Civil Engineering Skills India Estimation, Quantity Surveyor and Extra Knowledge
Civil Engineering Skills India Estimation, Quantity Surveyor and Extra Knowledge
Civil Engineering Skills India Estimation, Quantity Surveyor and Extra Knowledge
168
Draughtsman Civil - Estimateing & costing
Before undertaking the construction of a project it is Estimate helps us in many ways before, during and after
necessary to know its probable cost which is worked out construction works. The use and importance of estimating
by estimating. An estimate is a computation or calculation are listed below:
of the quantities required and expenditure likely to be
incurred in the construction of work. The primary object of • To give approxiamate cost of construction work.
the estimate is to enable one to know beforehand; the
cost of the work (building, sturctures etc.). The estimate • To know whether the work can be completed according
is the probable cost of a work and is determined to given specifications and within the financial limit.
theoretically by mathematical calculations based on the
• To invite tenders for work and arrange the contract.
plans and drawing and current rates. Apporoximate
estimate may be prepared by various methods but accurate • To get an idea of the material requirements.
estimate is prepared by Detailed Estimate Method. The
acutal cost should not differ much from the estimated cost • To check out work done by contractors during
worked out at the begining. execution.
• To calculate the payment to the contractors according
Accuracy in estimate is very important, if estimate is
to the actual measurement compared with existing
exceeded it becomes a very difficult problem for engineers
estimate.
to explain, to account for and arrange for the additional
money. Inaccuracy in preparing estimate, omission of • To calculate the sale value of buildings.
items, changes in design, improper rates, etc. are the
reasons for exceeding the estimate, though increase in • To fix standard rent.
the rates in one of the main reason. In framing a correct
omissions of any kind of work or part thereof. The rate of Technical terms
each item should be reason. In framing a correct omissions
of any kind of work or part thereof. The rate of each item Project: Project means a full scheme consisting of detailed
should be reasonable and workable. The rates in the technical report, history design data and calculations,
estimate provide for the complete work, which consists of drawings, specifications, rates, project estimates etc. It
the cost of materials, cost of tools and plants, cost of is the detailed requirements of proposal or scheme. The
labour, cost of scaffolding, cost and tools and plants, cost project gives full details of all works involved for both
of water, taxes, establishment and supervision cost, structural and financial requirements.
reasonable profit of contractor, etc.
It requires preliminary investigation and surveying and
Estimate includes cost of material, cost of transportation, selection of site or alignment to start with and then the
cost of labour, cost of temporary structure (scaffolding etc.), detailed surveying before taking up preparation of details
cost of tools, equipments and plant, estamlishment, of the project. Detailed estimate of all works are prepared
supervision charges, cost of water, taxes, profit of contrator separately and a general abstract of cost is prepared
etc. Before starting the work of estimate it is important to showing the cost of the whole project. Drawings of all works
study the drawing carefully. - plans, elevations, sectional elevations and nessary
detailed drawings - and layout plan or index plan of the
Definition: works are given seperately and detailed specifications of
each item of works are also given fo all works.
An art of calculating or computing the various items of
work or project to find out its approximate cost likely to be Besides the buildingm, structurres etc. provisions are
incurred, the quantity required or various materials, made for external services as outer water supply and
requirement of labour etc. is called “Estimation.” sanitary works, strom water drains, road, electric service
lines, etc. Cost of land and levelling and dressing of land
are also included. The cost of preliminary investigation
work is also included in the project estimate.
143
Circulation area: Circulation area is the floor area of The carpet area of an office building may be 60% to 75%
verandahs, passages, corridors, balconies, entrance hall, of plinth area of the building with a target of 75%. The
porches, staircases, etc., which are used for movements planners should aim to achieve a target to 75% of the
of persons using the building. The circulation area of any plinth area. The carpet area of residential building may be
floor shall comprise of the following; 50 to 65% of the plinth area of the building.
a Verandahs and balconies For a framed multi-storeyed building the area occupied by
wall may be 5% to 10% of the plinth area (a standard 3%
b Passages and corridors
for external walls and 2% for internal walls). For ordinary
c Entrance halls building without frame, the area occupied by wall may be
10% to 15% of the plinth area.
d Staircase and mumties
e Shafts for lift External services: In a project besides the building
structure, certain outside work are required which come
The circulation area may be divided ino two parts (i) under external services. External service or work include
Horizontal circulation area and (ii) Vertical circulation area. the following:
Horizontal circulation area: Horizontal circulation area i Digging, filling, levelling and dressing of road.
of a building is the area of verandahs, passages, corridors,
ii Road including approach road, if any.
balconies, porches, etc., which are required for the
horizontal movement of the users of the building. This may iii External sewerage, sewage, disposal of works.
be 10% to 15% of the plinth area of the building.
iv Exrternal electrical service line with posts, if any.
Vertical circulation area: Vertical circulation area of a v Storm water drains, fencing or compound wall, gate,
building is the area or space occupied by staircases, lifts etc.
and the entrance halls adjecents to them which are
vii Arboriculture plantation of trees.
required for vertical movement of the users of the building.
