance requirements and demonstrate that access to
the equipment can be accommodated within NG safety clearances.

Maintenance shall be in accordance with the suppliers instructions.

17.2 Training: Where equipment is offered which is new to the National Grid System, the
Contractor shall include within his offer for the training of NG staff in the safe operation of the
equipment.

Supplier design: We assume that the above is given for information and all associated works is
the responsibility of EDF.

18. OTHER

Item Key Requirements and Issues


18.1 None

Supplier design: We assume that the above is given for information and all associated works is
the responsibility of EDF.

19. INTERFACE WITH OTHER PROJECTS

Item Key Requirements and Issues


19.1 NG works associated with the Rayleigh main site will be running concurrent with this project.
EDF/NG project engineer to co-ordinate and advise overlapping site activities.

Supplier design: We assume that the above is given for information and all associated works is
the responsibility of EDF.

You might also like