04 Edu91 Costing Practice Sheets Solutions (Not To Print)
04 Edu91 Costing Practice Sheets Solutions (Not To Print)
Solution 2:
Workings:
Consumption is calculated on the basis of material requisitions:
Maximum component usage = 4,500 units (Material requisition on 10-01-20)
Minimum component usage = 1,500 units (Material requisition on 24-01-20)
Lead time is calculated from purchase order date to material received date
Maximum lead time = 21 days (15-12-2019 to 05-01-2020)
Minimum lead time = 14 days (30-12-2019 to 13-01-2020)
Reorder quantity (observed) = 10,000 units.
Calculations:
(i) Re-order level
= Maximum usage × Maximum lead time
= 4,500 units × 21 days = 94,500 units
(iv) Store Ledger for the month of January 2020: (Weighted Average Method
Date Receipts Issue Balance
GRN/ Units Rate Amt. MRN/ Units Rate Amt. Units Rate Amt.
MRN (‘000) MR (‘000) (‘000)
01-01-20 - - - - - - - - 3,500 9,810 34,335
05-01-20 008 10,000 9,930 99,300 003 500 9,930 4,965 13,000 9,898 1,28,670
06-01-20 - - - 011 3,000 9,898 29,694 10,000 9,898 98,980
10-01-20 - - - 012 4,500 9,898 44,541 5,500 9,898 54,439
12-01-20 009 10,000 9,780 97,800 004 400 9,780 3,912 15,100 9,823 1,48,327
15-01-20 - - - - 013 2,200 9,823 21,611 12,900 9,823 1,26,716
24-01-20 - - - - 014 1,500 9,823 14,734 11,400 9,823 1,11,982
25-01-20 010 10,000 - - - - 21,400 9,789 2,09,482
28-01-20 - - - - 015 4,000 9,789 39,156 17,400 9,789 1,70,326
31-01-20 - - - - 016 3,200 9,789 31,325 14,200 9,789 1,39,001
[Note: Decimal figures may be rounded-off to the nearest rupee value wherever required)
Value of 14,200 units of stock as on 31-01-2020 (‘000) = Rs. 1,39,001
Solution 3:
From the point of view of cost of material charged to each job, it is minimum under FIFO and maximum under LIFO
(Refer to Tables). During the period of rising prices, the use of FIFO give rise to high profits and that of LIFO low profits.
In the case of weighted average, there is no significant adverse or favourable effect on the cost of material as well as on
profits.
From the point of view of valuation of closing stock, it is apparent from the above statement, that it is maximum under
FIFO, moderate under weighted average and minimum under LIFO.
It is clear from the tables that the use of weighted average evens out the fluctuations in the prices. Under this method,
the cost of materials issued to the jobs and the cost of material in hands reflects greater uniformity than under FIFO and
LIFO. Thus, from different points of view, weighted average method is preferred over LIFO and FIFO.
100 2 200
Jan. 23 Issue to Job W 17 - - - 40 1 40 80 2 160
20 2 40
Statement of Material Values allocated to Job W 16, Job 17 and Closing Stock, under aforesaid methods
FIFO LIFO Weighted Average
(Rs.) (Rs.) (Rs.)
Material for Job W 16 60 120 90
Material for Job W 17 80 100 90
Closing Stock 160 80 120
300 300 300
Solution 4:
Working Notes:
(i) Computation of Annual consumption & Annual Demand for raw material ‘D’:
EOQ =
2Annualdemandof 'D' Ordering cost
= =
Rs. 25014%
= 2,328 kg.
(d) Impact on the profitability of the company by not ordering the EOQ.
Solution 5:
(i) Minimum stock of A
Re-order level – (Average consumption × Average time required to obtain delivery)
= 60,000 kg. – (900units × 12 kg. × 3 weeks) = 27,600 kg.
Working note:
Maximum stock of A = ROL + ROQ – (Minimum consumption × Minimum re-order period)
= 60,000 kg. + 12,000 kg. – [(550units × 12 kg.) × 2 weeks] = 58,800 kg.
Solution 6:
1. Workings:
Consumption is calculated on the basis of material requisitions:
Maximum component usage = 4,500 units (Material requisition on 10-01-20)
Minimum component usage = 1,500 units (Material requisition on 24 -01-20)
Lead time is calculated from purchase order date to material received date
Maximum lead time = 21 days (15-12-2019 to 05-01-2020)
Minimum lead time = 14 days (30-12-2019 to 12-01-2020)
Calculations:
(i) Re-order level
= Maximum usage × Maximum lead time
= 4,500 units × 21 days = 94,500 units
Solution 7.
(i) Minimum stock of Pi
Re-order level – (Average consumption × Average time required to obtain delivery)
= 8,000 kg. – (400 units × 5 kg. × 2 weeks) = 4,000 kg.
Solution 8:
(i) Reorder Quantity (ROQ) = 1,691 kg. ( Refer to working note )
(iii) Maximum level = ROL + ROQ – (Min. usage × Min. re-order period)
= 7,200 kg. + 1,691 kg. – (200 kg.× 4 weeks)
= 8,091 kg.
Solution 9.
Working Notes:
Annual requirement (A) = 27,000 units
Cost per order (O) = Rs. 240
Inventory carrying cost (i) = 12.5%
Cost per unit of spare (c) = Rs. 50
Carrying cost per unit (i × c) = Rs. 50 × 12.5% = Rs. 6.25
𝟐 ×𝐀 ×𝐐
Economic Order Quantity (EOQ) = √
𝐢 ×𝐜
(𝟐 × 𝟐𝟕, 𝟎𝟎𝟎 × 𝟐𝟒𝟎)
=√ = 1440 units
𝟔. 𝟐𝟓
(i) Calculation of saving by opting EOQ:
Existing Order policy EOQ Model
No. of orders 9 18.75 or 19
(27,000 / 3,000) (27,000 /1,440)
A. Ordering Cost (Rs.) 2160 4,500
(Rs. 240 × 9) (Rs.240 × [27,000 / 1,440])
B. Carrying cost (Rs.) 9,375 4,500
(3,000 × Rs.6.25)/ 2 (1,440 × Rs.6.25)/2
Total cost (A+B) (Rs.) 11,535 9,000
Savings of Cost by opting EOQ Model = Rs. 11,535 – Rs. 9,000 = Rs. 2,535
Solution 10.
Working:
Calculation of Annual demand of raw material
= 4,000 Litres (per quarter) x 4 (No. of Quarter in a year) x 2 kg. (raw material required for each Litre of paint)
= 32,000 kg.
Calculation of Carrying cost
Storage rate = 2%
Interest Rate = 6%
Total = 8% per annum
Carrying cost per unit per annum = 8% of Rs. 50 = Rs. 4 per unit per annum
𝟐 × 𝟑𝟐, 𝟎𝟎𝟎 𝐊𝐠 × 𝐑𝐬 𝟒𝟎
=√ = 800 Kg
𝐑𝐬 𝟒
Solution 11:
(a) Re-order level
= Minimum stock + (Average consumption x average delivery time)
= 1,250 units + [625 units x 4 weeks] = 3,750 units
(ii) Workings :
Calculations of standard input of Material B
Material Usage Variance (B) = 300 (A)
Material Usage Variance = (SQ – AQ) x SP
Therefore : = (SQ – 70) x Rs. 15 = 300 (A)
= SQ (B) = 50 Kg
(a) Material cost variance
Material cost variance = (SQ x SP) – (AQ x AP)
Material A = (50 x Rs. 12) – (40 x Rs. 15) = 0
Material B = (50 x Rs. 15) – (70 x Rs. 20) = Rs. 650 (A)
= Rs. 650 (A)
Solution 12:
Annual requirement of raw material in kg. (A) = 2,00,000 units = 40,000 kg.
5 units per kg.
Solution 13:
(i) Computation of Value of Inventory as on 30th September 2019:
Date Particulars Units WAM (Rs.) FIFO (Rs.) LIFO (Rs.)
01-07-19 Opening Stock 25,000 50,00,000 50,00,000 50,00,000
(Rs. 200×25,000) (Rs. 200×25,000) (Rs. 200×25,000)
Weighted average rate = Rs. 50,00,000 + Rs. 95,50,000 + 52,50,000 = Rs. 198
(25,000 + 50,000 + 25,000) units
* Rs. 198 x 68,000
** Rs. 200 × 25,000 + Rs. 191 × 43,000 = Rs. 50,00,000 + Rs. 82,13,000
*** Rs. 210 × 25,000 + Rs. 191 × 43,000 = Rs. 52,50,000 + Rs. 82,13,000
(ii) Computation of Profit or Loss for the Quarter ended 30th September 2019
Particulars WAM (Rs.) FIFO (Rs.) LIFO (Rs.)
Sales 1,46,20,000 1,46,20,000 1,46,20,000
Less: Consumption 1,34,64,000 1,32,13,000 1,34,63,000
Less: Administrative Exp. 3,75,000 3,75,000 3,75,000
Profit or Loss 7,81,000 10,32,000 7,82,000
[Assumption: Issue/ consumption pattern was even throughout the quarter]
Solution 14:
(i) (a) Inventory turnover ratio (Refer to working note)
= Cost of Stock of raw materials consumed
= Rs 1,68,00,000 = 16.8
Rs 10,00,000
(b) Average number of days for which the average inventory is held
= 365 = 365 days = 21.73 days
Working Note:
Particulars (Rs)
Opening stock of raw material 9,00,000
Add: Material purchases during the year 1,70,00,000
Less: Closing stock of raw material 11,00,000
1,68,00,000
(ii) The Inventory turnover ratio for material X is 16.8 which mean an inventory item takes only 21.73 or 22 days to
issue from stores for production process. The rate is better than the industry rate which is 10 time or 36.5 days. This
inventory turnover ratio indicates better inventory management system and good demand for the final product in
market.
Solution 15:
Calculation of cost per unit:
Particulars Units (Rs)
Listed price of Materials 5,000 2,50,000
Less: Trade discount @ 10% on invoice price (25,000)
2,25,000
Add: CGST @ 6% of Rs 2,25,000 13,500
Add: SGST @ 6% of Rs 2,25,000 13,500
2,52,000
Add: Toll Tax 5,000
Freight and Insurance 17,000
Commission and Brokerage Paid 10,000
Add: Cost of returnable containers:
Amount Deposited Rs 30,000
Less: Amount Refunded Rs 20,000 10,000
2,94,000
Add: Other Expenses @ 2% of Total Cost (2,94,000/98 x 2) 6,000
Total Cost of material 3,00,000
Less: Shortage material due to normal reasons @ 20% 1,000 -
Total cost of material of good units 4,000 3,00,000
Cost per unit (Rs 3,00,000/4,000 units) 75
Note:
(1) GST is payable on net price i.e., listed price less discount.
(2) Cash discount is treated as interest and finance charges; hence it is ignored.
(3) Demurrage is penalty imposed by the transporter for delay in uploading or off-loading of materials. It is an
abnormal cost and not included.
(4) Shortage due to normal reasons should not be deducted from cost to ascertain total cost of good units.
Solution 16:
(i) Calculation of Inventory Turnover ratios and number of days:
Material A (Rs) Material B (Rs)
Opening Stock 30,000 32,000
Add: Purchases 90,000 51,000
1,20,000 83,000
Less: Closing Stock 20,000 14,000
Materials Consumed 1,00,000 69,000
Average inventory: (Opening stock + Closing stock) ÷ 2 25,000 23,000
(a) Inventory Turnover ratio: (Consumption ÷ Average Inventory) 4 times 3 times
(b) Number of days for which the average inventory held (Number of 90 days 120 days
days in a year/IT ratio)
(ii) Comments: Materials A is moving faster than Material B. Or Material A has a less holding period.
Solution 17:
Working Notes
1. Annual production = 40,000 units
2. Raw material required for 40,000 units (40,000 units x 1 kg.) = 40,000 kg.
𝟐 × 𝟒𝟎, 𝟎𝟎𝟎 𝐤𝐠𝐬.× 𝐑𝐬. 𝟏, 𝟎𝟎𝟎
3. EOQ = √ = 2,000 kgs.
𝐑𝐬. 𝟐𝟎
4. Total cost of procurement and storage when the order size is equal to EOQ or 2,000 kg.
No. of order (40,000 kg ÷ 2,000 kg) = 20 times
Ordering Cost (20 orders x Rs 1,000) = Rs 20,000
Carrying Cost (Rs) (1/2 x 2,000 kg x Rs 20) = Rs 20,000
Total Cost Rs 40,000
(ii) Statement showing the total cost of procurement and storage of raw materials
(After considering the discount)
Order No. of Total cost of Average Stock Total cost of Discount Total cost
size orders procurement storage of raw
materials
Kg. (Rs) Kg. (Rs.) (Rs.) (Rs.)
(1) (2) (3)=(2) x Rs (4) = ½ x (1) (5) = (4) x Rs 20 (6) (7)=((3)+(5)-(6))
1,000
40,000 1 1,000 20,000 4,00,000 40,000 3,61,000
20,000 2 2,000 10,000 2,00,000 32,000 1,70,000
10,000 4 4,000 5,000 1,00,000 20,000 84,000
Solution 18:
(i) Optimal order quantity i.e. E.O.Q.
𝟐 × 𝟒𝟖, 𝟎𝟎𝟎 × 𝟏, 𝟑𝟓𝟎
=√ = √𝟖𝟔, 𝟒𝟎, 𝟎𝟎𝟎 = 2,939 units
𝟏𝟓
Relevant cost of this order quantity
Ordering Cost = 48,000/2,939 = 16.33, say 17 orders at Rs. 1,350 22,950.00
Carrying Cost = ½ x 2,939 x 15 22,042.50
Relevant Cost 44,992.50
(iii) In case of discount in purchase price, the total cost of Purchase Cost, ordering cost and carrying cost should be
compared.
Original offer at Rs 80 per unit Supplier offered at Rs 72 per unit
Rs Rs
Purchase Cost (48,000 x 80) 38,40,000.00 Purchase Cost (48,000 x 72) 34,56,000.00
Ordering Cost 22,950.00 Ordering Cost 0.00
Carrying Cost 22,042.50 Carrying Cost (1/2 x 48,000 x 3,60,000.00
15)
Total Cost 38,84,992.50 38,16,000.00
This special offer at Rs 72 per unit should be accepted as it saves Rs 68,992.50 as compared to original offer.
Solution 2:
Calculation of total earnings:
= Time taken × Rate per hour + Time Saved × Time taken × Rate per hour
Time Allowed
Solution 3:
Statement of Bonus, total earnings of Employee and hourly earnings under Halsey and Rowan Systems.
SH AH Time Basic Wages Bonus Bonus Total Total Hourly Hourly
Saved (AH x Rs 8) under Under earnings earnings earnings earnings
(B x Rs 8) Halsey Rowan under under under under
System system Halsey Rowan Halsey Rowan
5 xCx8 BxCx8 System system system system
100 A D+E D+F G/B H/B
A B C= (A- D E F G H I J
Hours Hours B) Rs Rs Rs Rs Rs Rs
Hours
8 8 - 64 - - 64 64 8.00 8.00
8 7 1 56 4 7 60 63 8.57 9.00
8 6 2 48 8 12 56 60 9.33 10.00
8 5 3 40 12 15 52 55 10.40 11.00
8 4 4 32 16 16 48 48 12.00 12.00
8 3 5 24 20 15 44 39 14.67 13.00
8 2 6 16 24 12 40 28 20.00 14.00
8 1 7 8 28 7 36 15 36.00 15.00
Solution 4:
Calculation of earnings under different wage schemes:
(i) Day wages:
Worker Day Wages (Rs) Actual Output Labour cost per 100
(Units) pieces (Rs)
A 600 180 333.33
B 600 120 500.00
C 600 100 600.00
Total 1,800 400
Solution 5:
Workings Notes:
Calculation of Total hours saved:
M J
No. of garments assigned (Pieces.) 15 21
Hour allowed per piece (Hours) 8 8
Total hours allowed (Hours) 120 168
(ii) Calculation of loss incurred due to incorrect rate selection had Rowan scheme of bonus payment followed:
M (Rs.) J (Rs.) Total (Rs.)
Basic Wages 1,200 1,680 2,880
(100 Hrs. × Rs.12) (140 Hrs. × Rs. 12)
Bonus [as per Rowan Scheme] 200 280 480
[(TimeTaken/TimeAllowed) × [(100/120) × 20 × Rs.12] [(140/168) × 28 × Rs.12]
Time Saved × Excess Rate]
Excess Wages Paid 1,400 1,960 3,360
(iii) Calculation of amount that could have been saved if Rowan Scheme were followed:
M (Rs.) J (Rs.) Total (Rs.)
Wages paid under Halsey 1,320 1,848 3,168
Scheme
Wages paid under Rowan 1,400 1,960 3,360
Scheme
Difference (loss) (80) (112) (192)
(iv) Rowan Scheme of incentive payment has the following benefits, which is suitable with the nature of business in
which JBL Sisters operates:
(a) Under Rowan Scheme of bonus payment, workers cannot increase their earnings or bonus by merely
increasing its work speed. Bonus under Rowan Scheme is maximum when the time taken by a worker on a job
is half of the time allowed. As this fact is known to the workers, therefore, they work at such a speed which
helps them to maintain the quality of output too.
(b) If the rate setting department commits any mistake in setting standards for time to be taken to complete the
works, the loss incurred will be relatively low.
Solution 6:
Workings:
1. Normal working hours in a month = (Daily working hours – lunch break) × no. of days
= (8 hours – 0.5 hours) × 26 days = 195 hours
2. Hours worked by Mr.Z = No. of normal days worked + Overtime + holiday/ Sunday worked
= (21 days × 7.5 hours) + (9.5 hours + 8.5 hours) + (5 hours + 6 hours)
= 157.5 hours + 18 hours + 11 hours = 186.50 hours.
31,200
House rent allowance (16% of basic salary) 4,160
Employer’s contribution to Provident fund (12% × Rs.31,200) 3,744
Employer’s contribution to Pension fund (7% × Rs.31,200) 2,184
41,288
No. of working days in a month (days) 26
Rate per day 1,588
Transport allowance per day 50
Earnings per day 1,638
Solution 7:
Employee turnover rate using:
(i) Separation Method:
= (No. of workers left + No. of workers discharged/ Average number of workers) × 100
=(40 + 120)/[(3,600 + 3,790) / 2] × 100 = (160/3,695) × 100 = 4.33%
Solution 8.
Employee turnover rate using:
Solution 9:
Labour Turnover Rate (Replacement method) = No. of workers replaced / Average No. of workers
Or, 8/100 = 36/Average No. of workers
Or, Average No. of workers = 450
Labour Turnover Rate (Separation method) = No. of workers separated / Average No. of workers
Or, 6/100 = No. of workers separated / 450
Or, No. of workers separated = 27
Labour Turnover Rate (Flux Method)= [No. of Separations + No. of accession (Joinings)] / Average No. of workers
Or, 14/100 = [27 + No. of accessions (Joinings)] / 450
Or, 100 (27 + No. of Accessions) = 6,300
Or, No. of Accessions = 36
(i) The No. of workers recruited and Joined = 36
(ii) The No. of workers left and discharged = 27
Solution 10.
(a) Working Notes:
(ii) (a) Saving in terms of direct labour cost per unit under Halsey scheme: (Refer to Working Note 3)
Labour cost per unit (under time wage scheme) = 1.975 hours × Rs. 50 = Rs. 98.75
Labour cost per unit (under Halsey scheme)
= (Total wages paid under the scheme / Total number of units produced ) = (Rs. 5, 42,175 / 6,120)
= Rs. 88.60
Saving per unit = Rs. 98.75 – Rs. 88.60 = Rs. 10.15
(b) Saving in terms of direct worker cost per unit under Rowan Scheme: (Refer to Working Note 4)
Labour cost per unit under Rowan scheme = Rs. 5,78,764/6,120 units= Rs. 94.57
Saving per unit = Rs. 98.75 – Rs. 94.57 = Rs. 4.18
Solution 11.
(i) Calculation of Net Wages paid to Worker ‘R’ and ‘S’
Particulars R (Rs.) S (Rs.)
Basic Wages 15,000.00 30,000.00
Dearness Allowance (DA) (50% of Basic Wages) 7,500.00 15,000.00
Overtime Wages (Refer to Working Note 1) 4,500.00 ----
Gross Wages earned 27,000.00 45,000.00
Less: Provident Fund (7% × Rs. 15,000); (7.5% × Rs. 30,000) (1,050.00) (2,250.00)
Less: ESI (2% × Rs. 15,000); (2% × Rs. 30,000) (300.00) (600.00)
Net Wages paid 25,650.00 42,150.00
Calculation of ordinary wage rate per hour of Worker ‘R’ and ‘S’
R (Rs.) S (Rs.)
Gross Wages (Basic Wages + DA) (excluding overtime) 22,500.00 45,000.00
Employer’s contribution to P.F. and E.S.I. 1,350.00 2,850.00
23,850.00 47,850.00
Ordinary wages Labour Rate per hour 119.25 239.25
(Rs. 23,850 ÷ 200 hours); (Rs. 47,850 ÷ 200 hours)
Worker R
Working Note:
Normal Wages are considered as basic wages.
Over time = {2 x(Basic wage + D.A.) x 20hours } / 200hours
= 2 x ( Rs.22,500 / 200 ) x 20hours
= Rs. 4,500
Solution 12.
Particulars Nasik Satara
Hours worked 32 hr. 30 hr.
Conversion Costs Rs.5,408 Rs.4,950
Less: Overheads Rs.800 (Rs.25×32 hr.) Rs.750 (Rs.25×30 hr.)
Labour Cost Rs.4,608 Rs.4,200
(i)Finding of Normal wage rate:
Let Wage rate be Rs.R per hour, this is same for both the Nasik and Satara factory. Normal wage rate can be found out
taking total cost of either factory.
OR
Rs. 4,200 = 35 R
Or R = Rs. 120
Normal Wage = 30 hrs × Rs. 120 = Rs. 3,600
Solution 13:
Time Time Wages (Rs) Bonus(Rs) Total Wages (Rs) Earning Per Hour (Rs)
Allowed Taken Halsey* Rowan** Halsey Rowan Halsey Rowan
(1) (2) (3) = (2) x Rs (4) (5) (6) (7) (8) (9)
80 = (3) + (4) = (3) + (5) = (6)/(2) = (7)/(2)
24,960 24,960 19,96,800 - - 19,96,800 19,96,800 80.00 80.00
24,960 18,720 14,97,600 2,49,600 3,74,400 17,47,200 18,72,000 93.33 100.00
24,960 12,480 9,98,400 4,99,200 4,99,200 14,97,600 14,97,600 120.00 120.00
24,960 6,240 4,99,200 7,48,800 3,74,400 12,48,000 8,73,600 200.00 140.00
* Bonus under Halsey Plan = 50% of (Time Allowed – Time Taken) × Rate per hour
𝐓𝐢𝐦𝐞 𝐓𝐚𝐤𝐞𝐧
** Bonus under Rowan Plan = x Time Saved x Rate per Hour
𝐓𝐢𝐦𝐞 𝐀𝐥𝐥𝐨𝐰𝐞𝐝
Rowan scheme of bonus keeps checks on speed of work as the rate of incentive increases only upto 50% of time taken to
time allowed but the rate decreases as the time taken to time allowed comes below 50%. It provides incentives for
efficient workers for saving in time but also puts check on careless speed. On implementation of Rowan scheme, the
management of ADV Pvt. Ltd. would resolve issue of the slow speed work while maintaining the skill and precision
required maintaining the quality of product.