This may be 4% to 5% of the plinth area of the buildings. The cost external service works should be included in the
complete estimate. The cost of external services works
Carpet area: Carpet area of building is the useful area or
may vary from 10% to 20% depending on the nature and
liveable area or lettable area. This is the total floor area
size of the project.
minus the circulation area, verandahs, corrdors, passages,
staircase, lifts, entrance hall etc., and minus other non- Contingencies: The term ‘Contingencies; indicates
usable areas as sanitary accommodations (Bath and incidental expenses of miscellaneous character which can
W.Cs), air conditioning room etc. For office building carpet not be classified under any distinct item sub-head, yet
area is the lettable area or usable area and for residential certain to the work as a whole.
building carpet area is the liveable area and should
excluded the kitchen, pantry, stores and similar other room In an estimate a certain amount in the form of contingencies
which are not used for living purposes. of 3% to 5% of estimate cost, is provided to allow for the
expenses for miscellaneous petty items which do not fall
The carpet area of building for any storey shall be the floor under any sub-head of items of works. Miscellaneous
area excluding the following: incidental expenses which cannot be classified under any
sub-head or item, are met from the amout provided under
a Sanitary accomodation
contingencies.
b Verandahs
c Corridors and passages
Construction: Draughtsman Civil (NSQF Level-5) - R.T. for Exercise 4.5.168 145
Construction: Draughtsman Civil (NSQF Level-5) - R.T. for Exercise 4.5.168 147
Item No. Description Nos Length (m) Breadth (m) Height or depth (m) Content or Quantity
iii When there are material deviation from the original If at any time either before or during the execution of
proposal, even though the cost may be met from the original work, it is found that the original estimate is
sanctioned amount. excessive, then divisional officer may sanction a revised
estimate of reduced amount. While giving such sanction
The revised estimate should be accompanied by a
the Accountant General and other higher authorities
comparative statement showing the variations of each item
are informed.
of works, its quantity, rate and cost under original and
revised, side by side, the excess or saving and reason for 5 Annual repair or annual maintenance estimate
variation. (A.R. or A.M. Estimate): Annual repair or annual
maintenance estimate is a detailed estimate and is
3 Supplementary estimate: Supplementary estimate
prepared to maintan the structure or work in proper
is a detailed estimate and is prepared when additional
order and safe condition. For building; this includes
works are required to supplement the originalworks, or
white washing, colour washing, painting, minor repairs
when furtheer developments is required during the
etc. For road works the A.R. estimate provides for patch
progress of work. This is a fresh detailed estimate of
repairing, renewals, repairs of bridges and culvert, etc.
the additional works in addition to the original estimate.
The absract should show the amount of the original Further, there may be special repair estimate, monsoon
estimate and the total amount including the damage repair estimate, etc.
supplementary amount for which sanction is required.
6 Extension and improvement estimate: When some
4 Supplementary and revised estimate: When a work changes and extensions are required to be made in
is partially abandoned and the estimated cost of the the old work, the cost of whcih cannot be met by the
remaining work is less than 95 percent of the original annual repair/maintenance estimate, a detailed
work, that is less than 95% of the original sanctioned estimate is prepared for such work which is called as
estimate, or when there are material deviations and extension and improvement estimate.
changes in the design which may cause substantial
saving in the estimate, then the amount of the original
estimate is revised by the competent authority. A
supplementary and Revised Estimate is then prepared
and fresh technical sanction of the competent authority
is obtained.
Construction: Draughtsman Civil (NSQF Level-5) - R.T. for Exercise 4.5.168 149
Rules and methods of measurements of works and 3 All work shall be measured net subject to following
taking out quantities tolerances unless otherwise stated
a Dimensions shall be measured to nearest 0.01 metre
Measurement of works occupies a very important place in
i.e. 1 cm.
the planning and execution of any work or project, from
the time of the first estimate are made until the b Areas shall be measured to the nearest 0.01 sq. m.
completion and settlement of payments. The methods
c Cubic contents shall be worked out to the nearest 0.01
followed for the measurements are not uniform and the
cu. m.
practices as prevalent differ considerably in different States.
Even in the same State different departments follow 4 Same type of work under different conditions and nature
different methods. for convenience, a uniform method shall be measured separatley under separate items
should be followed throughout the country. the uniform
5 The bill of quantities shall fully describe the materials
method of measurement to be followed, which is
proportions and workmanships, and accuratley
applicable tothe preparation of the estimates and bill of
respresent the work to be executed. Work which by
quantities and to the site measurement of completed works
its nature cannot be accuratley taken off or which
has been described below.
requires site measurements, shall be described as
provisional.
General rules
6 In case of structural concrete, brickwork or stone
1 Measurement shall be item wise for the finished item masonry, the work under the following categories shall
of work and the description of each item shall be held be measured separatley and the heights shall be
to include materials, transport, labour, fabrication, described
hoisting, tools and plants, overheads and other
a From foundation to plinth level.
incidental charges for finishing the work to the requisred
shape, size, design and specifications. the b From plinth level to first flor level.
nomenclature of each item shall be fully desribed so c From first floor level to second floor level and so on.
that the work involved in item is self-explanatory.