Solution 14:
Workings:
Calculation of bonus hours:
Time saved 150 hours Time saved 270 hours
For first 20% of time allowed i.e. 60 15 15
hours (25% of 60 hours) (25% of 60 hours)
For next 30% of time allowed i..e. 90 36 36
hours (40% of 90 hours) (40% of 90 hours)
For next 30% of time allowed i..e. 90 - 27
Solution 15:
Workings :
Computation of less productive hours
Actual hours worked (given) 5,75,000
Less : Unproductive training hours 18,000
Actual productive hours 5,57,000
Particulars (Rs)
Contribution foregone (as calculated above) 68,36,250
Recruitment cost 5,36,300
Selection cost 2,78,400
Training costs 4,25,000
Settlement cost due to leaving 7,18,800
Profit foregone 87,94,750
Alternatively, the Productive hours lost can be calculated as 1,25,000 hours (delay in vacancy) + 18000 hours
(unproductive training hours) = 1,43,000 hours. So,
𝐑𝐬 𝟏𝟐,𝟏𝟖,𝟒𝟗,𝟑𝟐𝟎
Sales lost for 1,43,000 hours will be x 1,43,000 hours = Rs 3,12,82,680. Therefore , contribution
𝟓,𝟓𝟕,𝟎𝟎𝟎 𝐡𝐨𝐮𝐫𝐬
𝐑𝐬 𝟑,𝟏𝟐,𝟖𝟐,𝟔𝟖𝟎
lost for 1,43,000 hours is x 25 = Rs 78,20,670 (instead of Rs 68,36,250). Accordingly , total profit
𝟏𝟎𝟎
foregone on account of labour turnover will be Rs 97,79,170.
Solution 16:
Workings:
Basic wage rate = Rs 100 per hour
Overtime wage rate before and after working hours = Rs 100 + (Rs 100 × 80%)
= Rs 180 per hour Overtime
wage rate for Sundays and holidays = Rs 100 + (Rs 100 × 150%)
= Rs 250 per hour
Wages for overtime before and after normal working hours (60,000 hrs. × 108,00,000
Rs 180)
Factory overhead = {400 hrs. × (Rs 100 × 80%)} + {100 hrs. × (Rs 100 × 150%)}
= {Rs 32,000 + Rs 15,000} = Rs 47,000
(c) Where overtime is worked at the request of the customer, overtime premium is also charged to the
job as under :
(Rs)
Job ‘Spinning’ Employee Cost : 4,500 hrs @ Rs 100 = 4,50,000
Overtime premium : 400 hrs. @(Rs 100 x 80%) = 32,000
100 hrs. @ (Rs 100 x 150%) = 15,000
Total = 4,97,000
Solution 19:
Calculation of total normal hours to be paid for Mr. Deep (Semi-skilled):
Day Normal Hours Extra Hours Overtime Hours Equivalent Total Normal
normal hours for hours
overtime
worked
A B C D=Cx2 E=A+B+D
Monday 8 1 1½ 3 12
Tuesday 8 --- --- --- 8
Wednesday 8 1 1½ 3 12
Thursday 8 1 1½ 1 10
Friday 8 1 1½ 3 12
Saturday --- --- --- --- ---
Total 40 4 5 10 54
Day Normal hours Extra hours Overtime hours Equivalent Total normal
normal hours for hours
overtime
worked
A B C D=Cx2 E=A+B+D
Monday 8 1 1½ 3 12
Tuesday 8 --- --- --- 8
Wednesday 8 1 1½ 3 12
Thursday 8 1 1½ 1 10
Friday 8 1 1½ 3 12
Saturday 5 3* + 1 1** 2 11
Total 45 8 6 12 65
*Mr. Sam will be paid for equivalent 8 normal working hours at ordinary wage rate, through 5 hours of working is
required on Saturday. Further, extra 9th hour worked will also be paid at ordinary wage rate.
** Overtime of 1 hour worked over and above 9 hours will be paid at overtime rate.
Wages payable:
Mr. Deep Mr. Sam
Basic Wages per hour (Rs 400/8, Rs 600/8) (Rs) 50 75
Dearness allowance per hour (@ 20%) (Rs) 10 15
Hourly rate (Rs) 60 90
Total equivalent normal hours 54 65
Total Wages payable (Rs) 3,240 5,850
Solution 20:
(i) Calculation of effective hourly rate of earnings under Rowan Incentives Plan:
Standard time allowed = 10 hours
Time taken = 8 hours, Time saved = 2 hours
Particulars Amount (Rs)
A Basic guaranteed wages (Rs 150 x 8 hours) 1,200
B Add: Bonus for time saved (2/10 x 8 x Rs 150) 240
C Total earnings (A + B) 1,440
D Hours worked 8 hours
E Effective Hourly rate (C÷D) 180
(ii) Let the time taken to complete the job is “T” and the time saved is 10-T
Effective hourly rate under the Halsey Incentive Scheme
= (Rate x Hours Worked) + (Rate x 50% of Time Saved) = Rs 180
Hours Worked
(Rs 150 x T) + Rs 150 x 50% (10 - T) = Rs 180
T
150T + 750 – 75T = 180T
180T – 75T = 750
T = 750 = 7.14 hours
105
Solution 21:
Particulars Noida Patparganj
Hours worked 36 hr. 33.75 hr.
Conversion Costs Rs 6,084 Rs 5,569
Less: Overheads Rs 900 Rs 844
(Rs 25 × 36 hr.) (Rs 25 × 33.75 hr.)
Labour Cost Rs 5,184 Rs 4,725
Or
Patparganj: Halsey Plan
Total Labour Cost = Wages for hours worked + Bonus as per Halsey plan
Rs 4,725 = Hours worked × Rate per hour + (50% × Hours saved × Rate per hour)
Rs 4,725 = 33.75 hr. × R + 50% × (45 hr. – 33.75 hr.) × R
Rs 4,725 = 39.375 R
R = Rs 120
Normal Wage = 33.75 hrs × Rs 120 = Rs 4,050
Solution 22:
(i) Computation of wages of each worker under guaranteed hourly rate basis
Actual Hours worked (Hours) Hourly wage rate (Rs) Wages (Rs)
Worker
M 380 90 34,200
N 100 100 10,000
O 540 110 59,400
(ii) Computation of wages of each worker under piece work earning basis
Piece rate per unit Worker-M Worker-N Worker-O
Product
(Rs)
Units Wages (Rs) Units Wages (Rs) Units Wages (Rs)
A 22.50 210 4,725 - - 600 13,500
B 30.00 360 10,800 - - 1,350 40,500
C 45.00 460 20,700 250 11,250 - -
Total 36,225 11,250 54,000
Since each worker’s earnings are more than 50% of basic pay. Therefore, worker-M, N and O will be paid the wages as
computed i.e. Rs 36,225, Rs 11,250 and Rs 54,000 respectively.
Working Notes:
1. Piece rate per unit
Product Standard time per unit (in Piece rate each minute Piece rate per unit (Rs)
minutes) (Rs)
A 15 1.5 22.50
B 20 1.5 30.00
C 30 1.5 45.00
(i) Computation of cost of running one machine for a four week period
(Rs) (Rs)
(A) Standing charges (per annum)
Rent 5,400
Heat and light 9,720
Forman’s salary 12,960
Other miscellaneous expenditure 18,000
Standing charges (per annum) 46,080
Total expenses for one machine for four week period
𝐑𝐬 𝟒𝟔, 𝟎𝟖𝟎 1,181.54
𝟑 𝐦𝐚𝐜𝐡𝐢𝐧𝐞𝐬 × 𝟏𝟑 𝐟𝐨𝐮𝐫 𝐰𝐞𝐞𝐤 𝐩𝐞𝐫𝐢𝐨𝐝𝐬
𝑹𝒔 𝟏𝟕,𝟓𝟏𝟑.𝟓𝟒
(ii) Machine hour rate = = Rs 99.51
𝟏𝟕𝟔 𝒉𝒐𝒖𝒓𝒔
Solution 2:
(i) Computation of percentage recovery rates of factory overheads and administrative overheads.
Let the factory overhead recovery rate as percentage of direct wages be F and administrative overheads recovery rate as
percentage of factory cost be A.
Factory Cost of Jobs: Direct materials + Direct wages + Factory overhead
For Job 101 = Rs 54,000 + Rs 42,000 + Rs 42,000F
For Job 102 = Rs 37,500 + Rs 30,000 + Rs 30,000F
Total Cost of Jobs:
Factory cost + Administrative overhead
For Job 101 = (Rs 96,000 + Rs 42,000F) + (Rs 96,000+ Rs 42,000F) A = Rs 1,51,500*
For Job-102 = (Rs 67,500 + Rs 30,000F) + (Rs 67,500+ Rs 30,000F) A = Rs 1,06,875**
Working Note:
𝐒𝐞𝐥𝐥𝐢𝐧𝐠 𝐩𝐫𝐢𝐜𝐞
Total Cost =
(𝟏𝟎𝟎% +𝐏𝐞𝐫𝐜𝐞𝐧𝐭𝐚𝐠𝐞 𝐨𝐟 𝐩𝐫𝐨𝐟𝐢𝐭)
𝐑𝐬 𝟏,𝟔𝟔,𝟔𝟓𝟎
* For Job 1 = = Rs 1,51,500
(𝟏𝟎𝟎% +𝟏𝟎%)
𝐑𝐬 𝟏,𝟐𝟖,𝟐𝟓𝟎
* For Job 1 = = Rs 1,06,875
(𝟏𝟎𝟎% +𝟐𝟎%)
(ii) Statement of jobs, showing amount of factory overheads, administrative overheads and profit
Particulars Job 101 (Rs) Job 102 (Rs)
Direct materials 54,000 37,500
Direct wages 42,000 30,000
Prime cost 96,000 67,500
Factory overheads
60% of direct wages 25,200 18,000
Factory cost 1,21,200 85,500
Administrative overheads
25% of factory cost 30,300 21,375
Total cost 1,51,500 1,06,875
Profit (10% and 20% respectively) 15,150 21,375
Selling price 1,66,650 1,28,250
Solution 3:
(a) Overhead Distribution Statement
Production Depts. Service Depts.
Machine shop Packing Gen. Plant Store &
Maintenance
(Rs) (Rs) (Rs) (Rs)
Allocated Expenses:
Indirect labour 4,000 3,000 2,000 5,650
Maintenance material 1,800 700 1,020 1,500
Misc. supplies 400 1,000 150 200
Superintendent’s salary - - 4,000
Cost & payroll salary - - 10,000 -
Total Allocated Overheads 6,200 4,700 17,170 7,350
Apportioned expenses (as 77,720 25,800 2,830 22,650
per schedule below)
Total overheads 83,920 30,500 20,000 30,000
Solution 4:
(i) Amount of under-absorption of production overheads during the year 2019-20
(Rs)
Total production overheads actually incurred during
the year 2019-20 6,00,000
Less: ‘Written off’ obsolete stores Rs 45,000
Wages paid for strike period Rs 30,000 75,000
Net production overheads actually incurred: (A) 5,25,000
Production overheads absorbed by 48,000 machine
hours @ Rs 10 per hour: (B) 4,80,000
Amount of under – absorption of production overheads:
(ii) Accounting treatment of under absorption of production overheads It is given in the statement of the
question that 20,000 units were completely finished and 8,000 units were 50% complete, one third of the
under-absorbed overheads were due to lack of production planning and the rest were attributable to
normal increase in costs.
(Rs)
1. (33 – 1/3% of Rs 45,000) i.e., Rs 15,000 of under-absorbed
overheads were due to lack of production planning.
This being abnormal, should be debited to the Costing
Profit and Loss A/c. 15,000
2. Balance (66–2/3% of Rs 45,000) i.e., Rs 30,000 of
Under - absorbed overheads should be distributed
over work-in-progress, finished goods and cost of
sales by using supplementary rate. 30,000
Total under-absorbed overheads 45,000
Apportionment of unabsorbed overheads of ₹ 30,000 over, work-in progress, finished goods and cost of sales
Equivalent (Rs)
Completed Units
Work-in-Progress
(4,000 units × Rs 1.25) 4,000 5,000
(Refer to working note)
Finished goods
(2,000 units × Rs 1.25) 2,000 2,500
Cost of sales
(18,000 units × Rs 1.25) 18,000 22,500
24,000 30,000
Working Note
Supplementary rate per unit = Rs 30,000 . = Rs 1.25
24,000
Solution 5:
(i) Computation of predetermined overhead rate for each production departments from budgeted data
Production Department Service Department
P1 P2 S1 S2
Budgeted factory overheads for the year in (Rs) 25,50,000 21,75,000 6,00,000 4,50,000
Working notes:
1.
Product A Product B Total
Budgeted output (in units) 50,000 30,000
Budgeted machine hours in Dept. P1 75,000 30,000 1,05,000
(50,000 x 1.5 hrs) (30,000 x 1 hr)
Budgeted labour hours in Dept. P2 1,00,000 75,000 1,75,000
(50,000 x 2 hrs) (30,000 x 2.5 hrs)
2.
Product A Product B Total
Actual output (in units) 4,000 3,000
Actual machine hours utilized in Dept. P1 6,100 4,150 10,250
3. Computation of actual overhead rates for each production department from actual data
Production Department Service Department
P1 P2 S1 S2
Actual factory overheads for the month of July, 25,50,000 21,75,000 6,00,000 4,50,000
2020 in (Rs)
Allocation of service Dept. S1’s costs to 30,000 30,000 (60,000) -
Solution 6:
Working Note:
Solution 7:
Computation of Machine Hour Rate
Machines
Basis of
Total (Rs) A (Rs) B (Rs) C (Rs)
Apportionment
(A) Standing Charges
Insurance Depreciation 80,000 30,000 30,000 20,000
Basis (3:3:2)
Indirect Labour Direct Labour 2,40,000 60,000 90,000 90,000
(2:3:3)
Building Floor Space 2,00,000 80,000 80,000 40,000
maintenance (2:2:1)
expenses
Rent and Rates Floor Space 2,40,000 96,000 96,000 48,000
(2:2:1)
Salary of foreman Equal 5,04,000 1,68,000 1,68,000 1,68,000
Salary of attendant Equal 1,44,000 48,000 48,000 48,000
Total standing 14,08,000 4,82,000 5,12,000 4,14,000
charges
Hourly rate for 247.43 262.83 212.53
standing charges
(B) Machine
Expenses:
Depreciation Direct 2,00,000 75,000 75,000 50,000
Spare parts Final estimates 1,32,250 46,000 57,500 28,750
Power K.W. rating 4,00,000 1,50,000 1,00,000 1,50,000
(3:2:3)
Consumable Stores Direct 80,000 30,000 25,000 25,000
Total Machine 8,12,250 3,01,000 2,57,500 2,53,750
expenses
Hourly Rate for 154.52 132.19 130.26
Machine expenses
Total (A + B) 22,20,250 7,83,000 7,69,500 6,67,750
Machine Hour rate 401.95 395.02 342.79
Working Notes:
(i) Calculation of effective working hours:
No. of full off-days = No. of Sunday + No. of holidays
= 52 + 12 = 64 days
No. of half working days = 52 days – 2 holidays = 50 days
No. of full working days = 365 days – 64 days – 50 days = 251 days
Total working Hours = {(251 days × 8 hours) + (50 days × 4 hours)}
= 2,008 hours + 200 = 2,208 hours.
Total effective hours = Total working hours × 90% - 2% for break-down
= 2,208 hours × 90% - 2% (2,208 hours × 90%)
= 1,987.2 hours – 39.74 hours
= 1947.46 or Rounded up to 1948 hours
2,40,000
(iv) Interest on capital outlay is a finance cost, therefore it has been excluded from the cost accounts.
Solution 8:
Primary Distribution Summary
Item of cost Basis of Total (Rs) P1 P2 P3 S1 S2
apportionment (Rs) (Rs) (Rs) (Rs) (Rs)
Direct wages Actual 2,50,000 -- -- -- 1,87,500 62,500
Rent and rates Floor area 6,25,000 1,25,000 1,56,250 1,87,500 1,25,000 31,250
(4 : 5 : 6 : 4 : 1)
General Light points 7,50,000 1,25,000 1,87,500 2,50,000 1,25,000 62,500
lighting (2 : 3 : 4 : 2 : 1)
Indirect wages Direct wages 1,87,500 56,250 37,500 56,250 28,125 9,375
(6 : 4 : 6 : 3 : 1)
Power Horse Power of 25,00,000 10,00,000 5,00,000 8,33,333 1,66,667 --
machines used
(6 : 3 : 5 : 1)
Depreciation of Value of 5,00,000 1,20,000 1,60,000 2,00,000 10,000 10,000
machinery machinery
(12:16:20:1:1)
Insurance of Value of 2,00,000 48,000 64,000 80,000 4,000 4,000
machinery machinery
(12:16:20:1:1)
50,12,500 14,74,250 11,05,250 16,07,083 6,46,292 1,79,625
P1 P2 P3
Total overheads cost (Rs) 17,07,131.4 13,55,883.5 19,49,485.1
Production hours worked 6,225 4,050 4,100
Rate per hour (Rs) 274.24 334.79 475.48
Production on overheads
P1 5 hours × Rs 274.24 = 1,371.20
Solution 9:
Working Notes:
(i) Total Productive hours = Estimated Working hours – Machine Maintenance hours = 2,200 hours – 200 hours =
2,000 hours
(ii) Depreciation per annum =(Rs 1,00,000- Rs 10,000) / 10 years = Rs 9000
(iii) Chemical solution cost per annum = Rs 200 × 50 weeks = Rs10,000
(iv) Wages of attendants (per annum) = (Rs 1,200 × 50 weeks) / 6 machines = Rs 10,000
B. Machine Expense
(iii) Depreciation 9,000 4.50
(iv) Electricity (Rs 0.9×16units×1,900hours) - 13.68
2,000hours
(v) Chemical solution 10,000 5.00
(vi) Maintenance cost 12,000 6.00
Machine operating cost per hour (A + B) 44.18
Solution 10:
Primary Distribution of Overheads
Item Basis Total Amount Production Departments Service Departments
(Rs) X (Rs) Y (Rs) Z (Rs) A (Rs) B (Rs)
Solution 11:
Workings:
Particulars Six months 6 operators (Hours)
Normal available hours per month (208 x 6 months x 6 operators) 7,488
Less: Absenteeism hours (18 x 6 operators) (108)
Paid hours (A) 7,380
Less: Leave hours (20 x 6 operators) (120)
Less: Normal idle time (10 x 6 operators) (60)
Effective working hours 7,200
Solution 12:
(i) Statement showing distribution of Overheads
Primary Distribution Summary
Item of cost Basis of Total P Q R X Y
apportionment (Rs) (Rs) (Rs) (Rs) (Rs) (Rs)
Production on overheads
P 6 hours x 3 = Rs 18
Note: Secondary Distribution can also be done using repeated distribution Method
Solution 13:
(i) Amount of over/ under absorption of production overheads during the period of first six months of the year
2019-20:
Amount (Rs) Amount (Rs)
Total production overheads actually incurred during the 34,08,000
period
Less: Amount paid to worker as per court order 4,50,000
Expenses of previous year booked in the current year 1,00,000
Wages paid for the strike period under an award 4,20,000
𝐑𝐬 𝟓𝟎,𝟒𝟎,𝟎𝟎𝟎
*Budgeted Machine hour rate (Blanket rate) = = Rs 840 per hour
𝟔,𝟎𝟎𝟎 𝐇𝐨𝐮𝐫𝐬
(ii) Accounting treatment of over absorbed production overheads: As, 40% of the over absorbed overheads were
due to defective production policies, this being abnormal, hence should be credited to Costing Profit and Loss
Account.
Amount to be credited to Costing Profit and Loss Account
= Rs 1,18,000 × 40% = Rs 47,200.
Balance of over absorbed production overheads should be distributed over Works in progress, Finished goods and Cost
of sales by applying supplementary rate*.
Amount to be distributed = Rs 1,18,000 × 60% = Rs 70,800
𝐑𝐬 𝟕𝟎,𝟖𝟎𝟎
Supplementary rate = = Rs 0.295 per Unit
𝟐,𝟒𝟎,𝟎𝟎𝟎 𝐮𝐧𝐢𝐭𝐬
(iii) Apportionment of over absorbed production overheads over WIP, Finished goods and Cost of sales:
Equivalent Amount (Rs)
completed units
Work-in-Progress (80,000 units × 50% × 0.472) 40,000 18,880
Finished goods (20,000 units × 0.472) 20,000 9,440
Cost of sales (90,000 units × 0.472) 90,000 42,480
Total 1,50,000 70,800
Solution 14:
Calculation of Machine Hour Rate:
Particulars Amount (Rs)
Solution 15:
(a) Computation of Machine Hour Rate
*Alternatively, Machine Hour rate can be calculated as total Cost ÷ total effective hours.
Working Notes :
(i) Calculation of effective working hours:
No. of off-days = No. of Sundays + No. of holidays
= 52 + 12 = 64 days
No. of working days = 365 days – 64 days = 301 days Total
working Hours = 301 days × 8 hours
= 2,408 hours
Total effective hours = Total working hours × 90%
= 2,408 hours × 90%
= 2,167.2 or Rounded up to 2,168 hours
Solution 16:
Primary Distribution Summary
Item of cost Basis of Total P1 P2 P3 S1 S2
apportionment (Rs) (Rs) (Rs) (Rs) (Rs) (Rs)
Direct wages Actual 5,00,000 -- -- -- 3,75,000 1,25,000
Rent and Floor area 12,50,000 2,50,000 3,12,500 3,75,000 2,50,000 62,500
Rates (4 : 5 : 6 : 4 : 1)
General Light points 1,50,000 25,000 37,500 50,000 25,000 12,500
lighting (2 : 3 : 4 : 2 : 1)
Indirect wages Direct wages 3,75,000 1,12,500 75,000 1,12,500 56,250 18,750
(6 : 4 : 6 : 3 :
1)
Power Horse Power of 5,00,000 2,00,000 1,00,000 1,66,667 33,333 -
machines used
(6 : 3 : 5 : 1)
Depreciation Value of 10,00,000 2,40,000 3,20,000 4,00,000 20,000 20,000
of machinery machinery (12 :
16 : 20 : 1 : 1)
Insurance Value of 4,00,000 96,000 1,28,000 1,60,000 8,000 8,000
o machinery (12 :
f machinery 16 : 20 : 1 : 1)
41,75,000 9,23,500 9,73,000 12,64,167 7,67,583 2,46,750
Solution 19:
(a) Primary Distribution of Overheads
Basis Total (Rs) A (Rs) B (Rs) X (Rs) Y (Rs)
Direct Direct 6,00,000 - - 4,00,000 2,00,000
materials
Direct Wages Direct 6,00,000 - - 2,00,000 4,00,000
Factory rent Area 9,00,000 3,00,000 1,50,000 1,50,000 3,00,000
(2:1:1:2)
Power H.P. x 5,10,000 1,50,000 2,40,000 45,000 75,000
(Machine) Machine Hrs.
(10:16:3:5)*
Depreciation Capital Value 2,00,000 50,000 1,00,000 25,000 25,000
(2:4:1:1)
General Light Points 3,00,000 60,000 1,20,000 60,000 60,000
Lighting
(1:2:1:1)
Perquisites Direct Wages 4,00,000 2,00,000 80,000 40,000 80,000
(5:2:1:2)
35,10,000 7,60,000 6,90,000 9,20,000 11,40,000
*{(1,000 x 50) : (2,000 x 40) : (1,000 x 15) : (1,000 x 25)}
(50,000 : 80,000 : 15,000 : 25,000)
(10 : 16 : 3 : 5)
(b) (i) Redistribution of Service Department’s expenses using ‘Simultaneous equation method’
X = 9,20,000 + 0.5Y
Y = 11,40,000 + 0.20X
Substituting the value of X,
Y = 11,40,000 + 0.20 (9,20,000 + 0.05 Y)
= 13,24,000 + 0.01Y
Y – 0.01 Y = 13,24,000
Y = 13,24,000 / 0.99
Y = Rs 13,37,374
The total expenses of Y is Rs 13,37,374 and that of X is Rs 9,86,869 i.e., Rs 9,20,000 + (0.05 x Rs 13,37,374)
Distribution of Service departments’ overheads to Production departments
Production Departments
A (Rs) B (Rs)
Overhead as per primary distribution 7,60,000 6,90,000
Dept- X (55% and 25% of Rs 9,86,869) 5,42,778 2,46,717
Dept- Y (60% and 35% of Rs 13,37,374) 8,02,424 4,68,081
21,05,202 14,04,798
(ii) Redistribution of Service Department’s expenses using ‘Trial and Error Method’:
Service Departments
X (Rs) Y (Rs)
Overheads as per primary distribution 9,20,000 11,40,000
(i) Apportionment of Dept-X expenses to Dept-Y (20% of Rs
9,20,000) --- 1,84,000
--- 13,24,000
(ii) Apportionment of Dept-Y expenses to Dept-X (5% of Rs
13,24,000) 66,200 ---
(i) Apportionment of Dept-X expenses to Dept-Y (20% of Rs
66,200) --- 13,240
(ii) Apportionment of Dept-Y expenses to Dept-X (5% of Rs 13,240) 662 ---
(i) Apportionment of Dept-X expenses to Dept-Y (20% of Rs 662) 132
(ii) Apportionment of Dept-Y expenses to Dept-X (5% of Rs 132) 7
Total 9,86,869 13,37,372
Production Departments
A (Rs) B (Rs)
Overhead as per primary distribution 7,60,000 6,90,000
Dept- X (55% and 25% of Rs 9,86,869) 5,42,778 2,46,717
Dept- Y (60% and 35% of Rs 13,37,372) 8,02,423 4,68,080
21,05,201 14,04,797
Solution 20:
(i) Amount of under-absorption of overheads during the year 2020-21
(Rs)
Total production overheads actually incurred during the year 2020- 35,50,000
21
Less: Wages paid during strike period Rs 2,00,000
Wages of previous year booked in current year Rs 1,00,000 3,00,000
Net production overheads actually incurred: (A) 32,50,000
Production overheads absorbed by 1.50 lakh man-days @ Rs 20 per man- 30,00,000
day: (B)
Amount of under-absorption of production overheads: [(A)–(B)] 2,50,000
(ii) Accounting treatment of under absorption of production overheads: It is given in the statement of the question
that 62,000 units (50,000 sold + 12,000 closing stock – 0 opening stock) were completely finished and 20,000 units
were 65% complete, 40% of the under-absorbed overheads were due to factory inefficiency and the rest were
attributable to increase in cost of indirect materials and indirect labour.
(Rs)
1. (40% of Rs 2,50,000) i.e. Rs 1,00,000 of under – absorbed overheads 1,00,000
were due to factory inefficiency. This being abnormal, should be
debited to the Costing Profit and Loss A/c
2. Balance (60% of Rs 2,50,000) i.e. Rs 1,50,000 of under – absorbed 1,50,000
overheads should be distributed over work-in- progress, finished goods
and cost of sales by using supplementary rate
Total under-absorbed overheads 2,50,000
Apportionment of unabsorbed overheads of Rs 1,50,000 over work-in-progress, finished goods and
cost of sales.
Equivalent (Rs)
Completed units
Work-in-progress (13,000 units × Rs 2) (Refer 20000 * 65% = 13,000 26,000
to Working Note)
Finished goods (12,000 units × Rs 2) 12,000 24,000
Cost of sales (50,000 units × Rs 2) 50,000 1,00,000
75,000 1,50,000
Journal Entry:
Work-in-progress control A/c Dr. Rs 26,000
Finished goods control A/c Dr. Rs 24,000
Solution 21:
Computation of machine hour rate of new machine
Total (Rs) Per Hour (Rs)
A. Standing Charges
I. Insurance Premium Rs 9,000 x 1/9 1,000
II. Rent 1/10 x Rs 2,400 x 12 months 2,880
3,880 0.97*
B. Machine expenses
I. Repairs & Maintenance (Rs 6,000 ÷ 4,000 hours) 1.50
II. Depreciation ((Rs 10,00,000 – Rs 10,000)/(10 years x 4,000 hours)) 24.75
III. Electricity (8 units x Rs 3.75) 30.00
Machine hour rate 57.22
Working note
Calculation of productive Machine hour rate
Total hours 4,200
Less: non-productive hours 200
Effective Machine Hours 4,000
* Rs 3,880 ÷ 4,000 hours = Rs 0.97
Solution 22:
Primary Distribution of Overheads
Item Basis Total Production Departments Service Departments
Amount
(Rs)
X (Rs) Y (Rs) Z (Rs) A (Rs) B (Rs)
Indirect Actual 5,00,000 80,000 1,20,000 1,80,000 1,00,000 20,000
Materials
Indirect Labour Actual 10,40,000 1,80,000 2,00,000 2,80,000 2,40,000 1,40,000
Supervisor’s Actual 3,84,000 - - 3,84,000 - -
Salary
Fuel & Heat Radiator 60,000 6,000 12,000 18,000 15,000 9,000
Sections
{2:4:6:5:3}
Power Kilowatt Hours 7,20,000 2,10,000 2,40,000 1,80,000 90,000 -
{7:8:6:3}
Rent & Rates Area (Sq. ft.) 6,00,000 1,76,000 1,60,000 1,20,000 96,000 48,000
{22:20:15:12:6}
Insurance Capital Value 72,000 16,000 24,000 20,000 4,000 8,000
of Assets
{4:6:5:1:2}
Canteen No. of 2,40,000 48,000 56,000 96,000 24,000 16,000
Charges employees
{6:7:12:3:2}
Depreciation Capital Value 10,80,000 2,40,000 3,60,000 3,00,000 60,000 1,20,000
of assets
{4:6:5:1:2}
Total 46,96,000 9,56,000 11,72,000 15,78,000 6,29,000 3,61,000
Overheads
a = 6,78,673
Putting the value of ‘a’ in equation (ii) we get
b = 3,61,000 + 0.20 x 6,78,673
b = 4,96,735
Secondary Distribution of Overheads
Production Departments
X (Rs) Y (Rs) Z (Rs)
Total overhead as per primary distribution 9,56,000 11,72,000 15,78,000
Service Department A (80% of 6,78,673) (3:3:2) 2,03,602 2,03,602 1,35,734
Service Department B (90% of 4,96,735) (5:8:5) 1,24,184 1,98,694 1,24,184
Total 12,83,786 15,74,296 18,37,918
Working Note
Activity Budgeted Cost Remark
(Rs)
ATM Services:
a) Machine Maintenance 4,00,000 All fixed, no change.
b) Rents 2,00,000 Fully fixed, no change.
c) Currency Replenishment Cost 2,00,000 Doubled during budget period
Total 8,00,000
Computer Processing 2,50,000 Rs 2,50,000 (half of Rs 5,00,000) is fixed and no
change is expected.
7,50,000 Rs 2,50,000 (variable portion) is expected to
increase to three times the current level.
Total 10,00,000
Issuing Statements 18,00,000 Existing
2,00,000 2 lakh statements are expected to be increased
in budgeted period. For every increase of one
lakh statement, one lakh rupees is the budgeted
increase.
Total 20,00,000
Computer Inquiries 3,60,000 Estimated to increase by 80% during the budget
period. (Rs 2,00,000 x 180%)
Total 3,60,000
Solution 2:
(i) Statement Showing “Cost per unit - Traditional Method”
Particulars of costs P Q R
(Rs) (Rs) (Rs)
Direct Materials 90 80 120
Direct Labour [(4, 12, 8 hours) × Rs 20] 80 240 160
Production Overheads [(10, 18, 14 hours) × Rs 6] 60 108 84
Cost per unit 230 428 364
Workings
Number of Batches, Purchase Orders, and Inspections-
Particulars P Q R Total
A. Production (units) 3,000 5,000 20,000
B. Batch Size (units) 150 500 1,000
C. Number of Batches (A÷B) 20 10 20 50
D. Number of Purchase Order per batch 3 10 8
E. Total Purchase Orders [C × D] 60 100 160 320
F. Number of Inspections per batch 5 4 3
G. Total Inspections [C × F] 100 40 60 200
Solution 3:
(i) Statement of Operating income and Operating income as a percentage of revenues for each product line
(When support costs are allocated to product lines on the basis of cost of goods sold of each product)
Soft drinks (Rs) Fresh produce Packaged food Total (Rs)
(Rs) (Rs)
Revenues (A) 39,67,500 1,05,03,000 60,49,500 2,05,20,000
Cost of goods sold (COGS) (B) 30,00,000 75,00,000 45,00,000 1,50,00,000
Support cost (30% of COGS) (C) 9,00,000 22,50,000 13,50,000 45,00,000
(Refer working notes)
Total cost: (D) = {(B) + (C)} 39,00,000 97,50,000 58,50,000 1,95,00,000
Operating income: E= {(A)-(D)} 67,500 7,53,000 1,99,500 10,20,000
Operating income as a percentage of 1.70% 7.17% 3.30% 4.97%
revenues:
(E/A) × 100
Working notes:
1. Total support Cost:
(Rs)
Bottles returns 60,000
Ordering 7,80,000
Delivery 12,60,000
Shelf stocking 8,64,000
Customer support 15,36,000
Total support cost 45,00,000
𝐑𝐬 𝟒𝟓,𝟎𝟎,𝟎𝟎𝟎
= x 100 = 30%
𝐑𝐬 𝟏,𝟓𝟎,𝟎𝟎,𝟎𝟎𝟎
(ii) Statement of Operating income and Operating income as a percentage of revenues for each product line
(When support costs are allocated to product lines using an activity based costing system)
Soft drinks (Rs) Fresh produce Packaged food Total (Rs)
(Rs) (Rs)
Solution 4:
(i) Traditional Absorption Costing
BABYSOFT- BABYSOFT- BABYSOFT- Total
Gold Pearl Diamond
(a )Production of soaps (Units) 4,000 3,000 2,000 9,000
(b) Direct labour (minutes) 30 40 60 -
(c) Direct labour hours 2,000 2,000 2,000 6,000
(a × b)/60 minutes
Overhead rate per direct labour hour:
= Budgeted overheads ÷ Budgeted labour hours
= Rs 1,98,000 ÷ 6,000 hours
= Rs 33 per direct labour hour
Unit Costs:
BABYSOFT- Gold BABYSOFT- Pearl BABYSOFT- Diamond
(Rs) (Rs) (Rs)
Direct Costs: 5.00 6.67 10.00
- Direct Labour (𝟏𝟎 × 𝟑𝟎) (𝟏𝟎 × 𝟒𝟎) (𝟏𝟎 × 𝟔𝟎)
𝟔𝟎 𝟔𝟎 𝟔𝟎
- Direct Material 167.50 215.50 248.50
(Refer working
note1)
16.50 22.00 33.00
- Production (𝟑𝟑 × 𝟑𝟎) (𝟑𝟑 × 𝟒𝟎) (𝟑𝟑 × 𝟔𝟎)
Overhead: 𝟔𝟎 𝟔𝟎 𝟔𝟎
Total units costs 189.00 244.17 291.50
Number of units 4,000 3,000 2,000
Total Costs 7,56,000 7,32,510 5,83,000
Working note-1
Calculation of Direct material cost
BABYSOFT- Gold BABYSOFT- Pearl BABYSOFT- Diamond
(Rs) (Rs) (Rs)
Essential Oils 120.00 165.00 195.00
(𝟐𝟎𝟎 × 𝟔𝟎) (𝟑𝟎𝟎 × 𝟓𝟓) (𝟑𝟎𝟎 × 𝟔𝟓)
𝟏𝟎𝟎 𝟏𝟎𝟎 𝟏𝟎𝟎
Cocoa Butter 40.00 40.00 40.00
(𝟐𝟎𝟎 × 𝟐𝟎) (𝟐𝟎𝟎 × 𝟐𝟎) (𝟐𝟎𝟎 × 𝟐𝟎)
𝟏𝟎𝟎 𝟏𝟎𝟎 𝟏𝟎𝟎
Filtered Water 4.50 4.50 4.50
(iii) Comments: The difference in the total costs under the two systems is due to the differences in the overheads
borne by each of the products. The Activity Based Costs appear to be more accurate.
Solution 5:
(i) Profit Statement using Absorption costing method:
Particulars PRODUCT Total
X Y Z
A. Sales Quantity 1,00,000 80,000 60,000 2,40,000
B. Selling price per unit 90 180 140
(Rs)
C. Sales Value (Rs) [A×B] 90,00,000 1,44,00,000 84,00,000 3,18,00,000
D. Direct cost per unit (Rs) 50 90 95
E. Direct Cost (Rs) [A×D] 50,00,000 72,00,000 57,00,000 1,79,00,000
F. Overheads:
(i) Machine department 24,00,000 25,60,000 24,00,000 73,60,000
(Rs) (Working note-1)
Working Notes:
1.
Products
X Y Z Total
A. Production (units) 1,00,000 80,000 60,000
B. Machine hours per 3 4 5
unit
C. Total Machine hours 3,00,000 3,20,000 3,00,000 9,20,000
[A×B]
D. Rate per hour (Rs) 8 8 8
Products
X Y Z Total
A. Machining hours 3,00,000 3,20,000 3,00,000 9,20,000
(Refer Working note-1)
B. Machine hour rate (Rs) 7 7 7
(Refer Working note-2)
C.Machining services cost 21,00,000 22,40,000 21,00,000 64,40,000
(Rs) [A×B]
D. Labour hours 6,00,000 3,20,000 1,80,000 11,00,000
(Refer Working note-1)
E. Labour hour rate (Rs) 4 4 4
(Refer Working note-2)
F. Assembly services cost 24,00,000 12,80,000 7,20,000 44,00,000
(Rs) [D×E]
G. Machine set-ups 4,500 3,000 1,500 9,000
H. Rate per set-up (Rs) 100 100 100
(Refer Working note-2)
I. Set-up cost (Rs) [G×H] 4,50,000 3,00,000 1,50,000 9,00,000
J. Customer orders 2,200 2,400 2,600 7,200
K. Rate per order (Rs) 100 100 100
(Refer Working note-2)
L. Order processing cost (Rs) 2,20,000 2,40,000 2,60,000 7,20,000
[J×K]
M. Purchase orders 300 350 150 800
N. Rate per order (Rs) 500 500 500
(Refer Working note-2)
O. Purchasing cost (Rs) 1,50,000 1,75,000 75,000 4,00,000
[M×N]
Solution 6:
(i) Calculation of cost driver rate:
To get the best out of these notes visit www.edu91.org
Join Us on YouTube www.youtube.com/neerajarora
Join Us on Telegram https://t.me/neerajaroraclasses
EDU91 | Where Learning Happens BY CA NITIN GURU
Cost pool Budgeted overheads (Rs) Cost driver Cost driver rate (Rs)
Material procurement 18,42,000 1,200 1,535.00
Material handling 8,50,000 1,240 685.48
Maintenance 24,56,000 17,550 139.94
Set-up 9,12,000 1,450 628.97
Quality control 4,42,000 1,820 242.86
Solution 7:
Working Notes:
(i) Total support cost:
(Rs)
Bottles returns 60,000
Ordering 7,80,000
Delivery 12,60,000
Shelf stocking 8,64,000
Customer support 15,36,000
Total support cost 45,00,000
Solution 8:
(a) Computation showing Rates for each Activity
Activity Activity Cost Activity driver Activity Activity Rate
(Rs) Capacity (A/B)
(A) (B)
Marketing Expenses 2,25,000 Number of Customer Contacts 7,50,000 0.30
Website Maintenance Expenses 1,50,000 Number of Customer Online Orders 6,00,000 0.25
Credit Card Processing Fees 1,35,000 Number of Credit card Transactions 2,70,000 0.50
(i) Statement of Operating Income and Operating Income percentage for each Department
Particulars Premium Recliner 7D Hall Cafeteria (Rs)
Hall Hall (Rs)
(Rs) (Rs)
(ii) Contention of Supervisor is valid as operating income of Cafeteria is negative i.e. (Rs 63,000) or percentage of
profit/loss is (12%).
Solution 9:
(i) Total Overhead = Rs (2,52,000 + 80,000 + 60,000 + 40,000 + 10,368) = Rs 4,42,368
Total machine hours = 1,440 × 4 + 1,200 × 3 + 960 × 2 + 1,008 × 1
= 5,760 + 3,600 + 1,920 + 1,008 = 12,288 M. Hrs.
Overhead recovery rate / M.H. = Rs 4,42,368 / 12,288 M.Hrs. = Rs 36
Cost Statement when overheads are absorbed on machine hours rate basis –
Product A B C D
Output in units 1,440 1,200 960 1,008
(Rs) (Rs) (Rs) (Rs)
Cost per unit:
Direct material 84 90 80 96
Direct labour 20 18 14 16
Overhead (@ Rs 36) 144 108 72 36
(4 × Rs 36) (3 × Rs 36) (2 × Rs 36) (1 × Rs 36)
Total cost per unit 248 216 166 148
Total cost 3,57,120 2,59,200 1,59,360 1,49,184
(ii)
(1) Machine department costs of Rs 2,52,000 to be apportioned to set-up cost, store receiving and inspection in 4 : 3 : 2
i.e. Rs 1,12,000, Rs 84,000 and Rs 56,000 respectively.
(2) One production run = 48 units. Hence, the number of production runs of different products:
A= 1440 / 48 = 30 , B = 1200/48 = 25 , C= 960/ 48 =20 , D = 1,008/48 = 21 or total 96 runs.
(3) One batch order is of 24 units. So the number of batches of different products:
A= 1440 / 24 = 60 , B = 1200/24 = 50 , C= 960/ 24 =40 , D = 1,008/24 = 42 or total 192 batches.
Total cost per unit (Total cost 193.75 202.75 196.25 212.46
/ Output
Solution 10:
Traditional Absorption Costing
X Y Z Total
(a) Quantity (units) 1,200 1,440 1,968 4608
Unit Costs :
X Y Z
Direct Costs:
Solution 11:
(i) Calculation Cost-Driver’s rate
Activity Overhead cost Cost-driver level Cost driver rate (Rs)
(Rs)
(A) (B) (C) = (A)/(B)
Solution 12:
Working note:
Computation of revenues (at listed price), discount, cost of goods sold and customer level operating activities costs:
Customers
Particular A B C D E
Cases sold: (a) 9,360 14,200 62,000 38,000 9,800
Revenues (at listed price) (Rs): (b) {(a) × 5,05,440 7,66,800 33,48,000 20,52,000 5,29,200
Rs 54)}
Discount (Rs): (c) {(a) × Discount per - 8,520 3,10,000 1,44,400 52,920
case} (14,200 (62,000 (38,000 (9,800
cases × cases × cases × cases ×
Rs 0.6) Rs 5) Rs 3.80) Rs 5.40)
Cost of goods sold (Rs): (d) 4,21,200 6,39,000 27,90,000 17,10,000 4,41000
{(a) × Rs 45}
Customer level operating activities costs
Order taking costs (Rs): (No. of purchase × 6,000 10,000 12,000 10,000 12,000
Rs 200)
Customer visits costs 1,200 1,800 3,600 1,200 1,800
(Rs) (No. of customer visits × Rs 300)
Delivery vehicles travel costs (Rs) (Kms 3,200 2,880 4,800 6,400 9,600
travelled by delivery vehicles × Rs 4 per
km.)
(ii) Comments
Customer D in comparison with Customer C: Operating income of Customer D is more than of Customer C, despite
having only 61.29% (38,000 units) of the units volume sold in comparison to Customer C (62,000 units). Customer C
receives a higher percent of discount i.e. 9.26% (Rs 5) while Customer D receive a discount of 7.04% (Rs 3.80). Though
the gross margin of customer C (Rs 2,48,000) is more than Customer D (Rs 1,97,600) but total cost of customer level
operating activities of C (Rs 1,44,400) is more in comparison to Customer D (Rs 93,600). As a result, operating income
is more in case of Customer D.
Customer E in comparison with Customer A: Customer E is not profitable while Customer A is profitable. Customer E
receives a discount of 10% ( Rs 5.4) while Customer A doesn’t receive any discount. Sales Volume of Customer A and E is
almost same. However, total cost of customer level operating activities of E is far more ( Rs 43,200) in comparison to
Customer A (Rs 29,120). This has resulted in occurrence of loss in case of Customer E.