2 In booking dimensions, the order shall be in the The parapet shall be measured with the corresponding
sequence of length, breadth and height or depth or items fo the storey next below
thickness.
Earthwork
1 Earthwork in excavation in ordinary soil, earth work is
mixed soil with kandkar, bajri, etc. earthwork in hard soil cu. m. Per % cu. m.
2 Rock excavation cu. m. Per % cu. m.
3 Earth filling in excavation in foundation cu. m. Per % cu. m.
4 Earth filling in foundation trenches (Usually not measured
and not paid separately cu. m. Per % cu. m.
5 Earth filling in plinth cu. m. Per % cu. m.
6 Earth work in banking, cutting, in road and irrigation channel cu. m. Per % cu. m.
7 Surface dressing and levelling, cleaning etc. sq. m. Per sq. m.
8 Cutting of trees (Girth specified) no. Per no.
9 Puddling, Puddle clay core cu. m. Per % cu. m.
10 Sand filling cu. m. Per cu. m.
11 Quarrying of stone or boulder cu. m. Per cu. m.
12 Blasting or rock (Blasted stone stacked and then measured) cu. m. Per cu. m.
For earth work, normal lead is 30m and normal lift is 1.5m
Concrete
Construction: Draughtsman Civil (NSQF Level-5) - R.T. for Exercise 4.5.169-4.5.172 151
Brick work
Stone work
Wood work
152 Construction: Draughtsman Civil (NSQF Level-5) - R.T. for Exercise 4.5.169-4.5.172
Roofing
Construction: Draughtsman Civil (NSQF Level-5) - R.T. for Exercise 4.5.169-4.5.172 153
Flooring
1 2.5 cm (1”) C.C. over 7.5 cm (3”) L.C. Floor (including L.C.) sq. m. per sq. m.
2 Conglomerate floor, artificial patent stone floor 2.5 cm.
(1”) C.C. over 7.5 cm (3”) L.C. (including L.C.) sq. m. per sq. m.
3 4 cm (1½”) thick stone floor flag stone floor over 7.5 cm
(3”) L.C. (including L.C.) sq. m. per sq. m.
4 2.5 cm (1”) marble flooring over 7.5 cm (3”) L.C. (including L.C.) sq. m. per sq. m.
5 Mosaic or terrazzo or granolithic floor over 7.5 cm (3”) L.C.
(including L.C.) sq. m. per sq. m.
6 Brick flat floor over 7.5 cm (3”) L.C. (including L.C.) sq. m. per sq. m.
7 Brick on edge floor over 7.5 cm (3”) L.C. (including L.C.) sq. m. per sq. m.
8 2.5 cm (1”) or 4 cm (1½”) C.C. floor sq. m. per sq. m.
9 Mud flooring finished gobri lepping sq. m. per sq. m.
154 Construction: Draughtsman Civil (NSQF Level-5) - R.T. for Exercise 4.5.169-4.5.172
10 Apron or Plinth protection (May be of C.C, L.C., brick, etc.) sq. m. per sq. m.
11 Door and window sill (C.C. or cement mortar plastered) sq. m. per sq. m.
Miscellaneous Items
1 Ornamental cornice (Projection, type specified) metre per m.
2 Moudling String course, Drip course, Beading, Throating, etc. metre per m.
3 Ornamental Pillar caps, Pillar base, Flowers, Brackets, etc., no. per no.
4 Railing (Height and type specified) metre per m.
5 Surface drain small (size, material, etc. specified) metre per m.
6 Surface drain large (item wise)
(i) Masonry cu. m. per cu. m.
(ii) Plastering sq. m. per sq. m.
7 Pipe - rainwater, sanitary, water pipe, etc. (Dia. specified) metre per m.
8 Laying pipe line - sanitary, water pipe, etc. (Dia, depth, beeding
etc. specified) metre per m.
9 Jungle clearance (May also be per kn for road and irrigation sq. m. or per sq. m. or
channel) hectare per hectare
10 Silt clearance in irrigation channels (Similar to earth work)
(For thin layer upto 5 cm may be on area basis) cu. m. per % cu. m.
11 Trestel, Crate (Size, type, etc. specified) no. per no.
12 Cleaning flues no. per no.
13 Cotton cords in sky light (May also be by weight in kg) no per no.
14 Easing doors and windows no. per no.
15 Fixing doors and windows no. per no.
16 Supply and fixing of Hinges, Tower bolts, Hasp and staples,
Handles, hardwares etc. no. per no.
17 Glazing sq. m. per sq. m.
18 Glass panes (supply sq m. per sq. m.
19 Fixing of glass panes or cleaning no. per no.
20 Renewing of glass panes no. per no.
21 Well sinking (Masonary or tube well) metre per m.
22 Pile driving or sinking metre per m.
23 Furniture - Chairs, tables, etc. (size, shape specified) no. per no.
24 Painting furniture’s no. per no.
25 Caning chairs no. per no.
26 Pitching of brick, stone, kankar, etc. (Brick pitching may also
be on area basis in sq. m.) cu. m. per cu. m.