Solution 13:
Working notes:
1. Total support cost:
(Rs)
Bottles returns 60,000
Ordering 7,80,000
Delivery 12,60,000
Shelf stocking 8,64,000
Customer support 15,36,000
Total support cost 45,00,000
Activity (1) Total cost Cost allocation base (3) Cost driver rate (4) =
(Rs) [(2) ÷ (3)]
(2)
(i) Statement of Operating income and Operating income as a percentage of revenues for each product line
(When support costs are allocated to product lines on the basis of cost of goods sold of each product)
(ii) Statement of Operating income and Operating income as a percentage of revenues for each product line
(When support costs are allocated to product lines using an activity -based costing system)
Soft drinks Fresh Packaged Total
(Rs) Produce Food (Rs)
(Rs) (Rs)
Solution 15:
(i) PCP Limited’s
Statement of operating income and gross margin percentage for each of its supermarket segments
Particulars Supermarket A Supermarket B Total
Revenues: (Rs) 11,21,67,000 9,52,87,500 20,74,54,500
(660 × Rs 1,69,950) (1,650 × Rs 57,750)
Less: Cost of goods sold: (Rs) 10,89,00,000 9,07,50,000 19,96,50,000
(660 × Rs 1,65,000) (1650 × RS 55,000)
Gross Margin: (Rs) 32,67,000 45,37,500 78,04,500
Less: Other operating costs: (Rs) 16,55,995
Operating income: (Rs) 61,48,505
Gross Margin 2.91% 4.76 % 3.76%
Operating income % 2.96%
(ii) Operating Income Statement of each distribution channel in April (Using the Activity based Costing information)
Supermarket A Supermarket B
Gross margin (Rs) : (A) 32,67,000 45,37,500
(Refer to (i) part of the answer)
Operating cost (Rs): (B) (Refer to 6,55,600 10,00,395
working note)
Operating income (Rs): (A–B) 26,11,400 35,37,105
Operating income (in %) (Operating income/Revenue) 2.33 3.71
×100
Working note:
Computation of rate per unit of the cost allocation base for each of the five activity areas for the month of April
(Rs)
Store delivery 100 per delivery
[Rs 3,90,500/ (1,100 + 2,805 store deliveries)]
Cartons dispatched 1 per carton dispatch
[Rs 4,15,250/ {(250×1,100) +( 50×2,805)} carton dispatches]
Shelf-stocking at customer store (Rs) 6 per hour
[Rs 64,845/ {(6×1,100) + (1.5×2,805)} hours]
Line item ordering 10 per line item order
[Rs 3,45,400/ {(14×770) + (12×1,980)} line items]
Customer purchase order processing [Rs 4,40,000/ (770 + 1,980 orders)] 160 per order
Solution 16:
(i) (a) Statement of Operating Income and Operating Income as a percentage of revenues for each product
line. (When support costs are allocated to product lines on the basis of cost of goods sold for each product).
Drug A (Rs) Drug B (Rs) Drug C (Rs) Total (Rs)
Revenues: (A) 74,50,000 1,11,75,000 1,86,25,000 3,72,50,000
Cost of goods sold (COGS) (B): 41,44,500 68,16,750 1,20,63,750 2,30,25,000
Support cost (40% of COGS) 16,57,800 27,26,700 48,25,500 92,10,000
(C):
(Refer working notes)
Total Cost (D) – {(B) + (C)} 58,02,300 95,43,450 1,68,89,250 3,22,35,000
Operating income: E = {(A) – 16,47,700 16,31,550 17,35,750 50,15,000
(D)}
Operating Income as a % of 22.12% 14.60% 9.32% 13.46%
revenues: (E/A) x 100)
Working Notes:
1. Total Support cost
Rs
Drug License Fee 5,00,000
Ordering 8,30,000
Delivery 18,20,000
Shelf stocking 32,40,000
Customer Support 28,20,000
Total support cost 92,10,000
(b) Statement of operating Income and operating income as a percentage of revenues for each
product line
(When support costs are allocated to product lines using an activity-based costing system)
(b) When support costs are allocated to product lines using an activity-based costing system.
Drug A (Rs) Drug B (Rs) Drug C (Rs) Total (Rs)
Operating 8.81% 12.71% 15.78% 13.46%
Income as a % of
revenues
On comparing the operating income as a % of revenue of each product, Drug C is the most
profitable product line, though its unit sold is least but with highest revenue.
Solution 17:
Working note:
Computation of revenues (at listed price), discount, and cost of goods sold and customer level operating activities costs:
Particulars Customers
Aey Bee Cee Dee Eey
Cases sold: (a) 9,360 14,200 62,000 38,000 9,800
Revenues (at listed price) (Rs): (b) {(a) x Rs 64.80} 6,06,528 9,20,160 40,17,600 24,62,400 6,35,040
Discount (Rs): (c) {(a) x Discount per case} - 10,224 3,72,000 1,73,280 63,504
(14,200 (62,000 (38,000 (9,800
cases x cases x cases x Rs cases x Rs
Rs 0.72) Rs 6) 4.56) 6.48)
Cost of goods sold (Rs): (d) {(a) x Rs 54} 5,05,440 7,66,800 33,48,000 20,52,000 5,29,200
Customer level operating activities costs
Order taking costs (Rs): 7,200 12,000 14,400 12,000 14,400
(No. of purchase x Rs 240)
Customer visits costs (Rs) (No. of customer visits x 1,440 2,160 4,320 1,440 2,160
Rs 360)
Delivery vehicles travel costs (Rs) (Km. travelled by 3,840 3,456 5,760 7,680 11,520
delivery vehicles x 4.80 per km.)
Product handling costs (Rs) 22,464 34,080 1,48,800 91,200 23,520
{(a) x Rs 2.40}
Cost of expediting deliveries (Rs) - - - - 240
(ii) Comments
Customer Dee in comparison with Customer Cee: Operating income of Customer Dee is more than that of
Customer Cee, despite having only 61.29% (38,000 units) of the units volume sold in comparison to Customer
Cee (62,000 units). Customer Cee receives a higher percent of discount i.e. 9.26% (Rs 6) while Customer Dee
receives a discount of 7.04% (Rs 4.56). Though the gross margin of customer Cee (Rs 2,97,600) is more than that
of Customer Dee (Rs 2,37,120) but total cost of customer level operating activities of Cee (Rs 1,73,280 ) is more
in comparison to Customer Dee (Rs 1,12,320). As a result, operating income is more in case of Customer Dee.
Customer Eey in comparison with Customer Aey: Customer Eey is not profitable while Customer Aey is
profitable. Customer Eey receives a discount of 10% (Rs 6.48) while Customer Aey doesn’t receive any discount.
Sales Volume of Customer Aey and Eey is almost same. However, total cost of customer level operating
activities of Eey is far more (Rs 51,840) in comparison to Customer Aey (Rs 34,944). This has resulted in
occurrence of loss in case of Customer Eey.
Solution 18:
(i) Profit Statement using Absorption costing method:
Particulars Product Total
X Y Z
A. Sales Quantity 1,00,000 80,000 60,000 2,40,000
B. Selling price per unit (Rs) 45 90 70
C. Sales value (Rs) [AxB] 45,00,000 72,00,000 42,00,000 1,59,00,000
D. Direct Cost per unit (Rs) 25 45 50
E Direct Cost (Rs) [A x D] 25,00,000 36,00,000 30,00,000 91,00,000
F. Overheads:
(i) Machine department (Rs) 12,00,000 12,80,000 12,00,000 36,80,000
(Working Note-1)
(ii) Assembly Department (Rs) 15,00,000 8,00,000 4,50,000 27,50,000
(Working Note-1)
G. Total Cost (Rs) [E+F] 52,00,000 56,80,000 46,50,000 1,55,30,000
H. Profit (C-G) (7,00,000) 15,20,000 (4,50,000) 3,70,000
Working Notes:
(1)
Product Total
X Y Z
A. Production (Units) 1,00,000 80,000 60,000
B. Machine hours per unit 3 4 5
C. Total Machine hours [A x B] 3,00,000 3,20,000 3,00,000 9,20,000
D. Rate per hour (Rs) 4 4 4
E. Machine Dept. Cost [C x D] 12,00,000 12,80,000 12,00,000 36,80,000
F. Labour Hours per unit 6 4 3
G. Total Labour Hours [A x F] 6,00,000 3,20,000 1,80,000 11,00,000
H. Rate per Hour (Rs) 2.5 2.5 2.5
I. Assembly Dept. Cost [G x H] 15,00,000 8,00,000 4,50,000 27,50,000
Note: GST paid on purchase of raw materials would not be part of cost of materials as it is eligible for input tax credit.
Solution 2:
Cost sheet of Aditya Industries for month of……
Units produced- 1,94,000
Units sold- 1,60,000
Particulars Amount(Rs) Cost per unit (Rs)
Raw materials purchased 1,44,00,000
Add: Opening value of raw materials 12,00,000
Less: Closing value of raw materials (14,00,000)
Materials consumed 1,42,00,000 73.19
Wages paid to production workers 36,64,000 18.89
Expenses paid for utilities 1,45,600 0.75
Prime Cost 1,80,09,600 92.83
Factory overheads (Rs 8 × 21,600 hours) 1,72,800
Add: Opening value of W-I-P 18,00,000
Less: Closing value of W-I-P (16,04,000)
Cost of Production 1,83,78,400 94.73
Add: Value of opening finished stock 9,60,000
Less: Value of closing finished stock (Rs 94.73 × 44,000) (41,68,120)
Cost of Goods Sold 1,51,70,280 94.81
Office and administration expenses paid 26,52,000 16.58
Travelling allowance paid to office staffs 1,21,000 0.75
Selling expenses 6,46,000 4.04
Cost of Sales 1,85,89,280 116.18
Add: Profit 32,80,461 20.50
2,18,69,741 136.68
Solution 3:
Statement of Cost of RTA Ltd. for the year ended 31st December, 2020:
PARTICULARS Amount (Rs.) Amount (Rs.)
(i) Material Consumed:
-Raw materials purchased 5,00,00,000
-Freight inward 9,20,600
Add: Opening stock of raw materials 10,00,000
Solution 4:
Statement of Cost of R Ltd. for the year ended 31st March, 2020:
Particulars
Material Consumed:
- Raw materials purchased 84,00,000
- Carriage inward 1,72,600
Add: Opening stock of raw materials 6,20,000
Less: Closing stock of raw materials (4,60,000) 87,32,600
Direct employee (labour) cost:
- Direct wages 60,00,000
- Employer’s Contribution towards PF 7,20,000 67,20,000
& ESIS
Direct expenses:
- Consumable materials 4,80,000
- Cost of power & fuel 28,00,000 32,80,000
Prime Cost 8,40,000 1,87,32,600
Works/ Factory overheads:
- Wages to foreman and store keeper
- Other indirect wages to factory staffs
1,35,000 9,75,000
Gross factory cost 1,97,07,600
Add: Opening value of W-I-P 7,84,000
Less: Closing value of W-I-P (6,64,000)
Factory Cost 1,98,27,600
Research & development cost paid for 9,60,000
improvement in production process
Production planning office expenses 12,60,000
Cost of Production 2,20,47,600
Add: Opening stock of finished goods 14,40,000
Less: Closing stock of finished goods (9,80,000)
Cost of Goods Sold 2,25,07,600
Administrative overheads:
- Salary to accountants 7,20,000
- Fees to statutory auditor 1,80,000
- Fees to cost auditor 80,000
- Fee paid to independent directors 9,40,000 19,20,000
Selling overheads& Distribution
overheads:
- Salary to delivery staffs 14,30,000
Solution 5:
Calculation of Cost of Production of Arnav Metallic Ltd. for the period…..
Particulars Amount (Rs.)
Raw materials purchased 64,00,000
Add: Opening stock 2,88,000
Less: Closing stock (4,46,000)
Material consumed 62,42,000
Wages paid 23,20,000
Prime cost 85,62,000
Repair and maintenance cost of plant & machinery 9,80,500
Insurance premium paid for plant & machinery 96,000
Quality control cost 86,000
Research & development cost 92,600
Administrative overheads related with factory and production 9,00,000
1,07,17,100
Add: Opening value of W-I-P 4,06,000
Less: Closing value of W-I-P (6,02,100)
1,05,21,000
Less: Amount realised by selling scrap (9,200)
Add: Primary packing cost 10,200
Cost of Production 1,05,22,000
Notes:
(i) Other administrative overhead does not form part of cost of production.
(ii) Salary paid to Director (Technical) is an administrative cost.
Solution 6:
(i) Calculation of Factory overhead rate.
If the single brand production was in operation, then
1 unit of Luxury = 3 units of Herbal = 6 units of Beauty. Therefore, the factory overhead ratio in the reverse order would
be 5,000:15,000:30,000 or 1:3:6.
The overhead rate will be lowest in case of brand which will be produced in high number. Therefore, in case of Beauty
soap brand, the overhead rate will be:
= 80,000 / (6 x 6,750 + 3 x 14,000 + 1 x 77,500)
= 80,000 / (40,500 + 42,000 + 77,500)
= 80,000 / 1,60,000 = 0.5
Solution 7:
Statement of Cost of A Ltd. for the year ended 31st March, 2021:
Sl. No. Particulars Amount (Rs.) Amount (Rs.)
(i) Material Consumed:
- Raw materials purchased 10,00,00,000
- Freight inward 11,20,600
Add: Opening stock of raw materials 18,00,000
Less: Closing stock of raw materials (9,60,000) 10,19,60,600
(ii) Direct employee (labour) cost:
- Wages paid to factory workers 29,20,000
(iii) Direct expenses:
- Royalty paid for production 1,72,600
- Amount paid for power & fuel 4,62,000
- Job charges paid to job workers 8,12,000 14,46,600
Prime Cost 10,63,27,200
(iv) Works/ Factory overheads:
- Stores and spares consumed 1,12,000
- Repairs & Maintenance paid for plant & machinery 48,000
- Insurance premium paid for plant & machinery 31,200
- Insurance premium paid for factory building 18,100
- Expenses paid for pollution control and engineering &
maintenance 26,600 2,35,900
Gross factory cost 10,65,63,100
Add: Opening value of W-I-P 9,20,000
Less: Closing value of W-I-P (8,70,000)
Factory Cost 10,66,13,100
(v) Quality control cost:
- Expenses paid for quality control check activities 19,600
(vi) Research & development cost paid for improvement in production 18,200
process
(vii) Less: Realisable value on sale of scrap and waste (86,000)
(viii) Add: Primary packing cost 96,000
Cost of Production 10,66,60,900
Add: Opening stock of finished goods 11,00,000
Less: Closing stock of finished goods (18,20,000)
Cost of Goods Sold 10,59,40,900
(ix) Administrative overheads:
- Depreciation on office building 56,000
- Salary paid to General Manager 12,56,000
- Fee paid to independent directors 2,20,000 15,32,000
(x) Selling overheads:
- Repairs & Maintenance paid for sales office building 18,000
- Salary paid to Manager- Sales & Marketing 10,12,000
- Performance bonus paid to sales staffs 1,80,000 12,10,000
(xi) Distribution overheads:
- Packing cost paid for re-distribution of finished goods 1,12,000
Cost of Sales 10,87,94,900
Solution 8:
Cost Sheet for the Month of April 2020
Particulars (Rs.)
Opening stock of Raw Material 20,000
Working Note:
1. Computation of the raw material consumed
Particulars (Rs.)
Cost of Sales 4,00,000
Less: General and administration expenses (18,000)
Less: Selling expenses (22,000)
Cost of goods sold 3,60,000
Add: Closing stock of finished goods 60,000
Less: Opening stock of finished goods (50,000)
Cost of production/Gross works cost 3,70,000
Add: Closing stock of work-in-progress 30,000
Less: Opening stock of work-in-progress (20,000)
Works cost 3,80,000
Less: Factory Overheads ( Rs.1,20,000 / 120) × 100 (1,00,000)
Prime cost 2,80,000
Less: Direct labour (1,20,000)
Raw material consumed 1,60,000
Solution 9:
Preparation of Cost Sheet for Super Pen
No. of units produced = 40,000 units No. of units sold = 36,000 units
Particulars Per unit (Rs.) Total (Rs.)
Direct materials (Working note- (i)) 8.00 3,20,000
Direct wages (Working note- (ii)) 4.00 1,60,000
Prime cost 12.00 4,80,000
Production overhead (Working note- (iii)) 1.20 48,000
Factory Cost 13.20 5,28,000
Administration Overhead* (200% of direct wages) 8.00 3,20,000
Cost of production 21.20 8,48,000
Less: Closing stock (40,000 units – 36,000 units) - (84,800)
Cost of goods sold i.e. 36,000 units 21.20 7,63,200
Selling cost 1.00 36,000
Cost of sales/ Total cost 22.20 7,99,200
Profit 7.80 2,80,800
Sales value (Rs. 30 × 36,000 units) 30.00 10,80,000
Working Notes:
(i) Direct material cost per unit of Normal pen = M
(iii) Production overhead per unit = Rs.1,92,000 / (40,000 + 1,20,000) = Rs. 1.20
Production overhead for Super pen = Rs. 1.20 × 40,000 units = Rs. 48,000
* Administration overhead is specific to the product as it is directly related to direct labour as mentioned in the question
and hence to be considered in cost of production only.
Assumption: It is assumed that in point (1) and (2) of the Question, direct materials cost and direct wages respectively is
related to per unit only.
Note: Direct Material and Direct wages can be calculated in alternative ways.
Solution 10:
Workings:
1. Calculation of Sales Quantity:
Particular Units
Production units 1,00,000
Less: Defectives (4%×1,00,000 units) 4,000
Less: Closing stock of finished goods 5,000
No. of units sold 91,000
6. Calculation of Cost of Materials Consumed & Labour cost Let Cost of Material Consumed = M and Labour cost = 0.5M
Prime Cost = Cost of Material Consumed + Labour Cost 78,00,000 = M + 0.5M
M = 52,00,000
Therefore, Cost of Material Consumed = Rs. 52,00,000 and Labour Cost = Rs. 26,00,000
Cost Sheet
Sl. Particulars Total Cost (Rs.)
1. Direct materials consumed:
Opening Stock of Raw Material 2,42,000
Add: Additions/ Purchases [balancing figure as per requirement (i)] 52,50,000
Solution 11:
Statement of Cost of Impact Ltd. for the year ended 31st March, 2021:
S.I. No. Particulars Amount (Rs) Amount (Rs)
(i) Material Consumed :
Raw material purchased 5,00,00,000
GST paid under Composition Scheme * 10,00,000
Freight inwards 5,20,000
Less : Trade discounts received (10,00,000)
Add : Opening stock of raw materials 9,00,000
Less : Closing Stock of raw materials 5,60,000 5,08,60,600
(ii) Direct Employee (Labour) Cost :
Wages paid for factory workers 15,20,000
Contribution made towards employees’ PF & ESIS 1,90,000
Production bonus paid to factory workers 1,50,000 18,60,000
(iii) Direct Expenses :
Fee for technical assistance 1,12,000
Amount paid for power & fuel 2,62,000
Job charges paid to job workers 4,50,000 8,24,000
Prime cost 5,35,44,600
(iv) Works/ Factory overheads:
Stores and spares consumed 1,10,000
Depreciation on factory building 64,000
Depreciation on plant & machinery 86,000
Repairs & Maintenance paid for plant & machinery 58,000
Insurance premium paid for plant & machinery 31,200
Insurance premium paid for factory building 28,100
Salary paid to supervisors 1,20,000 4,97,300
Gross factory cost 5,40,41,900
Add: Opening value of W-I-P 4,00,000
Less: Closing value of W-I-P (2,50,000)
Factory Cost 5,41,91,900
(v) Quality control cost:
Expenses paid for quality control check activities 25,000
(vi) Research & development cost paid for improvement in 48,200
production process
(vii) Administration cost related with production:
-Expenses paid for administration of factory work 1,38,000
-Salary paid to Production control manager 4,80,000 6,18,000
Solution 12:
(a)Cost Sheet of A Ltd. for the month of December 2021
Particulars Amount (Rs) Amount (Rs)
Materials consumed 15,00,000
Wages & Salary 64,00,000
Gratuity & leave encashment 44,20,000 1,08,20,000
Power cost (13,000 kwh × Rs 7) 91,000
Diesel cost (1,000 ltr × Rs 93) 93,000 1,84,000
HEMM hiring charges 13,00,000
Prime Cost 1,38,04,000
AMC cost of CCTV installed at factory premises 18,000
Cost of Production/ Cost of Goods Sold 1,38,22,000
Hiring charges of cars 80,000
Reimbursement of diesel cost 20,000
1,00,000
Add: GST @5% on RCM basis 5,000 1,05,000
Maintenance cost for weighing bridge 7,000
AMC cost of CCTV installed at weigh bridge 6,000 13,000
TA/ DA & hotel bill of sales manager 16,000
Cost of Sales 1,39,56,000
4,680
Solution 13:
(i) Flexible Budget (before promotion)
Particulars Product ‘AYE’ Product ‘ZYE’ Total
Production & Sales (units) 4,000 3,000
Amount (Rs) Amount (Rs) Amount (Rs)
A. Sales Value 8,00,000 5,40,000 13,40,000
(Rs 200×4,000) (Rs 180×3,000)
B. Direct Materials 3,20,000 2,10,000 5,30,000
(Rs 80 × 4,000) (Rs 70 × 3,000)
C. Direct labour 1,60,000 1,05,000 2,65,000
(Rs 40 × 4,000) (Rs 35 × 3,000)
D. Variable Overheads 80,000 75,000 1,55,000
(Rs 20 × 4,000) (Rs 25 × 3,000)
E. Total Variable Cost (B+C+D) 5,60,000 3,90,000 9,50,000
F. Contribution (A-E) 2,40,000 1,50,000 3,90,000
G. Fixed Overhead 40,000 30,000 70,000
(Rs 10 × 4,000) (Rs 10 × 3,000)
H. Profit (F-G) 2,00,000 1,20,000 3,20,000
Profit per unit 50 40
Solution 14:
No. of bags manufactured = 1,000 units
Cost sheet for the month of September 2021
Particulars Total Cost (Rs) Cost per unit (Rs)
1. Direct materials consumed
- Leather sheets 3,20,000 320.00
- Cotton Clothes 15,000 15.00
Add: freight paid on purchase 8,500 8.50
(i) Cost of material consumed 3,43,500 343.50
2. Direct wages (Rs 80 x 2000 hours) 1,60,000 160.00
3. Direct expenses (Rs 10 x 2000 hours) 20,000 20.00
4 (ii) Prime Cost 5,23,500 523.50
5. Factory Overheads: Depreciation on 16,500 16.50
machines {(Rs 22,00,000 x 90%) ÷ 120
months}
Apportioned Cost of factory rent 98,000 98.00
6. (iii) Works/Factory Cost 6,38,000 638.00
7. Less: Realizable value of cuttings (Rs 150 x (5,250) (5.25)
35 kgs.)