27 Lining of Irrigation Channel, Tunner, etc. Materials, thickness
specified (Thick lining may be in volume basis in cu. m.) sq. m. per sq. m.
28 Kankar quarrying, kankar supply cu. m. per cu. m.
29 Kankar consolidation, road metal consolidation cu. m. per cu. m.
30 Dag-belling (May also be per km) metre per m.
31 Bituminous road surfacing sq. m. per sq. m.
32 Dismantiling Same as for Same as for
different iteem different iteam
Construction: Draughtsman Civil (NSQF Level-5) - R.T. for Exercise 4.5.169-4.5.172 155
156 Construction: Draughtsman Civil (NSQF Level-5) - R.T. for Exercise 4.5.169-4.5.172
Construction: Draughtsman Civil (NSQF Level-5) - R.T. for Exercise 4.5.169-4.5.172 157
For large arches the actual area of opening should be R.C.C. and R.B. works may also be estimated inclusive
calculated correctly by mensuration formulae, and of steel and centering and shuttering for the complete
deduction should be made for actual area. works, if specified.
158 Construction: Draughtsman Civil (NSQF Level-5) - R.T. for Exercise 4.5.169-4.5.172
Construction: Draughtsman Civil (NSQF Level-5) - R.T. for Exercise 4.5.169-4.5.172 159
160 Construction: Draughtsman Civil (NSQF Level-5) - R.T. for Exercise 4.5.169-4.5.172
162 Construction: Draughtsman Civil (NSQF Level-5) - R.T. for Exercise 4.5.169-4.5.172
The determination of rate per unit of a particular item of i Establishment (Office, Staff)
work, from the cost of quantities of materials, the cost of
ii Stationary, Printing,Postages, etc.
labourers and other miscellaneous petty expenses require
for its completion is known as the analysis of rate. A iii Travelling expenses.
reasonable profit, usually 10% for the contractor is also iv Telephone
included in the analysis of rate. Rates of materials are
usually taken as the rates delivered at the site of work and v Rent and taxes.
include the first cost (cost at origin), cost of transport,
railway freight if any, taxes, etc. If the materials are to be B Job overheads
carried from a distant place, more than 8 kms. then cost
of transport is also added. The rates of materials and labour i Supervision (Salary of Engineers, Oversers,
vary from place to place and therefore, the rates of different Supervision, etc.)
items of work also vary from place to place. ii Handling of materials.
For the purpose of analysis, the details about all the iii Repairs, carriage and depreciation of T and P.
operations involved in carrying out the work should be iv Amenities of labour.
available, the quantities of materials required and their costs
should be known and the number of different categories of v Workmen’s compensation, insurance, etc.
labourers required and the capacity of doing work per vi Interest on investment
labourer and their wages per day should be known. These
can be known only from experience of practical works. vii Losses on advances.
The rates of a particular item of work depends on the The contractor may be allowed a net profit of 6 to 8 percent,
following: and the miscellaneous overhead expenses may come to
about 5 to 10 percent. For overhead expenses and
i Specifications of works and materials, quality of contractors profit 15 percent of the actual cost may be
materials, proportion of mortar, method of reasonable amount but it is usual practice to add 10
constructional operation, etc. percent for all these under the head profit. For small works
overhead cost may be very little.
ii Quantities of materials and their rates, number of
different types of labourer and their rates. The analysis of rate is usually worked out for the unit of
iii Location of the site of work and its distances from the payment of the particular item of work under two heads.
sources of materials and the rate of transport, availability i Materials and
of water.
ii Labour
iv Profits and miscellaneous and overhead expenses of
contractor. and their costs added together give the cost of the items
of work. The costs of the materials as delivered at site
Overhead costs: Overhead costs include general office inclusive of the transport, local taxes and other charges.
expenses, rents, taxes, supervision and other costs which For tools and plants (T. and P.) and miscellaneous petty
are indirect expenses and non productive expenses on items (sundries) which cannot be accounted in details
the job. lump-sum provision is made. A provision for water charges
@ 1½ of the total cost is made in the rate. Adding 10% to
The miscellaneous expenses on overheads may be under this cost as contractor’s profit, the rate per unit of the item
the following heads: of work is obtained. If transport of matrials is to be done
from a distant place more than 8 km analysis of transport
work may be done separately. If cement and steel are
supplied by the department and the contractor is not to
163
1 Brickwork in lime or cement mortar in foundation and plinth 1.25 cu. m. (45 cu. ft.) per mason
2 -Do- in superstructure 1.00 cu. m. (35 cu. ft.) per mason
3 Brickwork in mud mortar in foundation and plinth 1.50 cu. m. (55 cu. ft.) per mason
4 -Do- in superstructure 1.25 cu. m. (45 cu. ft.) per mason
5 Brick in cement or lime mortar in arches 0.55 cu. m. (20 cu. ft.) per mason
6 -Do- in jack arches 0.55 cu. m. (20 cu. ft.) per mason
7 Half brick wall in partition 5.00 sq. m. (50 sq. ft.) per mason
8 Coursed rubble stone masonry in lime or cement mortar
Including dressing 0.80 cu. m. (30 cu. ft.) per mason
9 Random rubble stone masonry in lime or cement mortar 1.00 cu. m. (35 cu. ft.) per mason
10 Ashlar masonry in lime or cement mortar 0.40 cu. m. (15 cu. ft.) per mason
11 Stone arch work 0.40 cu. m. (15 cu. ft.) per mason
12 Lime concrete in foundation or floor 8.50 cu. m. (300 cu. ft.) per mason
13 Lime concrete in roof terracing 6.00 cu. m. (200 cu. ft.) per mason
14 Cement concrete 1 : 2 : 4 5.00 cu. m. (175 cu. ft.) per mason
15 R.B. work 1.00 cu. m. (32 cu. ft.) per mason
16 R.C.C. work 3.00 cu. m. (125 cu. ft.) per mason
17 12 mm (½”) plastering with cement or lime mortar 8.00 sq. m. (80 sq. ft.) per mason
18 Pointing with cement or lime mortar 10.00 sq. m. (100 sq. ft.) per mason
19 White washing or colour washing three coats 70.00 sq. m. (700 sq. ft.) per washer
20 White washing or colour washing one coat 200.00 sq. m. (2000 sq. ft.) per washer
21 Painting or varnishing doors or windows one coat 25.00 sq. m. (250 sq. ft.) per painter
22 Coal tarring or solignum painting one coat 35.00 sq. m. (350 sq. ft.) per painter
23 Painting large surface one coat 35.00 sq. m. (350 sq. ft.) per painter
24 Distempering one coat 35.00 sq. m. (350 sq. ft.) per painter
25 2.5 cm (1J C.C. floor 7.50 sq. m. (75 sq. ft.) per painter
26 Flag stone floor laying with lime or cement mortar
Excluding L.C. 10.00 sq. m. (100 sq. ft.) per mason
27 Terrazo floor 6 mm thick mosaic work over 2 cm thick
Cement concrete (1 : 2 : 4) 5.00 sq. m. (50 sq. ft.) per mason
164 Construction: Draughtsman Civil (NSQF Level-5) - R.T. for Exercise 4.5.173
50 Scaffolding cost for single storey building Re.0.50 (Rs.1.5% cu. ft. of
Per cu. m.brickwork)
Construction: Draughtsman Civil (NSQF Level-5) - R.T. for Exercise 4.5.173 165
1.54xC
Cement(C) = cu. m. Quantity of materials for brick work
(C + S + A)
1.54 x S Brick work masonry is constructed either in mud, or lime
Sand (S) = cu. m. surkhi or cement sand mortar. Various mixes of mortars
(C + S + A)
are used in construction of brick masonry such as cement
1.54 x A sand mixes of 1:2, 1:3, 1:4, 1:5, 1:6 and 1:7 etc. in which
Aggregates (A) = cu.m first figure denotes the cement and the second as sand.
(C + S + A)
In case of lime mortar, the binding material is lime and
surkhi is added in it in certain ratio to prepare lime surkhi
Where (C + S + A) is the sum of the ratios in a mix of mortar. Ratio of such mix may be 1:2, 1:3 etc. Sometimes
concrete i.e. in a concrete of mix 1:6:12, cement is taken lime sand surkhi mortar in the ration of 1:1:2 is prepared.
1, sand as 6 and aggregates 12 and sum of these ratios
is, C + S + A = 1 + 6 + 12 = 19. Dry materials required for cement sand mortar for 1 cu.
m. of brick masonry = 0.30 cu. m.
1 cu. m. of Portland cement = 30 bags (for
practical purposes) [Volume of brick masonry – total volume of bricks = 1m3
– 500 x (0.19 x 0.09 x 0.09) = 0.25 m3
Quantity Per day
To get dry volume, increase the wet volume by 20%]
4.00 cu.m. per beldar (140 cu.ft) mazdoor
600 bricks per mason Wet materials required for 1 cu. m. of brick work – 0.25
cu. m.
3 cu.m (100 cu.ft) mortar per mazdoor
4000 nos to a distance of 15m (50’) per mazdoor
0.30
5.5 cu.m (200 cu. ft) per mazdoor Factor to convert wet mortar into dry mortar = = 1.2
0.25
Re.0.50 (Rs. 1.5% cu.ft. of brickwork) No. of metric bricks with size 20 cm x 10 cm x 10 cm
per cu.m. required for one cu. m. = 500 Nos
166 Construction: Draughtsman Civil (NSQF Level-5) - R.T. for Exercise 4.5.173
Quantity of dry mortar required = 0.30 cu. m. As the thickness of plaster is more, 20% of mortar may
be taken to fill up the joints, unevenness etc. The quality
Ratio of ingredients i.e. Cement : Sand = 1:5 of wet mortar is equal to 200 x 0.02 + 20% =2.00+0.40 =
2.40 cu. m. Increasing by 25% the dry volume=2.40+
Sum of ingredients = 1+5=6 0.60=3.00 cu. m. the quantities of each material of mortar
may be found by usual method.