8. (iv) Cost of Production 6,32,750 632.75
9. Add: Opening stock of bags 0
10. Less: Closing stock of bags (100 bags x Rs (63,275)
632.75)
11. (v) Cost of Goods Sold 5,69,475 632.75
12. Add: Administrative Overheads:
- Staff Salary 45,000 50.00
- Apportioned rent for administrative office 12,000 13.33
13. Add: Selling and Distribution Overheads
- Staff salary 72,000 80.00
- Apportioned rent for sales office 10,000 11.11
- Freight paid on delivery of bags 18,000 20.00
14 (vi) Cost of sales 7,26,475 807.19
Solution 15:
Cost Sheet of ‘Super’
Particulars Per unit Total (Rs)
(Rs)
Solution 16:
Statement of Cost of G Ltd. for the year ended 31st March, 2021:
Sl. No. Particulars Amount (Rs) Amount (Rs)
(i) Material Consumed:
- Raw materials purchased 20,00,00,000
- Freight inward 22,41,200
Add: Opening stock of raw materials 36,00,000
Less: Closing stock of raw materials (19,20,000) 20,39,21,200
(ii) Direct employee (labour) cost:
- Wages paid to factory workers 58,40,000
(iii) Direct expenses:
- Royalty paid for production 3,45,200
- Amount paid for power & fuel 9,24,000
- Job charges paid to job workers 16,24,000 28,93,200
Prime Cost 21,26,54,400
(iv) Works/ Factory overheads:
- Stores and spares consumed 2,24,000
- Repairs & Maintenance paid for plant & 96,000
machinery
Solution 17:
Statement of Cost
First three months (Rs) Remaining nine months (Rs) Total (Rs)
37,500 units 1,68,750 units 2,06,250 units
Direct material 18,75,000 84,37,500 1,03,12,500
Direct employee cost 6,00,000 27,00,000 33,00,000
Indirect – Variable expenses 3,75,000 16,87,500 20,62,500
Indirect – Fixed expenses 8,12,500 24,37,500 32,50,000
Indirect – Semi-variable
expense
1,00,000 1,00,000
30,000 30,000
30,000 30,000
1,05,000 1,05,000
1,00,000 1,00,000
* Alternatively, Costing Profit & Loss Account
1,06,000 1,06,000
Notes:
(1) Materials transferred between batches will not affect the Control Accounts.
(2) Non-production time of direct workers is a production overhead and therefore will not be charged to work-in-
Process control A/c.
(3) Production overheads absorbed in work-in-Process Control A/c equals to ₹ 30,000 (150% of ₹ 20,000).
(4) In the work-in-Process Control A/c the excess physical value of stock is taken resulting in stock gain. Stock gain
is transferred to Profit & Loss A/c.
Solution 2:
Journal entries are as follows:
DR. (Rs) CR. (Rs)
Stores Ledger Control A/c…………………………… Dr. 6,00,000
To Payables (Creditors) A/c 3,00,000
To Cash or Bank 3,00,000
Work-in-Process Control A/c…………………… Dr. 4,00,000
To Stores Ledger Control A/c 4,00,000
Wages Control A/c………………………………………. Dr. 2,00,000
To Bank A/c 2,00,000
Factory Overhead Control A/c…………………… Dr. 1,00,000
To Wages Control A/c 1,00,000
Work-in-Process Control A/c……………………… Dr. 1,00,000
To Wages Control A/c 1,00,000
Factory Overhead Control A/c………………… Dr. 80,000
To Bank A/c 80,000
Work-in-Process Control A/c…………………… Dr. 1,00,000
To Factory Overhead Control A/c 1,00,000
Selling and Dist. Overhead Control A/c………………. Dr. 40,000
To Bank A/c 40,000
Finished Goods Control A/c…………………… Dr. 5,00,000
To Work-in-Process Control A/c 5,00,000
Cost of Sales A/c………………………………………… Dr. 5,40,000
Solution 3:
Profit and Loss Statement of Go-getter Company
for the year ended 30th September, 2020
(Rs) (Rs)
Gross Sales 7,68,000
Less: Returns and rebates (14,000) 7,54,000
Less: Cost of Sales [Refer to Schedule (i)] (7,14,020)
Net Operating Profit 39,980
Less: Interest on borrowed funds (2,000+2,000) (4,000)
Net Profit 35,980
Solution 4:
(i) Statement of Profit as per financial records (for the year ended March 31, 2020)
(Rs.) (Rs.)
To Opening stock of Finished Goods 1,06,250 By Sales 45,60,000
Statement of Profit as per costing records (for the year ended March 31,2020)
(Rs.)
Sales revenue (A) 45,60,000
(12,615 units)
Cost of sales:
Opening stock 1,50,000
(625 units × Rs.240)
Add: Cost of production of 12,405 units 43,28,140
(Refer to working note 2)
Less: Closing stock (1,44,795)
Working notes:
Units
Sales 12,615
Add: Closing stock 415
Total 13,030
Less: Opening stock (625)
Number of units produced 12,405
2. Cost Sheet
(Rs.)
Raw materials consumed 16,80,000
Direct labour 12,20,000
Prime cost 29,00,000
Factory Overheads (70% of direct wages) 8,54,000
Factory cost 37,54,000
Add: Opening work-in-process 92,000
Less: Closing work-in-process (82,400)
Factory cost of goods produced 37,63,600
Solution 5:
Memorandum Reconciliation Accounts
Dr. Cr.
(Rs.) (Rs.)
To Net Loss as per Costing 6,94,000 By Administration overheads 1,20,000
books over recovered in cost accounts
To Factory overheads under 80,000 By Interest on investment not 1,92,000
Absorbed in Cost Accounts included in Cost Accounts
To Depreciation under 1,00,000 By Transfer fees in 48,000
charged in Cost Accounts Financial books
To Income-Tax not provided 1,08,000 By Stores adjustment 28,000
Cost Accounts (Credit in financial books)
To Interest on Loan Funds in 4,90,000 By Dividend received in 64,000
Financial Accounts financial books
By Net loss as per 10,20,000
Financial books
14,72,000 14,72,000
Solution 6:
Cost Ledger Control Account
Particulars (Rs.) Particulars (Rs.)
To Stores Ledger control A/c 1,30,000 By Balance b/d 68,50,000
To Costing Profit & Loss A/c 17,10,000 By Stores Ledger control A/c 12,50,000
By Wages Control A/c 6,00,000
To Balance c/d 77,10,000 By Manufacturing overhead 8,50,000
control A/c
95,50,000 95,50,000
Trial Balance
Particulars Dr. Cr.
(Rs.) (Rs.)
Stores Ledger Control A/c 27,70,000
WIP Control A/c 18,50,000
Finished Goods Control A/c 30,90,000
Cost Ledger Control A/c 77,10,000
77,10,000 77,10,000
Working:
Costing P&L Account
Particulars (Rs.) Particulars (Rs.)
To Cost of Sales A/c 16,60,000 By Cost Ledger control A/c 17,10,000
To Manufacturing overhead control 50,000
A/c
17,10,000 17,10,000
Solution 7:
Cost Ledger Control Account
(Rs) (Rs)
To Store Ledger Control A/c 65,000 By Opening Balance 34,25,00
To Balance c/d 47,10,000 By Store ledger control A/c 6,25,000
By Manufacturing Overhead Control 4,25,000
A/c 3,00,000
By Wages Control A/c
47,75,000 47,75,000
21,25,000 21,25,000
3,00,000 3,00,000
20,50,000 20,50,000
24,20,000 24,20,000
5,25,000 5,25,000
8,75,000 8,75,000
Trial Balance
(Rs) (Rs)
Stores Ledger Control A/c 13,85,000
WIP Control A/c 9,25,000
Finished Stock Ledger Control A/c 15,45,000
Manufacturing Overhead Control A/c 25,000
Cost of Sales A/c 8,30,000
Cost ledger control A/c --- 47,10,000
47,10,000 47,10,000
Solution 8:
(i) Amount of under absorption of production overheads:
Particular Amount (Rs.) Amount (Rs.)
Total production overheads actually incurred 8,80,000
Less: Amount paid to worker as per court order 50,000
Wages paid for the strike period under an award 38,000
Stores written off 22,000
Expenses of previous year booked in the current year 18,500 1,28,500
7,51,500
Less: Production overheads absorbed as per machine hour rate 5,17,500
(45,000 hours × Rs.11.50*)
Amount of under- absorbed production overheads 2,34,000
*Budgeted Machine hour rate (Blanket rate) = Rs. 10,35,000 / 90,000 = Rs. 11.50 per hour
(a) As 1/3rd of the under absorbed overheads were due to defective production planning, this being abnormal, hence
should be debited to Costing Profit and Loss Account.
Amount to be debited to Costing Profit and Loss Account
= Rs. 2,34,000 × 1/3 = Rs. 78,000.
(b) Balance of under absorbed production overheads should be distributed over Finished goods and Cost of sales by
applying supplementary rate*.
Amount to be distributed = Rs. 2,34,000 × 2/3 = Rs.1,56,000
*Supplementary rate = Rs. 1,56,000 / 30,000 units = Rs. 5.20 per unit
(iii) Apportionment of under absorbed production overheads over Finished goods and Cost of sales:
Particular Units Amount (Rs.)
Finished goods (3,000 units × Rs.5.20) 3,000 15,600
Cost of sales (27,000 units × Rs.5.20) 27,000 1,40,400
Total 30,000 1,56,000
Solution 9:
Cost Ledger Control Account
Particulars (Rs in ‘000) Particulars (Rs in ‘000)
To Costing P&L A/c 1,35,000 By Balance b/d 1,62,000
To Building Construction A/c 13,200 By Stores Ledger control A/c 12,000
To Balance c/d 1,44,900 By Wages Control A/c 45,000
By Factory overhead control A/c 48,000
45,000 45,000
To Wages Control A/c 12,000 By WIP Control A/c (bal. fig.) 54,900
To Cost Ledger control A/c 48,000 By Costing P&L A/c (under- 2,400
absorption)
63,300 63,300
Royalty Account
Particulars (Rs in ‘000) Particulars (Rs in ‘000)
1,500 1,500
1,08,000 1,08,000
Royalty Account
Particulars (Rs in ‘000) Particulars (Rs in ‘000)
1,500 1,500
1,08,000 1,08,000
13,200 13,200
Trial Balance
Particulars Dr. Cr.
(Rs in ‘000) (Rs in ‘000)
Stores Ledger Control A/c 16,500
WIP Control A/c 7,500
Finished Goods Control A/c 1,20,900
Workings:
Solution 10:
Cost Ledger Control Account
Particulars (Rs in ‘000) Particulars (Rs in ‘000)
To Costing P&L A/c 2,70,000 By Balance b/d 3,24,000
To Building Construction A/c 26,400 By Stores Ledger Control A/c 24,000
To Balance c/d 2,89,800 By Wages Control A/c 90,000
By Factory overhead control 96,000
A/c
By Royalty A/c 3,000
By Selling, Distribution and 15,000
Administration overheads
By Costing P&L A/c 34,200
5,86,200 5,86,200
4,57,800 4,57,800
Royalty Account
Particulars (Rs in ‘000) Particulars (Rs in ‘000)
To Cost Ledger control A/c 3,000 By WIP Control A/c 3,000
3,000 3,000
Trial Balance
Particulars Dr. Cr.
(Rs in ‘000) (Rs in ‘000)
Stores Ledger Control A/c 33,000
WIP Control A/c 15,000
Finished Goods Control A/c 2,41,800
Cost Ledger Control A/c 2,89,800
2,89,800 2,89,800
Working Note:
Cost of Goods sold = 2,70,000 × 80/100 = Rs 2,16,000
Solution 11:
Cost Ledger Control Account
Particulars (Rs in ‘000) Particulars (Rs in ‘000)
To costing P&L A/c 2,70,000 By balance b/d 3,24,000
To Building Construction 26,400 By Stores Ledger Control 24,000
A/c A/c
To balance c/d 2,89,800 By Wages Control A/c 90,000
By Factory Overhead 96,000
control A/c
By Royalty A/c 3,000
By Selling, Distribution and 15,000
Administration overheads
By Costing P&L A/c 34,200
5,86,200 5,86,200
To Cost Ledger control A/c 24,000 By Factory overheads control A/c 3,600
72,000 72,000
To Cost Ledger control A/c 96,000 By WIP Control A/c (bal. fig) 1,09,800
1,26,600 1,26,600
Royalty Account
Particulars (Rs in ‘000) Particulars (Rs in ‘000)
3,000 3,000
2,14,800 2,14,800
4,57,800 4,57,800
2,16,000 2,16,000
Trial Balance
Particulars Dr. Cr.
2,89,800 2,89,800
Working Note:
Cost of goods sold: Rs 2,70,000 x 80 / 100 = Rs 2,16,000
Solution 2:
Costing Profit and Loss Account
Particulars Amount (Rs.) Particulars Amount (Rs.)
Reconciliation Statement
Particulars Amount (Rs.) Amount (Rs.)
Net profit as per Financial Profit & Loss A/c 7,08,000
Add: Administrative overheads (2,80,000 - 2,49,600) 30,400
Selling & Distribution overheads (3,84,000 - 3,07,200) 76,800
Bad debts 32,000
Preliminary expenses 16,000
Legal charges 4,000 1,59,200
8,67,200
Less: Difference in value of materials consumed (22,40,000 - 20,00,000) 2,40,000
Factory overheads (6,88,000 - 6,40,000) 48,000
Dividend received 40,000
Interest on fixed deposit 8,000
Closing stock (3,20,000 - 3,10,154) 9,846 (3,45,846)
Profit as per Costing Profit & Loss A/c 5,21,354
Solution 3:
Statement of Reconciliation
Particulars Amount (Rs.) Amount (Rs.)
Net profit as per Cost accounts 10,20,000
Add:
Administration Overheads over- 1,20,000
absorbed
Interest on investments 1,92,000
Transfer fees 48,000
Stores adjustment 28,000
Dividend received 64,000 4,52,000
Less:
Factory Overheads under-absorbed 80,000
Depreciation under charged 1,00,000
Income-tax provided 1,08,000
Interest on loan funds 4,90,000 (7,78,000)
Net profit as per Financial accounts 6,94,000
Solution 4:
(i) Statement of Profit as per financial records
(for the year ended March 31, 2020)
(₨) (₨)
To Opening stock of Finished 1,06,250 By Sales 45,60,000
Goods
To Work-in-process 92,000 By Closing stock of finished 91,300
Goods
To Profit 1,39,450
49,01,700 49,01,700
(₨) (₨)
Profit as per Cost Accounts 1,50,965
Add: Administration overheads over absorbed 1,68,540
(₨ 5,64,540 – ₨ 3,96,000)
Opening stock overvalued 43,750
(₨ 1,50,000 – ₨ 1,06,250)
Interest received 76,000
2. Cost Sheet
(₨)
Raw materials consumed 16,80,000
Direct labour 12,20,000
Prime cost 29,00,000
Factory overheads (70% 8,54,000
of direct wages)
Solution 6:
Statement of Reconciliation
(Reconciling the profit as per costing records with the profit as per financial records)
(Rs) (Rs)
Net Profit as per Cost Accounts 3,60,740
Add:
Over recovery of selling overheads in cost accounts 10,250
Rent received credited in financial accounts 5,450 15,700
376,440
Less:
Over valuation of closing stock in cost accounts 7,300
Bad debts provided in financial accounts 3,250
Income tax provided in financial accounts 15,900
Loss on sale of capital asset debited in financial accounts 5,800
Under recovery of administration overheads in cost accounts 3,600 35,850
Profit as per Financial Accounts 3,40,590
Solution 2:
Contract Account
Particulars (Rs) Particulars (Rs)
To Material issued 2,51,000 By Machine (Working note 1) 2,46,000
To Wages 5,65,600 By Material (in hand) 35,400
To Foreman’s salary 81,300 By Works cost 10,49,000
To Machine 2,60,000 (balancing figure)
To Supervisor’s salary (Rs 8,000 × 9)/2 36,000
To Administrative charges 1,36,500
13,30,400 13,30,400
12,62,250 12,62,250
Working notes:
1. Written down value of Machine:
= Rs 2,60,000 - Rs 15,000 x 146 days = Rs 14,000
7 Years 365 days
Hence the value of machine after the period of 146 days = Rs 2,60,000 – Rs 14,000 = Rs 2,46,000
2. The cost of 2/3rd of the contract is Rs 10,49,000
∴ Cost of 100% of the contract is Rs 10,49,000 x 3 = Rs 15,73,500
2
∴Cost of 50% of the contract which has been certified by the architect is Rs 7,86,750. Also the cost of 1/3rd of
the contract, which has been completed but not certified by the architect is Rs 2,62,250.
Solution 3:
Contract No. 1551 Account for the year ended 31st March, 2021
Dr. Cr.
Particulars Amount (Rs.) Particulars Amount(Rs.)
Solution 4.
Workings:
(i) Percentage of work certified:
(Value of workcertified / Contract price) × 100
= (Rs. 2,00,000 / Rs. 5,00,000) ×100 = 40%
(ii) Value of material and labour used in the contract:
Particulars Amount (Rs.) Amount (Rs.)
Material purchased 1,00,000
Less: Material on hand (30-06-2020) (25,000) 75,000
Wages paid 45,000
Add: Wages accrued (30-06-2020) 5,000 50,000
1,25,000
Price of materials and wages has been increased by 25%, the value before price increase is:
(Rs. 1,25,000 / 125) × 100 = Rs. 1,00,000
(iii) Calculation of Value of work certified:
The value of the contract would be increased by 25% of the price increased beyond 5%.
Price increased beyond 5% = Rs. 25,000 – 5% of Rs. 1,00,000 = Rs. 20,000
Value of contract would be increased by 25% of Rs. 20,000 = Rs. 5,000
Therefore, the revised contract value = Rs. 5,00,000 + Rs. 5,000 = Rs. 5,05,000
Calculation of the Value of work certified after taking the effect of escalation clause:
Revised contract value × Percentage of work certified
= Rs. 5,05,000 × 40% = Rs. 2,02,000
Solution 5:
GVL Ltd.
Contract A/c
(April 1, 2018 to March 31, 2019)
Particulars Amount Particulars Amount
(Rs) (Rs)
To Materials Issued 18,24,000 By Plant returned to Stores (Working 2,40,000
Note 1)
To Labour 12,20,000 By Materials at Site 1,20,000
Add: Outstanding 96,000 13,16,000
To Plant Purchased 9,00,000 By W.I.P.
Certified 51,00,000
Uncertified 1,60,000 52,60,000
To Expenses 4,00,000 By Plant at Site (Working Note 2) 4,80,000
Less: Prepaid 90,000 3,10,000
To Notional Profit c/d 17,50,000
61,00,000 61,00,000
GVL Ltd.
Contract A/c
(April 1, 2018 to September 30, 2019)
(For Computing estimated profit)
Particulars Amount (Rs) Particulars Amount (Rs)
To materials issued 50,80,000 By Materials at site 3,00,000
(Rs 18,24,000 + Rs 32,56,000)
To Labour Cost 28,90,000 By Plant returned to stores on 2,40,000
(Rs 12,20,000 + Rs 96,000 + Rs 31-03-2019.
14,24,000* + Rs 1,50,000)
To plant purchased 9,00,000 By Plant returned to stores on 4,32,000
30.03.2019 (Working Note 3)
To Expenses 12,00,000 By Contractee A/c 1,08,50,000
(Rs 3,10,000 + Rs 7,90,000 + Rs
1,00,000)
To Estimated profit 17,52,000
1,18,22,000 1,18,22,000
• Labour paid in 2019-20 : Rs 15,20,000 – Rs 96,000 = Rs 14,24,000
Working Notes
(Rs)
1. Value of plant returned to stores on 31.03.2019
Historical Cost of the plant returned 3,00,000
Less : Depreciation @ 20% of WDV for one year (60,000)
2,40,000
2. Value of plants at site 31.03.2019
Historical cost of plants at site (Rs 9,00,000 – Rs 3,00,000) 6,00,000
Less : Depreciation @ 20% on WDV for one year (1,20,000)
4,80,000
Solution 6:
Contract A/c
(April 1, 2018 to March 31, 2019)
Contract A/c
(April 1, 2018 to December 31, 2019)
(For Computing estimated profit
Particulars Amount (Rs) Particulars Amount(Rs)
44,02,734 44,02,734
Solution 7:
RN Builders Ltd.
Contract Account (2019-20)
Particulars (Rs) Particular s (Rs)
Add: Further charges for nine months (5,85,000 x 9/12) 4,38,750 10,23,750
Solution 9:
Contract A/c
Particulars Amount (Rs) Particulars Amount
(Rs)
To opening work in By materials returned to 35,000
progress store
- Work certified 2,50,000 By materials returned to 50,000
suppliers
- Work uncertified 10,000 2,60,000 By costing P&L (Loss on 20,000
sale of materials)
To Material at site 35,000 By materials sold 20,000
To Materials purchased 2,00,000 By materials at site 25,000
To stores 8,00,000 By works cost (bal. fig.) 17,02,000
To wages 1,50,000
Add: Closing o/s wages 22,000
Less: Opening o/s (15,000) 1,57,000
wages
To Plant supervisor 80,000
salary
(2,40,000 x 1/3)
To Drawing and maps 50,000
To sundry expenses 30,000
To electricity charges 40,000
To Plant hire expenses 75,000
Add: O/s at end 15,000
Less: O/s at beginning (20,000) 70,000
To sub-contract 40,000
To Depreciation 90,000
5,00,000 – 20,000 x 270
4 360
18,52,000 18,52,000
To works cost 17,02,000 By work-in-progress
To costing P&L 6,10,750 Work Certified 21,00,000
(Notional profit)
Work uncertified 23,12,750
2,12,750
23,12,750 23,12,750
Working notes:
Calculation of value of work uncertified
Cost incurred till date 17,02,000
Estimated total cost (17,02,000/80%) 21,27,500
Cost of work certified till date (21,27,500 x 14,89,250
70%)
Cost of uncertified work (17,02,000 – 2,12,750
14,89,250)
Solution 10:
Computation of Notional Profit (Rs)
Value of work certified 4,89,600
Less: Cost of work certified
(Rs 4,00,000 – Rs 30,200) 3,69,800
Notional profit 1,19,800
Process- II Account
Particulars Units Amount (Rs) Particulars Units Amount (Rs)
To process- I A/C 1,150 2,76,000 By process – II A/c 2,700 6,48,000
To Material 208 50,000 (Transfer to Process – III)
To Labour 834 2,00,000
To Other exp. 300 72,000
To Indirect exp. * 208 50,000
2,700 6,48,000 2,700 6,48,000
Apportionment to:
Solution 2:
Statement of Evaluation
Particulars Equivalent Units Cost per EU Amount
(EU) (Rs) (Rs)
(i) Opening W-I-P completed during 400 210.88 84,352
the period
Add: Cost of W-I-P at the beginning -- -- 1,10,000
Complete cost of 1,00 units of 1,000 194.35 1,94,352
opening W-I-P
(ii) Completely processed units 8,000 210.88 16,87,040
(iii) Abnormal Loss 100 210.88 21,088
(iv) Closing W-I-P 600 210.88 1,26,528
(The difference in total amount may arise due to rounding off error)
Solution 3:
Statement of Equivalent Production Units (Under FIFO Method)
Particulars Input Particulars Output Equivalent Production
units Units % Equivalent
units
Opening W-I-P 1,000 From Opening W-I-P 1,000 40 400
Units introduced 10,000 From fresh inputs 8,000 100 8,000
Units completed 9,000
(Transferred to next
process)
Normal Loss {10% 1,100 -- --
(1,000 + 10,000 units)}
Closing W-I-P 800 75 600
Abnormal loss 100 100 100
(Balancing figure)
11,000 11,000 9,100
Statement of Evaluation
Solution 4:
Process – I Account
Particulars Total Cost Profit Particulars Total Cost Profit
(Rs) (Rs) (Rs) (Rs) (Rs) (Rs)
Opening Stock 7,500 7,500 -- Process- II A/c* 54,000 40,500 13,500
Direct material 15,000 15,000 -- (Transferred)
Direct Wages 11,200 11,200 -- Closing stock 3,700 3,700 --
Prime Cost 33,700 33,700
Overheads 10,500 10,500 --
Total Cost 44,200 44,200
Profit** 13,500 -- 13,500
57,700 44,200 13,500 57,700 44,200 13,500
Opening Stock 9,000 7,500 1,500 Finished stock A/c** 1,12,500 75,750 36,750
T/f from process-I 54,000 40,500 13,500 (Transferred)
Direct material 15,750 15,750 -- Closing stock* 4,500 3,750 750
Direct Wages 11,250 11,250 --
Prime Cost 90,000 75,000 15,000
Overheads 4,500 4,500 --
Total Cost 94,500 79,500 15,000
Profit*** 22,500 -- 22,500
1,17,000 79,500 37,500 1,17,000 79,500 37,500
Opening Stock 22,500 14,250 8,250 Costing P & L A/c 1,40,00 82,425 57,575
*Cost of Closing stock = Cost of transfer from Process –II x Value of closing stock
Transfer price from process –II
(As per instruction given in the question)
= Rs 75,750 x Rs 11,250 = Rs 7,575
Rs 1,12,500
Solution 5:
Total 42,400
Solution 6:
Solution 7:
(i) Statement of equivalent production (Average cost method)
Input Units Output Units Equivalent Units
Details Particulars Material Labour & O.H.