Materials for 12 mm thick plastering in wall for 100 Materials for different items of works
sq. m.
The requirement of materials for different items of works
Wets mixed mortar for uniform layer = 1.2 cu.m. Adding is as given below:
30% to fill up joints, uneven surfaces, etc. the quantity of
mortar comes to 1.2+0.36=1.56 CU. M. Increasing by In practice for analysis of rates the reduction in volume of
25% the total dry volume=1.95 cu.m. 2.00 cu.m. (say). finished concrete over the sum total volume of ingredient
materials is taken as 50% to 55%. For 100 cu. m. of
For 1:6 cement sand mortar, Cement=2/1+6=0.30 cu. m., finished concrete the sum total volume of dry ingredient
sand= 0.30 x 6= 1.80 cu.m. Similarly, the quantities of materials may be taken as 152 cu.m. to 154 cu.m.
materials for other proportions may be calculated. The
quantities of materials for different proportions are given
in the following pages.
Construction: Draughtsman Civil (NSQF Level-5) - R.T. for Exercise 4.5.173 167
168 Construction: Draughtsman Civil (NSQF Level-5) - R.T. for Exercise 4.5.173
Materials required for cement concrete of different proportions for 100 cu. m.
Proportion Cement Sand Corse aggregate Quantity of concrete
by volume (cu.m.) (coarse) (Stone) (cu.m.) mixed with water
(cu.m.) (cu.m.)
1:2:4 21 42 84 100
1:2:5 17.2 34.40 86 100
1:3:6 14.00 44.00 88 100
1:4:8 11.25 45.00 90 100
1 : 5 : 10 9.20 46.00 92 100
It is a printed list of rates of various items of work for From the information regarding out-turn, materials
preparing detailed estimates and is maintained by the requirements, rates, etc. the analysis of rates of different
engineering department. It is in a book form and is called items of works may be worked out. The number of
as “schedule of rates book”. These rates are prepared on mazdoors, coolies, bhishties, etc. may be adopted from
the basis of analysis of rates. As these rates vary year the general ideas and different operations of construction
after year, therefore, a premium of fixed percentage is of the particular item of work. As for example, for brickwork
allowed on the schedule of rates. If the variation in the 1½ to 2 mazdoors or helper may be taken per mason; for
workable rates and schedule of rates is much more the lime concrete in foundation mason’s work is very little,
revision of rates is done and a new revised schedule of but requirement of mazdoor is greater for mixing, carrying,
rates is prepared. laying, ramming, etc., for lime concrete in roof terracing
requirement of mazdoor is still greater for beating a number
of days.
Construction: Draughtsman Civil (NSQF Level-5) - R.T. for Exercise 4.5.173 169
Approximate calculation of materials for 100 cu. m. L.C. 1:2:6, Lime = 150/(1+2+6) 16.6 cu. m.
170 Construction: Draughtsman Civil (NSQF Level-5) - R.T. for Exercise 4.5.173
Definition: Valuation is the technique of estimating or a Taxes: These include municipal tax, property tax,
determining the fair price or value of a property such as a wealth tax, etc., which are to be paid by owner of the
building, other engineering structures of various types, property annually.
land etc. By valuation the present value of a property is
b Repairs: The repairs are required to be carried out
determined.
every year to maintain a property in fit condition usually
10 to 15 percent of the gross income or 1% to 1.5%
The value of property depends of its structure, life,
monthly rent or 1% to 1.5% of the total cost of
maintenance, location, bank interest, legal control,
construction may be taken.
demand, purpose for which valuation is required etc.
c Management and collection charges: These
Purpose of valuation include the expenses on rent collection, watchman,
pump attendant, sweeper etc. (about 5% to 10%) of
1 Buying or selling property: When it is required to the gross rent. For small building none of these may
buy or to sell a property, it valuation is required. be taken into account.
2 Taxation: To assess the tax of a property, its valuation d Sinking fund: A certain amount of the gross rent is
is required. Taxes may be municipal tax, wealth tax, set aside annually as sinking fund to accumulate the
property tax, etc. total cost of construction when the life of the building
3 Rent fixation: In order to determine the rent of a is over.
property, valuation is required. Rent is usually fixed in e Loss of rent: The property may not be kept fully
certain percentage of the amount of valuation (6% to occupied in such a case, a suitable amount should be
10%). deducted from the gross rent under out goings.
4 Security of loans or mortgage: When loans are f Miscellaneous: These include electric charges for
taken against the security of the property, its valuation running lift, pump, for lighting common place which
is required. are to be borne by the owner.