% Units % Units
Opening 4,000 Completed and 14,000 100 14,000 100 14,000
WIP
transferred
Unit
Introduced 16,000 Closing W-I-P 6,000 100 6,000 33-1/3 2,000
Solution 8:
(i) Statement of Equivalent Production
Particulars Units Particulars Units Equivalent Units
Sugarcane Labour O.H.
% Units % Units
Opening 4,500 Completed and 39,500 100 39,500 100 39,500
WIP transferred to
Process- II
Unit 1,00,000 55,000 -- -- -- --
Normal Loss (55%*
Introduced
of 1,00,000)
Abnormal Loss 1,000 100 1,000 80 800
Closing W-I-P
9,000 100 9,000 80 7,200
Solution 9:
Process I : Statement of Equivalent Production and Cost
Input Particulars Output Equivalent Production
(Units (Units)
Materials Labour Overheads
(%) Units (%) Units (%) Units
40,000 Completed 30,000 100 30,000 100 30,000 100 30,000
Closing 10,000 100 10,000 50 5,000 50 5,000
WIP
40,000 40,000 40,000 35,000 35,000
Process-II Account
Particulars Units (Rs) Particulars Units (Rs)
To Process-I A/c 30,000 7,35,000 By Normal loss 200 --
A/c
To Packing -- 80,000 By Finished Goods 28,000* 9,24,604
Material Stock A/c
To Direct Wages -- 71,125 By Closing WIP 1,800** 46,871
To Factory -- 85,350
Overhead
30,000 9,71,475 30,000 9,71,475
* 28,000 × Rs 30.1644 = Rs 8,44,603 + Rs 80,000 (Packing Material Cost) = Rs 9,24,604
** 1,800 units × Rs 24.6644 + 450 units × (Rs 2.5 + Rs 3) = Rs 46,871
Solution 10:
Total direct wages
= Rs 42,000 + Rs 54,000 + Rs 48,000 = Rs 1,44,000
Percentage absorption of production overhead on the basis of direct wages
= [2,88,000 / 1,44,000 ] x 100= 200%
Process-II A/c
Particulars Units Amt.(Rs) Particulars Units Amt.(Rs)
To Process-I A/c 6,600 3,35,955 By Normal loss 660 6,600
(10% of 6,600)
Process-III A/c
Particulars Units Amt.(Rs) Particulars Units Amt.(Rs)
To Process-I A/c 5,200 5,63,206 By Normal loss 260 2,600
(5% of 5,200)
To Production OH - 96,000
(200% of ₹48,000)
Solution 11:
(i) Calculation of Raw Material inputs during the month:
Quantities Entering Process Litres Quantities Leaving Process Litres
(iii) Calculation of values of Raw Material, Labour and Overheads added to the process:
Material Labour Overheads
Cost per equivalent unit Rs 46.00 Rs 14.00 Rs 18.00
Equivalent units (litre) (refer the working 7,488 7,744 7,872
note)
Cost of equivalent units Rs 3,44,448 Rs 1,08,416 Rs 1,41,696
Add: Scrap value of normal loss (832 units × Rs 15) Rs 12,480 -- --
Total value added Rs 3,56,928 Rs 1,08,416 Rs 1,41,696
Workings:
Statement of Equivalent Units (litre):
Input Details Units Output details Units Equivalent Production
Solution 12:
Statement of production
Operation Input Rejections Output
Total % of output
Solution 13:
(i) Statement of Equivalent Production (FIFO Method)
Input Output Equivalent Production
Solution 14:
(i) Statement of Equivalent Production (Using FIFO method)
Particulars Input Particulars Output Equivalent Production
Units Units
Material Labour & O.H.
% Units % Units
To Process-I A/c 6,250 29,698 By Cost Ledger Control A/c 6,250 53,125
(Refer Working Note-2) (6,250 units × Rs 8.5)
To Costing Profit - 23,427
& Loss A/c
Working Notes:
1. Computation of Cost per unit
Particulars Materials Labour Overhead
(Rs) (Rs) (Rs)
Input costs 2,20,000 26,500 61,500
Less: Realisable value of normal (27,625) -- --
scrap (3,250 units x Rs 8.5)
Net cost 1,92,375 26,500 61,500
Equivalent Units 51,750 51,050 51,050
Cost Per Unit 3.7174 0.5191 1.2047
Total cost per unit = Rs (3.7174 + 0.5191 + 1.2047) = Rs 5.4412
Solution 15:
(i) Statement of Equivalent Production (Weighted Average method)
Particulars Input Particulars Output Equivalent Production
Units Units
Material Labour & O.H.
% Units % Units
Opening WIP 3,000 Completed and 36,000 100 36,000 100 36,000
Transferred to Process-II
Units introduced 42,000 Normal Loss 1,800 -- -- -- --
(4% of 45,000 units)
Solution 16:
(i)
Dr. Process-1 Account Cr.
Particulars Units Total (Rs) Particulars Units Total (Rs)
To Raw Material Consumed 10,000 7,50,000 By Normal Loss A/c @ 500 6,750
13.5
” Direct Wages -- 3,00,000 ” Process 2 @ 133.5 9,000 12,01,500
(ii)
Particulars Units Total (Rs) Particulars Units Total (Rs)
To Process-I A/c 9,000 12,01500 By Normal Loss A/c @ 900 1,30,500
145
” To Direct Wages -- 5,60,000 ” By Finished Stock A/c 8,200 21,04,667
[bal fig]
” Direct Expenses -- 3,64,000
” Manufacturing Overheads -- 84,000
” To Abnormal gain 100 25,667
(Rs 256.67 × 100 units)
9,100 22,35,167 9,100 22,35,167
Cost per unit of completed units and abnormal gain:
= ( Rs 22,09,500 – Rs 130500 )/ 8,100units = Rs 256.67
Solution 17:
(i) Statement of Equivalent Production
Input Units Output Units Equivalent Units
Details Particulars Material Conversion Cost
% Units % Units
Opening WIP 1,000 Completed and
Units transferred to 35,000 100 35,000 100 35,000
introduced 40,000 Process-2
Normal Loss (10% of 4,000 - - - -
40,000)
Abnormal loss 500 100 500 60 300
(Balancing figure)
Closing W-I-P 1,500 100 1,500 60 900
41,000 41,000 37,000 36,200
Solution 18:
(i) Statement of Equivalent Production
Input Details Units Output Units Equivalent Production
Particulars Material- A Consumable Labour &
s Overheads
% Units % Units % Units
Units transferred 75,000 Units transferred 68,000 100 68,000 100 68,000 100 68,000
from Process-A to Process-C
Normal loss (6% 4,500 - - - - - -
of 75,000 units)
Closing W-I-P 3,000 100 3,000 70 2,100 50 1,500
Solution 19:
(i) Statement of Equivalent Production
Particulars Input Particulars Output Equivalent Production
Units Units
Material Labour & O.H.
% Units % Units
Opening WIP 5,000 Completed and 19,000 100 19,000 100 19,000
transferred
t
o next Process
Units introduced 25,000 Abnormal loss 1,000 100 1,000 100 1,000
(Balancing figure)
(19,000 units × Rs 4)
- Overheads -- 5,000
To Overheads -- 22,500
Solution 20:
Process- I Account
Particulars Units Amount (Rs) Particulars Units Amount (Rs)
To Raw Materials 2,000 12,000 By Normal loss (200 units × Rs 2) 200 400
To Production OH - 6,000
To Abnormal gain A/c 40 1,000
(40 units × Rs 25)
2,040 46,400 2,040 46,400
Working :
Cost per unit = Rs 45,400 - Rs 400 = Rs 25 per unit
2,000 units – 200 units
Process- II Account
Particulars Units Amount (Rs) Particulars Units Amount (Rs)
Workings :
Cost per unit = Rs 1,42,680 - Rs 1,740 = Rs 90 per unit
1,740 units – 174 units
Normal loss = 1,740 units × 10% = 174 units
Abnormal gain = (174 units + 1,580 units) – 1,740 = 14 units
Solution 21:
(i) Statement of equivalent production (Average cost method)
Particulars Input Particulars Output Equivalent Production
Units Units Material Labour &
O.H.
% Units % Units
Opening WIP 8,000 Completed and 28,000 100 28,000 100 28,000
transferred
Units introduced 32,000 Closing WIP 12,000 100 12,000 1/3rd 4,000
40,000 40,000 40,000 32,000
Solution 23:
(i) Process I
Statement of Equivalent Production Cost
Input (Units) Particulars Output Equivalent Production
Units Materials Labour Overheads
(%) Units (%) Units (%) Units
40,000 Completed 30,000 100 30,000 100 30,000 100 30,000
Closing WIP 10,000 100 10,000 50 5,000 50 5,000
40,000 40,000 40,000 35,000 35,000
Process-I Account
(ii) Process II
Statement of Equivalent Production and Cost
Input (Units) Particulars Output Equivalent Production
Units Materials Labour Overheads
(%) Units (%) Units (%) Units
30,000 Completed 28,000 100 28,000 100 28,000 100 28,000
Normal loss 200 -- -- --
Closing WIP 1,800 100 1,800 25 450 25 450
30,000 30,000 29,800 28,450 28,450
Process-II Account
Particulars Units (Rs) Particulars Units (Rs)
To Process-I A/c 30,000 14,70,000 By Normal loss A/c 200 --
To Packing Material -- 1,60,000 By Finished Goods 28,000* 18,49,209
Stock A/c
To Direct Wages -- 1,42,250 By Closing WIP 1,800** 93,741
To Factory -- 1,70,700
Overhead
30,000 19,42,950 30,000 19,42,950
* 28,000 × Rs 60.3289 = Rs 16,89,209 + Rs 1,60,000 (Packing Material Cost)
= Rs 18,49,209
** 1,800 units × Rs 49.3289 + 450 units × (Rs 5 + Rs 6) = Rs 93,741
Solution 24:
(i) Process – I Account
Particulars Units (Rs) Particulars Units (Rs)
To Materials 10,000 80,000 By Normal Loss (5% of 500 2,500
10,000)
To wages - 60,000 By process-II A/c 9,650 1,93,000
(Rs 20* x 9,650 units)
To Manufacturing OH 52,500
To Abnormal Gain A/c 150 3,000
(Rs 20* x 150 units)
150 3,000 150 3,000
To get the best out of these notes visit www.edu91.org
Join Us on YouTube www.youtube.com/neerajarora
Join Us on Telegram https://t.me/neerajaroraclasses
EDU91 | Where Learning Happens BY CA NITIN GURU
Solution 25:
(i) Calculation of raw material inputs during the month:
Quantities Entering Process Litres Quantities Leaving Process Litres
Opening WIP 900 Transfer to Finished Goods 4,200
Raw material input (balancing figure) 5,260 Process Losses 1,800
Closing WIP 160
6,160 6,160
(iii) Calculation of values of Raw Material, Labour and Overheads added to the process:
Material Labour Overheads
Cost per equivalent unit Rs 23.00 Rs 7.00 Rs 9.00
Equivalent units (litre) (refer the working note) 4,734 4,892 4,966
Solution 26:
(i) Statement of Equivalent Production (Average cost method)
Input Particulars Output Equivalent Production
(Units) Units
Materials Labour Overheads
(%*) Units** (%)** Units** (%)* Units**
40,000 Completed 28,000 100 28,000 100 28,000 100 28,000
WIP 12,000 100 12,000 33-1/3 4,000 33-1/3 4,000
40,000 40,000 40,000 32,000 32,000
* Percentage of Completion ** Equivalent Units
Solution 2:
Calculation of Net joint costs to be allocated:
Particulars Amount (Rs)
Joint Costs 10,00,000
Less: Net Realizable value of by-product (50,000× 5) 2,50,000
Net joint costs to be allocated 7,50,000
Therefore, amount of joint product cost that Smile company would allocate to the product-B by using the physical
volume method to allocate joint production costs:
= Physical quantity of Product-B × Net joint costs to be allocated
Total Quantity
= 1,20,000 units × Rs 7,50,000 = Rs 5,00,000
1,80,000 units
Solution 3:
(i) Estimated Net Realisable Value Method:
Buttermilk Butter
Amount (Rs) Amount (Rs)
Sales Value 8,40,000 76,80,000
(Rs 30 × 28 × 1000) (Rs 480 × 16 × 1000)
Less: Post split-off cost (Further
processing cost) -- (1,20,000)
Net Realisable Value 8,40,000 75,60,000
Apportionment of Joint Cost of Rs 5,10,000 45,90,000
51,00,000* in ratio of 1:9
* [(Rs 100 × 50 × 1000) + Rs 1,00,000] = Rs 51,00,000
(ii) Incremental revenue from further processing of Butter into Ghee
(Rs 480 × 16 × 1000 - Rs 360 × 20 × 1000) Rs 4,80,000
Less: Incremental cost of further processing
of Butter into Ghee Rs 1,20,000
Incremental operating income from further processing Rs 3,60,000
The operating income of ‘Buttery Butter’ will be reduced by ₹ 3,60,000 in February if it sells 20 tonne of Butter to
‘Healthy Bones’, instead of further processing of Butter into Ghee for sale. Thus, ‘Buttery Butter’ is advised not to accept
the offer and further process butter to make Ghee itself.
Solution 4:
Product A can be sold at the split-off point, because the question says that "Products B and C must be processed further
before they can be sold." Since product A is not included in that, we know that Product A can be sold at the split-off
point. Furthermore, the cost to process Product A after the split-off point is Rs 150,000, whereas the additional revenue
to be earned by processing it further is only Rs 75,000 (Rs 50 increase in selling price per unit multiplied by the 1,500
units produced during September). Therefore, Product A will not be processed further, and we use the sales value at
split-off for A for allocating the joint costs. The sales value at the split-off for A is Rs 100 × 1,500 units, or Rs 1,50,000.
Since Product B must be processed further, we use its net realizable value for the joint cost allocation. The net realizable
value of Product B is Rs 5,25,000 (Rs 175 selling price after further processing × 3,000 units produced) – Rs 1,50,000 in
further processing costs = Rs 3,75,000.
Product C, the by-product, must also be processed further to be sold. The net realizable value of Product C is Rs 75,000
(Rs 50 sales price after further processing × 4,500 units produced – Rs 1,50,000 in further processing costs = Rs 75,000.
Joint production costs total Rs 8,40,000. Since the by-product C is accounted for as a reduction to the joint costs, the
joint costs to be allocated are Rs 7,65,000 (Rs 8,40,000 minus the Rs 75,000 NRV of Product C), to be allocated between
Product A (sales value Rs 1,50,000) and Product B (net realizable value Rs 3,75,000). So, the total on which the allocation
of the joint costs is based is Rs 1,50,000 + 3,75,000 = Rs 5,25,000. Product A represents 28.571% of the total (Rs 1,50,000
÷ Rs 5,25,000).
Since Product A has no further processing costs, the total cost of Product A is equal to its allocated joint costs, which are
28.571% of the net joint costs of Rs 7,65,000, or Rs 2,18,568.
Solution 5:
(i) (a) Statement of Joint Cost allocation of inventories of X, Y and Z
(By using Net Realisable Value Method)
PRODUCTS TOTAL
X Y Z
Cost of goods sold as on March 31, 2020 (By using Net Realisable Value Method)
Products Total
X Y Z
Working Notes
1. Total production of three products for the year 2019-2020
Products Quantity sold in tones Quantity of ending Total production Ending inventory
inventory in tons percentage (%)
(1) (2) (3) (4) = [(2) + (3)} (5) = (3)/ (4)
X 186 180 366 49.18
Y 527 60 587 10.22
Z 736 25 761 3.29
Solution 6:
(i) Statement of Joint Cost allocation of inventories of X, Y and Z
Products Total (Rs.)
X (Rs.) Y (Rs.) Z (Rs.)
Working Notes:
1. Total production of three products for the year 2019-2020
Products Quantity sold in Quantity of closing Total production Closing inventory percentage
litres inventory in litres (%)
(1) (2) (3) (4) = [(2) + (3)} (5) = (3)/ (4)
X 10,000 5,000 15,000 100/3
Y 15,000 -- 15,000 --
Z 22,500 7,500 30,000 25
Solution 7:
Comprehensive Cost Statement
Particulars Total Cost Product-M Product-N
(Rs.) (Rs.) (Rs.)
No. of units produced * 5,400 units 810 units
Cost of raw material (Rs. 80 × 6,750 units) 5,40,000
Processing cost:
- Labour cost (Rs. 2,25,000 × 66%) 1,48,500
- Other costs (Rs. 2,25,000 - 1,48,500) 76,500
Total joint cost 7,65,000
(i) Apportionment of joint costs between the joint
products
Labour cost in the ratio of 100:80 1,48,500 82,500 66,000
(1,48,500 x (1,48,500 x 80)/
100)/ 180) 180)
Other joint costs (including material) in the ratio of 6,16,500 5,36,087 80,413
output (6,16,500 x (6,16,500 x 810) /
(5,400:810) 5,400) / 6,210 6,210
(ii) Total product cost 7,65,000 6,18,587 1,46,413
* No. of units produced of Product M = 6750 units x 80% = 5400 units
No. of units produced of Product N = 6750 units x 12% = 810 units
Solution 8:
Total Joint Cost
Amount (Rs.)
Solution 9:
Calculation of quantity produced
Dept I (kg) Dept II (kg) Dept III (kg)
Input 4,00,000 2,00,000 1,60,000
(50% of 4,00,000 kg.) (40% of 4,00,000 kg.)
Weight (lost) or (40,000) (40,000) 1,60,000
added (10% of 4,00,000 kg.) (1/5th of 2,00,000 kg.)
84,375 4,50,000
Profit 3,50,000 1,40,000
(as per iii above) (as per iii above)
Product A should be sold at split off point and product B after processing because of higher profitability.
Solution 12:
Total Joint Cost
Particulars Amount (Rs)
Direct Material 60,000
Direct Labour 19,200
Variable Overheads 24,000
Total Variable Cost 1,03,200
Fixed Overheads 64,000
Total joint cost 1,67,200
Working Notes:
1. Teacher’s Salary
Particulars Arts (Rs) Commerce Science (Rs)
(Rs)
No. of teachers 4 5 6
Salary per annum (Rs) (Rs 35,000 x 12) 4,20,000 4,20,000 4,20,000
Total Salary 16,80,000 21,00,000 25,20,000
( 𝐑𝐬. 𝟏,𝟎𝟒𝟎
𝟒,𝟐𝟎,𝟎𝟎𝟎
x 𝟐𝟎𝟖) ( 𝐑𝐬. 𝟏,𝟏𝟎𝟎
𝟒,𝟐𝟎,𝟎𝟎𝟎
x 𝟏𝟔𝟎)
3. Principal’s salary has been apportioned on the basis of time spent by him for administration of classes.
4. Lab attendants’ salary has been apportioned on the basis of lab classes attended by the students.
5. Salary of library staffs are apportioned on the basis of time spent by the students in library.
6. Salary of Peons are apportioned on the basis of number of students. The peons’ salary allocable to higher secondary
classes is calculated as below:
Amount (Rs)
Peon dedicated for higher secondary 1,20,000
(1 peon × Rs 10,000 × 12 months)
Add: 15% of other peons’ salary 54,000
{15% of (3 peons × Rs 10,000 × 12 months)}
1,74,000
7. Salary to other staffs, office & administration cost, Annual day expenses and sports expenses are apportioned on the
basis of number of students.
8. Examination expenditure has been apportioned taking number of students into account (It may also be apportioned
on the basis of number of examinations).