5 Compulsory acquisition: Whenever a property is
Scrap value: Scrap value is the value of dismantled
acquired by law, compensation is paid to the owner.
materials. For a building when the life is over at the end
To determine the amount of compensation, valuation
of its utility period, the dismantled materials such as
of the property is required.
steel, bricks, timber, etc. will fetch a certain amount which
6 Insurance: Valuation of a property is also required for is the scrap value of the building. The scrap value of a
insurance, betterment charges, etc. building may be about 10% of its total cost of construction.
Technical terms Salvage value: It is the value at the end of utility period
without being dismantled.
Gross income: Gross income is the total income and
includes all receipts from various sources. The out goings Market value: The market value of a property is the
and the operational and collections charges are not amount which can be offered from the open market. The
deducted. market value will differ from time to time according to
demand and supply.
Net income or net return: This is the amount left after
deducting all out goings, operational and collection Book value: Book value is the amount shown in the
expenses from the gross income or total receipt. account book after allowing necessary depreciation. The
book value of a property at a particular year is the original
Net Income = Gross income - Out goings cost minus the amount of depreciation up to the previous
year. It will be gradually reduced year after year and at
Out goings: Out goings or the expenses are required to the end of the utility period of the property the book value
be incurred to maintain the revenue of the building. the will be only scrap value.
various types of out goings are as follows:
171
Before valuation, the age of the building should be obtained 0 - 5 years Nil Nil
from record or by enquiries or from visual inspection.
5 - 10 years 0.5% 2.5%
Present day cost may be determined by the following
method. 10 - 20 years 0.75% 7.5%
20 - 40 years 1.0% 60%
40 - 80 years 1.5% 60%
Total 90%
The balance 10% represents the net scrap value at the
end of utility period.
Flooring
172 Construction: Draughtsman Civil (NSQF Level-5) - R.T. for Exercise 4.5.174
8 R.C.C., R.B., terraced roofing over stone flags, jack arck roofing
with L.C. terracing 75 years
9 Iron work in roofing 80 years
10 Sal wood work in roof 60 years
11 Country wood in work 15 years
12 Allahabad lock tiling 25 years
13 G. I. sheet roofing of 22 B.W.G. sheet 50 years
14 Sal ballies in roof 20 years
15 Pine wood ceiling 30 years
16 Teak wood doors and windows, Sal wood doors and windows 40 years
17 Country wood doors and wondows 30 years
Iron work
174 Construction: Draughtsman Civil (NSQF Level-5) - R.T. for Exercise 4.5.174
Specification
Objectives: At the end of this lesson you shall be able to
• define and describe the importance of specifications
• classify the specification
• describe the general specification
• explain the detailed specification
• calculate the area and volume at irregular boundary.
Specification: Specification specifies or describes the Specifications depend on the nature of the work, the
nature and the class of the work, materials to be used in purpose for whch the work is required, strength of the
the work, workmanship, etc. and is very important for the materials, availability of materials, quantity of materials
execution of the work. The cost of a work depends much etc.
on the specifications. Specifications should be clear, and
there should not be any ambiguity anywhere. From the Specifications are of two types
study of the specifications, one can be easily understand
the nature of the work and what the work shall be. The 1 General specification or brief specification and
drawings of the building or structure show that 2 Detailed specification
arrangement of the rooms and various parts and the
dimensions - length, breadth and height with brief General or brief specification: General specification
descriptions of different parts. Drawings do not furnish gives the nature and class of the work and materials in
the details of different items of work, the quantity of general terms, to be used in the various parts of the work,
materials, proportion of mortar and workmanship which from the foundation to the supersturcture. It is a short
are described in specifications. Thus the combinations of description of different parts of the work specifying
drawings and specifications define completely the materials, proportions, qualities, etc. General
structure. Drawings and specifications form important parts specifications give general idea of the whole work or
of contract document. structure and are useful for preparing the estimate.
During writing specification attempts should be made to For general idea, the general specifications of different
express all the requirement of the work clearly and in a class of the buildings are given below. These will of course
concise form avoiding repetition. As far as possible, the vary according to the necessity and type of works.
clauses of the specification whould be arranged in the
same order in which the work will be carried out. The General specifications of different class of buildings is as
specifications are wirtten in a language so that they indicate follows:
what the work should be, and words “shall be” or “should
be” are used. 1 First class bulding: The first class building
specifications are as follows.
1 Foundation and Plinth It shall be of first class brickwork (or random rubble masonry) in lime mortar
or 1:6 cement mortars over lime concrete or 1:4:8 cement concrete
2 Damp Proof Course It shall be 2.5 thick cement concrete 1:1.5:3 mixed with water proofing
materials and painted with two coats of bitumen
3 Super Structure It shall be of 1st class brick with lime mortar or 1:6 cement mortar. Lintels
shall be of R.C.C.
4 Roofing Roof shall be of R.C.C. slab with an insulation layer. Height of rooms not
less than 3.7 m.
5 Flooring Drawing and dining room floors shall be of mosaic, bath room and W.C.
floors and dado shall be of mosaic. Bedroom shall be coloured and polished
of 2.5 cm cement concrete over 7.5 lime concrete. Floor of others shall be of
2.5 cm. Cement concrete 7.5 cm. Lime concrete polished.
6 Finishing Inside and outside walls shall be of 12 mm. Cement lime plastered 1:1:6
Drawing, Dining and Bed rooms inside shall be distempered and other inside
white washed 3 coats. Outside shall be coloured snow cem washed 2 coats
over 1 coat of white wash
175
2. Second class buildings: The second class building specifications are as follows
1 Foundation and plinth Foundation and plinth shall be of 1st class brickwork cement mortar over
lime concrete
2 Damp proof course It shall be of 2 cm. thick cement concrete 1 : 2 : 4 mixed with standard water
proofing materials.
3 Superstructure It shall be of 2nd class brick with lime mortar. Lintels shall be of R.B.
4 Roofing Roof shall be of R.B. slab with 7.5 cm. Lime concrete terracing above.
Verandah roof may be of A.C. sheet or Allahabad tiles.
5 Flooring Floor shall be 2.5 cm. cement concrete over 7.5 L.C. verandah floor shall be
of brick tiles finished cement pointed.
6 Finishing Inside and outside walls shall be of 12 mm. Cement mortar plastered 1 : 6
ceiling shall be cement pastered 1 : 3.
7 Doors and windows Frame shall be of R.C.C. or well seasoned sal wood, shutter of deodars wood
4 cm. thick panelled or partly glazed. Doors and windows shall be painted
two coats over one coat of priming.
8 Miscellaneous Rain water pipes shall be provided. Electrification, sanitary and water fittings
may be provided if required.
3 Third class buildings: The specifications for the third class building are as follows
1 Foundation and It shall be of sun dried bricks and mud mortar. Opening shall be provided
with superstructure arch of 2nd class brick work in lime mortar or with wooden
planks. Inside and outside wall shall be water proof mud plastered.
3 Flooring If shall be earthen floor finished with gobris washing (cow dung lapping)
176 Construction: Draughtsman Civil (NSQF Level-5) - R.T. for Exercise 4.5.175
Construction: Draughtsman Civil (NSQF Level-5) - R.T. for Exercise 4.5.175 177
( )
d ⎡01 + 0n + 4 02 + 0 4 + ...... + 0n− 2 + ⎤
Distance (m) 0 5 10 15 20 30 40 60 80
A= ⎢
(
3 ⎢2 0 + 0 + .....0
⎣ 3 5 n −1
) ⎥
⎥⎦
Offset (m) 2.50 3.80 4.60 5.20 6.10 4.70 5.80 3.90 2.20
Find the area between the survey line, the curved boundary
⎡(first ordinate + last ordinate )+ ⎤ line and the first and last offsets by (a) Trapezoidal Rule
Common dist. (d) ⎢
⎢4(sum of even ordinates )+
A= and (b) Simpson’s Rule.
3
⎢⎣2(sum of odd ordinates ) ⎦ Here, the intervals between the offsets are not regular
throughout the length. So the section is divided into three
compartments.
Let,
178 Construction: Draughtsman Civil (NSQF Level-5) - R.T. for Exercise 4.5.175
Construction: Draughtsman Civil (NSQF Level-5) - R.T. for Exercise 4.5.175 179
2L x d s 2 + 1
Chainage Height Height sloping breadth stations (L) 1
Quantity or Volume =
L
6
(A1 + A 2 + 4A m )
where A1 and A2 are the cross sectional areas at the two
ends of a portion or embankment of a road of length L,
and Am is the mid-sanctional area.
180 Construction: Draughtsman Civil (NSQF Level-5) - R.T. for Exercise 4.5.175
=
BL
(d + d ) + 2LS
6 1 2 3
(d12 + d22 + d1d2 ) V=
D
(A1 + 2A 2 + 2A 3 + ...... + 2A n−1 + A n )
2
=
BL
(d + d ) + LS3 (d12 + d22 + d1d2 )
2 1 2
⎛ A + An ⎞
V = D⎜ 1 + A 1 + A 2 + A 3 + ... ... + A n−1 ⎟ or
⎜ 2 ⎟
⎡ ⎛ d + d ⎞ ⎛ d 2 + d 2 + 2d d ⎞⎤ ⎝ ⎠
= ⎢B⎜ 1 2 ⎟ + S⎜ 1 2 1 2 ⎟⎥ x L
⎢ ⎜⎝ 2 ⎟⎠ ⎜ 3 ⎟⎥
V=
D
{A1 + A n + 2 (A 2 + A 3 ...... + A n−1 )}
⎣ ⎝ ⎠⎦
2
Construction: Draughtsman Civil (NSQF Level-5) - R.T. for Exercise 4.5.175 181
200
∴Quantity = (12 + 21.12 + 4 x 16.38 )
6
200 19728
= x 98.64 = = 3288 cu. m.
6 6
182 Construction: Draughtsman Civil (NSQF Level-5) - R.T. for Exercise 4.5.175