Solution 2:
(i) Calculation of total cost for ‘Professionals Protection Plus’ policy
Particulars Amount (Rs) Amount (Rs)
1. Marketing and Sales support:
- Policy development cost 11,25,00
- Cost of marketing 45,20,000
- Sales support expenses 11,45,000 67,90,000
2. Operations:
- Policy issuance cost 10,05,900
- Policy servicing cost 35,20,700
- Claims management cost 1,25,600 46,52,200
3. IT Cost 74,32,000
4. Support functions
- Postage and logistics 10,25,000
- Facilities cost 15,24,000
- Employees cost 5,60,000
- Office administration cost 16,20,400 47,29,400
Total Cost 2,36,03,600
Solution 3:
Cost Statement of Ignus Thermal Power Station
Total units generated 20,00,000 kWh
Per annum (Rs) Per kWh (Rs)
Fixed Costs
Plant supervision 6,00,000
Administration overheads 40,00,000
Depreciation (5% of Rs 5,00,00,000 p.a.) 25,00,000
Total fixed cost: (A) 71,00,000 3.55
Variable costs:
Operating labour 30,00,000
Lubricants, spares and stores 8,00,000
Repairs & maintenance 10,00,000
Coal cost (Refer to working note) 17,00,000
Total variable cost: (B) 65,00,000 3.25
Total cost [(A) + (B)] 1,36,00,000 6.80
Working Note:
Coal cost (20,00,000 kwh. ÷ 5 kWh) × Rs 4.25 per kg. = Rs 17,00,000
Solution 4:
(i) Calculation of total project cost per day of concession period:
Activities Amount (Rs in
Lakh)
Site clearance 170.70
Land development and filling work 9,080.35
Sub base and base courses 10,260.70
Bituminous work 35,070.80
Bridge, flyovers, underpass, Pedestrian subway, footbridge, etc. 29,055.60
Drainage and protection work 9,040.50
Traffic sign, marking and road appurtenance 8,405.00
Maintenance, repairing and rehabilitation 12,429.60
Environmental management 982.20
Total Project cost 1,14,495.25
Administration and toll plaza operation cost 1,120.00
Total Cost 1,15,615.25
Concession period in days (25 years × 365 days) 9,125
Cost per day of concession period (Rs in lakh) 12.67
S.No. Type of vehicle Equivalent cost [A] Weight Toll fee per
(B) vehicle [A×B]
1. Two wheelers Rs 19.06 1 19.06
2. Car and SUVs Rs 19.06 4 76.24
3. Bus and LCV Rs 19.06 6 114.36
4. Heavy commercial vehicles Rs 19.06 9 171.54
Working Note:
The cost per day has to be recovered from the daily traffic. The each type of vehicle is to be converted into equivalent
unit. Let’s convert all vehicle types equivalent to Two-wheelers.
S.No. Type of vehicle Daily traffic Weight Ratio Equivalent Two
volume [A] [B] wheeler [A×B]
1. Two wheelers 44,500 0.05 1 44,500
2. Car and SUVs 3,450 0.20 4 13,800
3. Bus and LCV 1,800 0.30 6 10,800
4. Heavy commercial vehicles 816 0.45 9 7,344
Total 76,444
Solution 5:
Working Notes:
Solution 6:
(i) Statement showing the expenses of operating a single bus and the fleet of 25 buses for a year
Particulars Per bus per annum (Rs) Fleet of 25 buses per annum (Rs)
Running costs : (A)
Diesel (Refer to working note 1) 2,21,056 55,26,400
Repairs & maintenance costs: (B) 20,500 5,12,500
Fixed charges:
Driver's salary 1,44,000 36,00,000
( Rs 12,000 × 12 months)
Cleaners salary 96,000 24,00,000
(Rs 8,000 × 12 months)
Licence fee, taxes etc. 8,400 2,10,000
Insurance 15,600 3,90,000
Depreciation
(Rs 20,00,000 – Rs 1,60,000)/16yrs. 1,15,000 28,75,000
(ii) Average cost per student per month in respect of students coming from a distance of:
(a) 2 km. from the school Rs 219.12
{Rs 6,20,556 / (236 students × 12 months)}
(Refer to Working Note 2)
(b) 4 km. from the school (Rs 219.12 × 2) Rs 438.24
(c) 8 km. from the school (Rs 219.12 × 4) Rs 876.48
(iii) Calculation of minimum bus fare to be recovered from the students during the year 2020:
Working Notes:
1. Calculation of diesel cost per bus:
No. of trips made by a bus each day 4
Distance travelled in one trip both ways (8 km. × 2 trips) 16 km.
Distance travelled per day by a bus (16 km. × 4 shifts) 64 km.
Distance travelled during a month (64 km. × 22 days) 1,408 km.
Distance travelled per year (1,408 × 10 months) 14,080 km.
No. of litres of diesel required per bus per year 2,816 litres
(14,080 km. ÷ 5 km.)
Cost of diesel per bus per year (2,816 litres × Rs 78.50) Rs 2,21,056
Cost of diesel per bus per year (844.8 litres × Rs 78.50) Rs 66,316.80
Solution 7:
(i) Operating Cost Sheet for the month of August, 2020
Particulars Amount (Rs)
(A) Fixed Charges:
Manager’s salary (Rs 60,000 × 60%) 36,000
Drivers’ Salary (Rs 20,000 × 30 drivers) 6,00,000
Helpers’ wages (Rs 12,000 × 25 helpers) 3,00,000
Insurance (Rs 8,40,000 ÷ 12 months) 70,000
Road licence (Rs 6,00,000 ÷ 12 months) 50,000
Garage rent (Rs 9,00,000 ÷ 12 months) 75,000
Routine mechanical services 3,00,000
Electricity charges (for office, garage and washing station) 55,000
Depreciation of vehicles 6,00,000
Apportioned workshop expenses 88,000
Total (A) 21,74,000
(B) Variable Charges:
Loading and unloading charges (Working Note 1) 7,65,000
Consumable Stores 1,35,000
Cost of diesel (Working Note 2) 14,04,000
Lubricant, Oil etc. 1,15,000
Replacement of Tyres, Tubes & other parts 4,25,000
Total (B) 28,44,000
(C) Total Cost (A + B) 50,18,000
(D) Total Ton-Kms. (Working Note 3) 9,43,200
(E) Cost per ton-km. (C ÷ D) 5.32
Working Notes:
2. Cost of Diesel:
Distance covered by each vehicle during August, 2020
= 100 k.m. × 2 × 25 days × 90% = 4,500 km.
Consumption of diesel = (4,500k.m. × 20vehicles)/ 5k.m. = 18,000 litres
Cost of diesel = 18,000 litres × Rs 78 = Rs 14,04,000.
Solution 8:
(i) Calculation of Absolute Ton-km for the next month:
Journey Distance (in km) Weight- Ton-km Weight- Ton-km Total
Up Down
(in MT) (in MT)
Solution 9:
(i) Calculation of Operating Cost per month for each vehicle
Ramgarh (Rs) Pratapgarh (Rs) Devgarh (Rs) Total(Rs)
A. Running Costs:
- Cost of diesel (Working Note- 2) 1,68,480 95,472 2,49,600 5,13,552
- Servicing cost (Working Note- 3) 45,000 - 45,000 90,000
2,13,480 95,472 2,94,600 6,03,552
B. Fixed Costs:
- Salary to drivers 96,000 72,000 1,20,000 2,88,000
(4 drivers × (3 drivers × (5 drivers ×
Rs 24,000) Rs 24,000) Rs 24,000)
- Salary to cleaners 48,000 36,000 60,000 1,44,000
(4 cleaners × (3 cleaners × (5 cleaners ×
Rs 12,000) Rs 12,000) Rs 12,000)
- Allocated garage parking fee 16,800 12,600 21,000 50,400
Working Notes:
1. Distance covered by the vehicles in a month
Route Total Distance (in K.M.)
Ramgarh (4 vehicles × 3 trips × 2 × 24 km. × 30 days) 17,280
Pratapgarh (3 vehicles × 2 trips × 2 × 34 km. × 30 days) 12,240
Devgarh (5 vehicles × 4 trips × 2 × 16 km. × 30 days) 19,200
3. Servicing Cost
Ramgarh Pratapgarh Devgarh
Total distance travelled (K.M.) 17,280 12,240 19,200
Covered under free service warranty No Yes No
No. of services required 3 2 3
(17,280 k.m. ÷ 5,000 (12,240 k.m. ÷ 5,000 (19,200 k.m. ÷ 5,000
k.m.) k.m.) k.m.)
Total Service Cost (Rs) 45,000 (Rs 15,000 × 3) --- 45,000 (Rs 15,000 × 3)
4. Calculation of Depreciation
Ramgarh Pratapgarh Devgarh
No. of vehicles 4 3 5
Cost of a vehicle (Rs) 11,02,000 13,12,000 9,25,000
Total Cost of vehicles (Rs) 44,08,000 39,36,000 46,25,000
Depreciation per month (Rs) 36,733 32,800 38,542
(Rs 44,08,000 ×10%) (Rs 39,36,000 ×10%) (Rs 46,25,000 ×10%)
/12months /12months /12months
Solution 10:
Workings:
Calculation of number of Patient days
100 Beds × 120 days = 12000
40 Beds × 80 days = 3,200
Extra beds = 400
Total = 15,600
Solution 11:
Statement of Cost
Particulars (Rs)
A. Apportionment of capital cost (Rs 900 crores / 10years) × (1/12 months) 7,50,00,000
B. Other Costs
Salary to Collection Personnel (3 Shifts × 5 persons per shift × 30 days 90,000
× Rs 200 per day)
Salary to Toll Booth Manager (3 Shifts × 1 person per shift × 30 days 45,000
× Rs 500 per day)
Electricity 1,50,000
Telephone 1,00,000
4,72,000
C. Maintenance cost 50,00,000
Total (A + B + C) 8,04,72,000
Solution 12:
Working Notes:
(i)Total Room days in a year
Season Occupancy (Room-days) Equivalent Full Room charge days
Season – 80% Occupancy 200 Rooms × 80% × 6 28,800 Room Days × 100%
months × 30 days in a month = = 28,800
28,800 Room Days
Off-season – 40% Occupancy 200 Rooms × 40% × 6 14,400 Room Days × 50%
months × 30 days in a month = = 7,200
14,400 Room Days
Total Room Days 28,800 + 14,400 = 43,200 36,000 Full Room days
Room Days
Solution 13:
(i) Statement of Expenses of operating bus/ buses for a year
Particulars Rate (Rs) Per Bus per annum Fleet of 5 buses
(Rs) p.a. (Rs)
(i) Standing Charges:
Driver’s salary 9,000 p.m. 1,08,000 5,40,000
Cleaner’s salary 6,000 p.m. 14,400 72,000
Licence fee, taxes etc. 8,600 p.m. 8,600 43,000
Insurance 10,000 p.m. 10,000 50,000
Depreciation (15,00,000 – 3,00,000) ÷ 12 yrs 1,00,000 p.a. 1,00,000 5,00,000
(ii) Maintenance Charges:
Repairs & maintenance 35,000 p.a. 35,000 1,75,000
(iii) Operating Charges:
Diesel (Working Note 1) 2,92,500 14,62,500
Total Cost [(i) + (ii) + (iii)] 5,68,500 28,42,500
Cost per month 47,375 2,36,875
Total no. of equivalent students (Working Note 2) 150 750
Total Cost per half fare equivalent student Rs 316 Rs 316
Working Notes:
1. Calculation of diesel cost per bus:
Distance travelled in a year : (8 round trip × 10 km. × 25 days × 9 months)
Distance travelled p.a. : 18,000 km.
Cost of diesel (per bus p.a.) : [18,000 km / 4 kmpl] x Rs 65 = Rs 2,92,500
Solution 14:
(i) Annual Cost Statement of four vehicles
(Rs)
Diesel {(4,21,632 km. ÷ 4 km) × Rs 60) (Refer to Working Note 1) 63,24,480
Oil & sundries {(4,21,632 km. ÷ 100 km.) × Rs 525} 22,13,568
Solution 15:
Working Notes:
1. Total Distance (in km.) covered per month
Bus route Km. per trip Trips per day Days per Km. per
month month
Delhi to Hisar 160 2 9 2,880
Delhi to Aligarh 160 2 12 3,840
Delhi to Alwar 170 2 6 2,040
Total 8,760
Total 4,14,000
Calculation of Rate per passenger km. and fares to be charged for different routes
Rate per Passenger-Km. = Total takings per month
Total Passengers – Km. per month
Rs 5,37,268
= 4,14,000 Passenger-Km. = RS 1.30 (approx.)
Solution 18:
Working Notes:
Calculation of Depreciation per month:
Particulars CNG Car EV Car
A Car purchase price (Rs) 9,20,000 15,20,000
B Less: Govt. subsidy (Rs) -- (1,50,000)
C Less: Residual value (Rs) (95,000) (1,70,000)
D Depreciable value of car (Rs) [A-B-C] 8,25,000 12,00,000
E Life of the car 15 years 10 years
F Annual depreciation (Rs) [D÷E] 55,000 1,20,000
G Depreciation per month (Rs) [F÷12] 4,583.33 10,000
1,544.45 6,283.33
C Fixed cost:
Depreciation [Refer WN-1] 4,583.33 10,000
Driver’s salary 20,000 20,000
Garage rent 4,500 4,500
Share of Office & Administration cost 1,500 1,500
30,583.33 36,000
D Operating cost per month [A+B+C] 36,627.78 43,708.33
Solution 19:
(i) Statement of Expenses of operating a mini bus in a year
Particulars Rate (Rs) Per Bus per
annum (Rs)
(A) Standing Charges:
Driver’s Salary 20,000 p.m. 2,40,000
Lady attendant’s salary 10,000 p.m. 1,20,000
Average Cleaner’s salary (50%) 15,000 p.m. 90,000
Insurance Charge 30,000 p.a. 30,000
License fee, taxes etc. 5,080 p.m. 60,960
Average Garage Rent 24,000 p.m. 36,000
Depreciation {(15,00,000 – 3,00,000) ÷ 8} 1,50,000 1,50,000
p.a.
(B) Maintenance Charges:
Repairs & maintenance including engine oil and lubricants (Working 28,560 p.a.
Notes 1)
(C) Operating Charges:
Diesel (Working Note 2) 5,76,000
Total Cost (A + B + C) 13,31,520
Cost per month 1,10,960
Solution 20:
Working Notes:
(i) Total room days in a year
Season Occupancy (Room-days) Equivalent Full Room charge days
Season – 80% Occupancy 200 Rooms × 80% × 6 months 28,800 Room Days × 100%
× 30 days in a month = 28,800 = 28,800
Room Days
Off-season – 40% Occupancy 200 Rooms × 40% × 6 months 14,400 Room Days × 50% = 7,200
× 30 days in a month = 14,400
Room Days
Total Room Days 28,800 + 14,400 = 43,200 36,000 Full Room days
Room Days
Solution 21:
(i) Calculation of total project cost per day of concession period:
Activities Amount (Rs in lakh)
Site clearance 341.00
Solution 2:
(a) Std. labour cost (Rs)
(1,000 hours × Rs 50) 50,000
(b) Actual wages paid 36,000
(c) Actual rate per hour: Rs 36,000/900 hours = Rs 40
Variances
(i) Labour Rate variance = Actual time (Std. rate – Actual rate)
= 900 hours (Rs 50 – Rs 40) = Rs 9,000 (F)
(ii) Efficiency variance = Std. rate per hr. (Std. time – Actual time)
= Rs 50 (1,000 hrs. – 900 hrs.) = Rs 5,000 (F)
(iii) Total labour cost variance = Std. labour cost – Actual labour cost
= {(Rs 50 × 1,000 hours) – Rs 36,000}
= (Rs 50,000 – Rs 36,000) = Rs 14,000 (F)
Solution 3:
Working Notes:
Budget Standard for Actual Actual
Hours Rate Amount Hours Rate Amount Hours Rate Amount
(Rs) (Rs) (Rs) (Rs) (Rs) (Rs)
Skilled 2 6 12 20,000 6 1,20,000 18,000 7 1,26,000
Semi-Skilled 3 4 12 30,000 4 1,20,000 33,000 3.5 1,15,500
Un-Skilled 5 3 15 50,000 3 1,50,000 58,000 4 2,32,000
10 39 1,00,000 3,90,000 1,09,000 4,73,500
Solution 4:
Workings:
1. Standard hours (SH) for actual hours produced are calculated as below:
Skilled = 1,800 × 1,280 = 1,152 hrs.
2,000
Semi-skilled = 1,800 × 480 = 432 hrs.
2,000
Unskilled = 1,800 × 240 = 215 hrs.
2,000
Semi-Skilled 18 40 720
Unskilled 4 40 160
2,000
3. For 40 hours week total Revised standard hours (RSH) will be calculated as below:
Category No. of Worker Hours in a week Total Hours
Skilled 32 40 1,280
Semi-Skilled 12 40 480
Unskilled 6 40 240
2,000
Calculations:
Category of workers SH x SR AR x SR AH x AR RSH x SR
Skilled 1,152 x 3 = 3,456 1,120 x 3 = 3,360 1,120 x 4 = 4,480 1,280 x 3 = 3,840
Semi-Skilled 432 x 2 = 864 720 x 2 = 1,440 720 x 3 = 2,160 480 x 2 = 960
Unskilled 216 x 1 = 216 160 x 1 = 160 160 x 2 = 320 240 x 1 = 240
Total Rs 4,536 Rs 4,960 Rs 6,960 Rs 5,040
(i) Labour Cost Variance = Std. Cost for hours worked – Actual cost paid
= (SH × SR) – (AH × AR)
= Rs 4,536 – 6,960 = Rs 2,424 (A)
(ii) Labour Rate Variance = AH (SR – AR) or (AH × SR) – (AH × AR)
Skilled = 3,360 – 4,480 = Rs 1,120 (A)
Semi-skilled = 1,440 – 2,160 = Rs 720 (A)
Unskilled = 160 - 320 = Rs 160 (A) 2,000 (A)
(iii) Labour Efficiency Variance = SR (SH – AH) or (SR × SH) – (SR × AH)
Skilled = 3,456 – 3,360 = Rs 96 (F)
Semi-skilled = 864 – 1,440 = Rs 576 (A)
Unskilled = 216 – 160 = Rs 56 (F) Rs 424 (A)
(iv) Labour Mix Variance = SR (RSH – AH) or (SR × RSH) – (SR × AH)
Skilled = 3,840 – 3,360 = Rs 480 (F)
Semi-skilled = 960 – 1,440 = Rs 480 (A)
Unskilled = 240 - 160 = Rs 80 (F) Rs 80 (F)
(v) Labour Yield Variance = SR (SH – RSH) or (SR × SH – SR × RSH)
Skilled = 3,456 - 3,840 = Rs 384 (A)
Semi-skilled = 864 - 960 = Rs 96 (A)
Unskilled = 216 - 240 = Rs 24 (A) Rs 504 (A)
Check
(i) LCV = LRV + LEV
Rs 2,424 (A) = Rs 2,000 (A) + Rs 424 (A)
(ii) LEV = LMV + LYV
Rs 424 (A) = Rs 80 (F) + Rs 504 (A)
Solution 5:
(i) Fixed Overhead Cost Variance:
= Overhead absorbed for actual production – Actual overhead incurred
= ( Rs 15,00,000 x 7,800) - Rs 15,60,000 = 0
7,500
(ii) Fixed Overhead Expenditure Variance:
= Budgeted overhead – Actual overhead
= Rs 15,00,000 - Rs 15,60,000 = Rs 60,000 (A)
(iii) Fixed Overhead Volume Variance:
= Absorbed overhead – Budgeted overhead
= ( Rs 15,00,000 x 7,800) - Rs 15,00,000 = Rs 60,000 (F)
7,500
(iv) Fixed Overhead Efficiency Variance:
= Std. Rate (Std. hours for actual production - Actual hours)
Solution 6:
Standard for 10 Units Actual for 10 Units
Material Qty. Rate Amount Qty. Rate Amount
Units (Rs) (Rs) Units (Rs) (Rs)
X 600 15 9,000 640 17.50 11,200
Y 800 20 16,000 950 18.00 17,100
Z 1,000 25 25,000 870 27.50 23,925
Total 2,400 50,000 2,460 52,225
4. Material Mix Variance = (Revised Std. Qty. – Actual Qty.) × Std. Price
Material X = (615* – 640) × 15 = Rs 375 (A)
Material Y = (820* – 950) × 20 = Rs 2,600 (A)
Material Z = (1,025 – 870) × 25 = Rs 3,875 (F)
MMV = Rs 900 (F)
*Revised Standard Quantity (RSQ) is calculated as follows:
Material X = 2460 × 600 = 615 units
2400
Material Y = 2460 × 800 = 820 units
2400
Material Z = 2460 × 1,000 = 1,025 units
2400
5. Material Yield Variance= (Std. Qty - Revised Std. Qty.) × Std. Price
Material X = (600 - 615) × 15 = Rs 225 (A)
Material Y = (800 - 820) × 20 = Rs 400 (A)
Material Z = (1,000 - 1,025) × 25 = Rs 625 (A)
MYV = Rs 1,250 (A)
Check,
MUV = MMV + MYV (Or MRUV)
Solution 7:
Production/ Overhead volume variance (only for fixed overhead)
Fixed Overhead Volume Variance:
= Absorbed overhead – Budgeted Overhead
= (Rs 5 × 15,000 units) – (Rs 5 × 20,000 units)
= Rs 75,000 - Rs 1,00,000 = Rs 25,000 (Adverse)
Solution 8:
(i) Actual Price of Material A
Let Actual Price of Material A be ‘X’
Material Price Variance (A) = Rs 105 (A)
Material Price Variance = (SP – AP) × AQ
(20 – X) × 70 = 105 (A)
1,400 – 70X = -105
X = 1,505 ÷ 70 = 21.5
Therefore X (Actual Price) = Rs 21.5
Solution 9:
Working Notes:
Budget Actual
1. Working hours per month 24,000 20,160
2. Production units per month = (Budget 24,000 ÷ 4 hrs, Actual given) 6,000 5,305
3. Standard fixed overhead rate per unit = Rs 1,44,000 ÷ 6,000 = Rs 24
4. Standard fixed overhead rate per hour = Rs 1,44,000 ÷ 24,000 = Rs 6
5. Standard fixed overhead rate per day = Rs 1,44,000 ÷ 25 = Rs 5,760
Variances:
(i) F.O. Expenditure Variance = (Budgeted fixed overhead – Actual fixed overhead)
= 1,44,000 – 1,42,000 = Rs 2,000 (F)
(ii) Total Volume Variance = (Standard fixed overhead – Budgeted fixed overhead)
= 1,27,320 – 1,44,000 = Rs 16,680 (A)
(iii) Fixed overhead variance = (Standard fixed overhead – Actual Fixed overhead)
= 1,27,320 – 1,42,000 = Rs 14,680 (A)
Alternatively: Expenditure Variance + Volume Variance = 2,000 (F) + 16,680 (A) = Rs 14,680 (A)
Solution 10:
For fixed overhead variances:
Actual F.O. incurred (given) Rs 12,000
Budgeted F.O. for the period Rs 10,000
Standard F.O. for production (Standard output for actual time × Standard Fixed Overhead per unit)
2,100 units × {Rs 10,000 ÷ 2,000 units} Rs 10,500
Solution 11:
(i) Material Cost Variance (A + B) = {(SQ × SP) – (AQ × AP)}
Rs 3,625 = (SQ × SP) – Rs 59,825
(SQ × SP) = Rs 63,450
(SQA × SPA) + (SQB × SPB) = Rs 63,450
(940 kg × SPA) + (705 kg × Rs 30) = Rs 63,450
(940 kg × SPA) + Rs 21,150 = Rs 63,450
(940 kg × SPA) = Rs 42,300
SPA = Rs 42,300
940kg
Standard Price of Material-A = Rs 45
Working Note:
SQ i.e. quantity of inputs to be used to produce actual output
= 1,480 kg = 1,645 kg
90%
SQA = 800 kg × 1,645kg = 940 kg
(800+600)
SQB = 600 kg × 1,645kg = 705 kg
(800+600)
Solution 12:
(i) Material Variances
Budget Standard for Actual Actual
Qty. Price Amount Qty. Price Amount Qty. Price Amount
(Rs) (Rs) (Rs) (Rs) (Rs) (Rs)
Material 0.5 60 30 5,000 60 3,00,000 5,700 58 3,30,600
Material Cost Variance = (SQ×SP – AQ ×AP)
3,00,000 – 3,30,600 = Rs 30,600(A)
Material Price Variance = (SP – AP) AQ
Solution 13:
(i) Material Usage Variance = Std. Price (Std. Quantity – Actual Quantity)
= Rs 90 (9,000 kg. – 8,900 kg.)
= Rs 9,000 (Favorable)
(ii) Material Price Variance = Actual Quantity (Std. Price – Actual Price)
= 8,900 kg. (Rs 90 – Rs 92) = Rs 17,800 (Adverse)
(iii) Material Cost Variance = Std. Material Cost – Actual Material Cost
= (SQ × SP) – (AQ × AP)
= (9,000 kg. × Rs 90) – (8,900 kg. × Rs 92)
= Rs 8,10,000 – Rs 8,18,800
= Rs 8,800 (Adverse)
(iv) Labour Efficiency Variance = Std. Rate (Std. Hours – Actual Hours)
= Rs 80[(9000/10) x 800hrs. – 7,000 hrs.)
= Rs 80 (7,200 hrs. – 7,000 hrs.)
= Rs 16,000 (Favorable)
(v) Labour Rate Variance = Actual Hours (Std. Rate – Actual Rate)
= 7,000 hrs. (Rs 80 – Rs 84)
= Rs 28,000 (Adverse)
(vi) Labour Cost Variance = Std. Labour Cost – Actual Labour Cost
= (SH × SR) – (AH × AR)
= (7,200 hrs. × Rs 80) – (7,000 hrs. × Rs 84)
= Rs 5,76,000 – Rs 5,88,000
= Rs 12,000 (Adverse)
(vii) Variable Cost Variance = Std. Variable Cost – Actual Variable Cost
= (7,200 hrs. × Rs 20) – Rs 1,40,000
= Rs 4,000 (Adverse)
(viii) Fixed Overhead Cost Variance = Absorbed Fixed Overhead – Actual Fixed Overhead
= (Rs 250/10) x 9000kgs.) – Rs 2,60,000
= Rs 2,25,000 – Rs 2,60,000 = Rs 35,000 (Adverse)
Solution 14:
(i) Material Usage Variance = Std. Price (Std. Quantity – Actual Quantity)
= Rs 90 (18,000 kg. – 17,800 kg.)
= Rs 18,000 (Favourable)
(ii) Material Price Variance = Actual Quantity (Std. Price – Actual Price)
= 17,800 kg. (Rs 90 – Rs 92) = Rs 35,600 (Adverse)
(iii) Material Cost Variance = Std. Material Cost – Actual Material Cost
= (SQ × SP) – (AQ × AP)
= (18,000 kg. × Rs 90) – (17,800 kg. × Rs 92)
= Rs 16,20,000 – Rs 16,37,600
= Rs 17,600 (Adverse)
(iv) Labour Efficiency Variance = Std. Rate (Std. Hours – Actual Hours)
= Rs 100 (1,800 units × 8 – 14,000 hrs.)
= Rs 100 (14,400 hrs. – 14,000 hrs.)
= Rs 40,000 (Favourable)
(v) Labour Rate Variance = Actual Hours (Std. Rate – Actual Rate)
= 14,000 hrs. (Rs 100 – Rs 104)
= Rs 56,000 (Adverse)
(vi) Labour Cost Variance = Std. Labour Cost – Actual Labour Cost
= (SH × SR) – (AH × AR)
= (14,400 hrs. × Rs 100) – (14,000 hrs. × Rs 104)
= Rs 14,40,000 – Rs 14,56,000
= Rs 16,000 (Adverse)
(vii) Variable Cost Variance = Std. Variable Cost – Actual Variable Cost
= (14,400 hrs. × Rs 15) – Rs 2,17,500
= Rs 1,500 (Adverse)
(viii) Fixed Overhead Cost Variance = Absorbed Fixed Overhead – Actual Fixed Overhead
= (1,800 units × Rs 400) - Rs 7,68,000
= Rs 7,20,000 – Rs 7,68,000 = Rs 48,000 (Adverse)
Solution 15:
Material Variances:
Material SQ SP SQ × SP RSQ RSQ × SP AQ AQ × SP AP AQ × AP
(WN-1) (Rs) (Rs) (WN-2) (Rs) (Rs) (Rs) (Rs)
A 940 kg. 90.00 84,600 886 kg. 79,740 900 kg. 81,000 86.00 77,400
B 705 kg. 60.00 42,300 664 kg. 39,840 650 kg. 39,000 65.00 42,250
1645 kg 1,26,900 1550 kg 1,19,580 1550 kg 1,20,000 1,19,650
Labour Variances:
Labour SH SR SH × SR RSH RSH × SR AH AH × SR AR AH × AR
(WN3) (Rs) (Rs) (WN-4) (Rs) (Rs) (Rs) (Rs)
Skilled 1,116 hrs 75.00 83,700 1144 85,800 1,200 90,000 71.00 85,200
Unskilled 893 hrs 44.00 39,292 916 40,304 860 37,840 46.00 39,560
2,009 hrs 1,22,992 2,060 1,26,104 2,060 1,27,840 1,24,760
(e) Labour Cost Variance (Skilled + Unskilled) = {(SH × SR) – (AH × AR)} = {1,22,992 – 1,24,760} = 1,768 (A)
(f) Labour Efficiency Variance (Skilled + Unskilled) = {(SH × SR) – (AH × SR)} = {1,22,992 – 1,27,840} = 4,848(A)
(g) Labour Yield Variance (Skilled + Unskilled) = {(SH × SR) – (RSH × SR)}= {1,22,992 – 1,26,104} = 3,112 (A)
Solution 16:
Budgeted Production 30,000 hours ÷ 6 hours per unit = 5,000 units
Budgeted Fixed Overhead Rate = Rs 45,00,000 ÷ 5,000 units = Rs 900 per unit Or
= Rs 45,00,000 ÷ 30,000 hours = Rs 150 per hour.
(i) Material Cost Variance = (Std. Qty. × Std. Price) – (Actual Qty. × Actual Price)
= (4,800 units × 10 kg. × Rs 100) - Rs 52,50,000
= Rs 48,00,000 – Rs 52,50,000
= Rs 4,50,000 (A)
(ii) Labour Cost Variance = (Std. Hours × Std. Rate) – (Actual Hours × Actual rate)
= (4,800 units × 6 hours × Rs 55) – Rs 15,50,000
= Rs 15,84,000 – Rs 15,50,000
= Rs 34,000 (F)
(iii) Fixed Overhead Cost Variance = (Budgeted Rate × Actual Qty) – Actual Overhead
= (Rs 900 × 4,800 units) – Rs 47,00,000
= Rs 3,80,000 (A) OR
= (Budgeted Rate × Std. Hours) – Actual Overhead
= (Rs 150 × 4,800 units × 6 hours) – Rs 47,00,000
= Rs 3,80,000 (A)
(iv) Variable Overhead Cost Variance = (Std. Rate × Std. Hours) – Actual Overhead
= (4,800 units × 6 hours × Rs 100) - Rs 29,30,000
= Rs 28,80,000 - Rs 29,30,000
= Rs 50,000 (A)
Solution 17:
Workings:
Calculation of budgeted hours
Budgeted hours = (52 x 25 x 8) x 85% = 8,840 hours
Solution 18:
(1) Fixed Overhead Expenditure Variance
= Budgeted Fixed Overheads – Actual Fixed Overheads
= Rs 12,000 – Rs 12,800 (as calculated below) = Rs 800 (A)
(2) Fixed Overhead Cost Variance= Absorbed Fixed Overheads – Actual Fixed Overheads
2,800 (A) = Rs 10,000 – Actual Overheads Actual Overheads = Rs 12,800
Working Note:
(i) Fixed Overhead Volume Variance = Absorbed Fixed Overheads – Budgeted Fixed Overheads
2,000 (A) = Absorbed Fixed Overheads – Rs 12,000
Absorbed Fixed Overheads = Rs 10,000
(ii) Standard Rate/ Hour = Rs 5 (Rs 12,000/2,400 hrs.)
Solution 19:
Basic Calculation
Material Standard for 640 kg. output Actual for 680 kg. output
Qty. Kg. Rate (Rs) Amount (Rs) Qty Kg. Rate (Rs) Amount (Rs)
A 480 50 24,000 540 60 32,400
B 320 60 19,200 260 50 13,000
Total 800 43,200 800 45,400
Less: Loss 160 - - 120 - -
640 43,200 680 45,400
Std. cost of actual output = Rs 43,200 × 680/640 = Rs 45,900
Calculation of Variances
(i) Material Cost Variance = (Std. cost of actual output – Actual cost)
= (45,900– 45,400) = Rs 500 (F)
(iii) Material Usage Variance (MUV) = (Std. Quantity for actual output – Actual Quantity) × Std. Price
Material A = [ (480 × 680) / 640 – 540) × 50 = Rs 1,500 (A)
Material B = [ (320 ×680) / 640 – 260) × 60 = Rs 4,800 (F)
MUV = Rs 3,300 (F)
Solution 20:
Working:
No. of units produced 1,000 units
Std. input per unit 30 kg.
Std. quantity (Kg.) 30,000 kg.
Add: Excess usage 7,200 kg
Actual Quantity 37,200 kg.
Add: Closing Stock 10,000 kg.
Less: Opening stock 5,000 kg.
Quantity of Material purchased 42,200 kg.
Solution 21:
(i) Material price variance: = Actual Quantity Consumed (Std. Price – Actual Price)
𝐑𝐬. 𝟏,𝟖𝟕,𝟎𝟎𝟎
= 22,000 pcs. [Rs 9 - ] = Rs 11,000 (Favourable)
𝟐𝟐,𝟎𝟎𝟎 𝐩𝐜𝐬
(ii) Material usage variance:
= Std. price per piece (Std. Quantity – Actual Quantity Consumed)
= Rs 9 (1,900 units × 10 pcs. – 22,000 pcs.) = Rs 27,000 (Adverse)
Solution 22:
Calculations of standard input of Material B
Solution 23:
(a) Basic Calculations:
Standard hours per unit = Budgeted hours / Budgeted Units = 25,000 / 50,000 = 0.50 hrs
Std. hrs. for actual output = 54,000 units x 0.50hr = 27,000 hrs.
Revised budgeted overhead (for fixed overhead) = 26,000 hrs. × Rs 2.60 = Rs 67,600
Calculation of variances
(i) F.O. Cost Variance = Recovered Overhead – Actual Overhead
= Rs 70,200 – Rs 54,000 = Rs 16,200 (F)
(vi) F.O. Calendar Variance = (Actual days – Budgeted days) x Std. rate per day
= (26 – 25) × Rs 2,600 = Rs 2,600 (F)
Solution 24:
(i) Material Cost , price and usage variance
Material cost variance ( on the basis of consumed quantity)
= SQ × SP – AQ Consumed × AP
= (5 kg. × 62,000 units × Rs 15) - (3,20,000 kg. × Rs 14)
= Rs 46,50,000 - Rs 44,80,000
= Rs 1,70,000 (F)
Alternatively,
Material Cost Variance (on the basis of purchased quantity)
= SQ × SP – AQ Purchase × AP
= 3,10,000 × Rs 15 – 3,50,000 × Rs 14
= Rs 2,50,000 (A)
Solution 25:
1. (i) Material Variances
Budget Std. for actual Actual
Solution 28:
Working Notes:
Calculation of Standard Man hours
When 100 workers work for 1 hour, the standard output is 50 units.
Standard man hours per unit = 100 hours/50units = 2 hours per unit
Calculation of standard man hours for actual output:
= 1,920units x 2 hours = 3,840 hours.
Calculation of actual cost
Type of Workers No of Actual Hours Rate Amount Idle Hours (5% of Actual hours
Workers Paid (Rs) (Rs) hours paid) Worked
Group ‘A’ 10 400 12.40 4,960 20 380
Group ‘B’ 30 1,200 12 14,400 60 1,140
Group ‘C’ 60 2,400 11.40 27,360 120 2,280
100 4,000 46,720 200 3,800
Calculation of Standard wage Rate:
Labour Efficiency Variance = 480F
(Standard hours for Actual production – Actual Hours) x SR = 480F
(3,840 – 3,800) x SR = 480
Standard Rate (SR) = Rs 12 per hour
Total Labour Cost Variance
= (Standard hours x Standard Rate) – (Actual Hours x Actual rate)
= (3,840 x 12) – 46,720 = 640A
Total Labour Rate Variance
= (Standard Rate – Actual Rate) x Actual Hours
Group ‘A’ = (12 – 12.40) 400 = 160 A
Group ‘B’ = (12 – 12) 1,200 0
Group ‘C’ = (12 – 11.40) 2,400 = 1,440 F
1,208 F
Total Labour Gang Variance
= Total Actual Time Worked (hours) × {Average Standard Rate per hour of Standard Gang -Average Standard Rate per
hour of Actual Gang@}
@ on the basis of hours worked
= 3,800 × (12- 3,840×12)
3,800
=0
[Note: As the number of workers in standard and actual is the same, there is no difference in mix ratio, so labour gang
variance will be NIL]
Total Labour Yield Variance
= Average Standard Rate per hour of Standard Gang × {Total Standard Time (hours) - Total Actual Time worked (hours)}
= 12 x (3,840 – 3,800)
= 480F
Total Labour idle time variance
= Total Idle hours x standard rate per hour
= 200 hours x 12
= 2,400A
Solution 29:
Working Notes
Fixed Overheads = Budgeted Fixed Overheads = Rs 12,00,000 Rs 10
Budgeted Output 1,20,000 units
Fixed Overheads element in Semi-Variable overheads i.e. 60% of Rs 1,80,000 Rs 1,08,000
Fixed Overheads = Budgeted Fixed Overheads = Rs 1,08,000 Rs 0.90
Budgeted output 1,20,000 units
Standard rate of Absorption of Fixed Overheads per units (Rs 10 + Rs 0.90) Rs 10.90
Fixed overheads absorbed on 8,000 units @ Rs 10.90 Rs 87,200
Budgeted Variable Overheads Rs 6,00,000
Add: Variable element in Semi-variable overheads 40% of Rs 1,80,000 Rs 72,000
Total Budgeted Variable Overheads Rs 6,72,000
Standard variable Cost per unit = Budgeted Variable Overheads = Rs 6,72,000 Rs 5.60
Budgeted Output 1,20,000 units
Standard Variable Overheads for 8,000 units @ Rs 5.60 Rs 44,800
Budgeted Annual Fixed Overheads (Rs 12,00,000 + 60% of Rs 1,80,000) Rs 13,08,000
Possible Fixed Overheads = Budgeted Fixed Overheads x Actual days Rs 1,03,550
Budgeted days
= Rs 1,09,000 x 19 days
20 days
Actual Fixed Overheads (Rs 1,10,000 + 60% of Rs 19,200) Rs 1,21,520
Actual Variable Overheads (Rs 48,000 + 40% of Rs 19,200) Rs 55,680
Computation of Variances
Overhead Cost Variable = Absorbed Overheads – Actual Overheads
= (Rs 87,200 + Rs 44,800) – (Rs 1,21,520 + Rs 55,680)
= Rs 45,200 (A)
Fixed Overhead cost Variance = Absorbed Fixed Overheads – Actual Fixed Overheads
= Rs 87,200 – Rs 1,21,520
= Rs 34,320 (A)
Variable Overhead Cost Variance = Standard Variable Overheads for Production – Actual Variable Overheads
= Rs 44,800 – Rs 55,680
= Rs 10,880 (A)
Fixed Overhead Volume Variance = Absorbed Fixed Overheads – Budgeted Fixed Overheads
= Rs 87,200 – Rs 1,09,000
= Rs 21,800 (A)
Fixed Overhead Expenditure Variance = Budgeted Fixed Overheads – Actual Fixed Overheads
= Rs 10.90 × 10,000 units – Rs 1,21,520
= Rs 12,520 (A)
Calendar Variance = Possible Fixed Overheads – Budgeted Fixed Overheads
= Rs 1,03,550 – Rs 1,09,000
= Rs 5,450 (A)
OR
Calendar Variance = (Actual days – Budgeted days) x Standard fixed overhead rate per day
Standard fixed overhead rate per day = 1308000/20*12 = Rs 5450
Fixed Overhead Calendar Variance = (19-20) x 5450 = 5450(A)
Solution 30:
SR – Standard Labour Rate per hour
AR – Actual Labour rate per hour
SH – Standard Hours
AH – Actual Hours
(i) Labour rate variance = AH (SR – AR)
-1,53,846 = 25,641 (12 – AR)
- 6 = 12 – AR
AR = Rs 18
(ii) Labour Efficiency = SH/AH x 100 = 105.3
SH = AH x 105.3/100 = 25,641 x 105.3/100
SH = 26,999.973
SH = 27,000 hours
(iii) Labour Efficiency variance = SR (SH – AH)
= 12 (27,000 – 25,641)
= Rs 16,308 (F)
(iv) Standard Labour Cost per unit = 27,000 x 12/9,000 = Rs 36
(v) Actual Labour Cost per unit = 25,641 x 18/9,000 = Rs 51.282
Solution 31:
Budgeted Production 30,000 hours ÷ 6 hours per unit = 5,000 units
Budgeted Fixed Overhead Rate = Rs 90,00,000 ÷ 5,000 units = Rs 1,800 per unit
= Rs 90,00,000 ÷ 30,000 hours = Rs 300 per hour.
(i) Material Cost Variance = (Std. Qty. × Std. Price) – (Actual Qty. × Actual Price)
= (4,800 units × 10 kg. × Rs 200) – Rs 1,05,00,000
= Rs 96,00,000 – Rs 1,05,00,000
= Rs 9,00,000 (A)
(ii) Labour Cost Variance = (Std. Hours × Std. Rate) – (Actual Hours × Actual rate)
= (4,800 units × 6 hours × Rs 110) – Rs 31,00,000
= Rs 31,68,000 – Rs 31,00,000
= Rs 68,000 (F)
(iii) Fixed Overhead Cost Variance= (Budgeted Rate × Actual Qty) – Actual Overhead
= (Rs 1,800 × 4,800 units) – Rs 94,00,000
= Rs 7,60,000 (A)
OR = (Budgeted Rate × Std. Hours) – Actual Overhead
= (Rs 300 × 4,800 units × 6 hours) – Rs 94,00,000
= Rs 7,60,000 (A)
(iv) Variable Overhead Cost Variance= (Std. Rate × Std. Hours) – Actual Overhead
= (4,800 units × 6 hours × Rs 200) - Rs 58,60,000
= Rs 57,60,000 - Rs 58,60,000
= Rs 1,00,000 (A)
(iii) The proposed sales mix increases the total contribution to sales ratio from 47.5% to 50% and the total profit from Rs
10,50,000 to Rs 14,00,000. Thus, the proposed sales mix should be accepted.
Solution 2:
(i) Computation of PV ratio, contribution and break-even sales for existing product mix
Products
S T U Total
Selling Price (Rs) 300 400 200
Less: Variable Cost (Rs) 150 200 120
Contribution per unit (Rs) 150 200 80
P/V Ratio (Contribution/Selling 50% 50% 40%
price)
Sales Mix 35% 35% 30%
Contribution per rupee of sales 17.5% 17.5% 12% 47%
(P/V Ratio × Sales Mix)
(ii) Computation of PV ratio, contribution and break-even sale for proposed product mix
Products
S T M Total
Selling Price (Rs) 300 400 300
Less: Variable Cost (Rs) 150 200 150
Contribution per unit (Rs) 150 200 150
P/V Ratio (Contribution/Selling 50% 50% 50%
price)
Sales Mix 50% 25% 25%
Contribution per rupee of sales 25% 12.5% 12.5% 50%
(P/V Ratio × Sales Mix)
Present Total Contribution (Rs Rs 32,00,000
64,00,000 × 50%)
Less: Fixed Costs Rs 18,00,000
Proposed Profit Rs 14,00,000
Present Break Even Sales (Rs Rs 36,00,000
18,00,000/0.50)
Solution 3:
Sales Volume 5,00,000 Units
Computation of existing contribution
(i) Break even sales in units = (Fixed Cost / Contribution per unit)
= Rs 10,00,00,000/ Rs 250 = 4,00,000 units
Break even sales in rupees = 4,00,000 units × Rs 680 = Rs 2,720 lakhs
OR
P/V Ratio = (250 / 680) × 100 = 36.76%
B.EP (Rupees) = [Fixed Cost / (P/V Ratio)] = 10,00,00,000/36.76% = Rs 2,720 lakhs (approx.)
(iii) Profit if selling price is increased by 10% and sales volume drops by 10%:
Existing Selling Price per unit = Rs 680
Revised selling price per unit = Rs 680 × 110% = Rs 748
Existing Sales Volume = 5,00,000 units
(iv)Volume to be achieved to earn target profit of Rs 700 lakhs with revised selling price and reduction of 10% in variable
costs and Rs 170 lakhs in fixed cost:
Revised selling price per unit = Rs 748
Variable costs per unit existing = Rs 430
Revised Variable Costs
Reduction of 10% in variable costs = Rs 430 – 10% of 430
= Rs 430 – Rs 43
= Rs 387
Total Fixed Cost (existing) = Rs 1,000 lakhs
Reduction in fixed cost = Rs 170 lakhs
Revised fixed cost = Rs 1,000 lakhs – Rs 170 lakhs = Rs 830 lakhs
Revised Contribution (unit) = Revised selling price per unit – Revised Variable Costs per units
Revised Contribution per unit = Rs 748 – Rs 387 = Rs 361
Desired Contribution = Revised Fixed Cost + Target Profit
= Rs 830 lakhs + Rs 700 lakhs = Rs 1,530 lakhs
No. of units to be sold = (Desired Contribution / Contribution per unit) = Rs 15,30,00,000/ Rs 361 = 4,23,823 units
Solution 4:
Working Notes:
(1) Calculation of Cost of Goods Sold (COGS):
COGS = DM + DL + FOH + AOH
COGS = {0.3 COGS + 0.15 COGS + (0.10 COGS + Rs 2,30,000) + (0.02 COGS + Rs 71,000)}
Or, COGS =0.57 COGS + Rs 3,01,000
Or, COGS =Rs 3,01,000/0.43= Rs 7,00,000
Solution 5:
Workings:
Statement Showing Profit on Sale of 90,000 units
(Rs) (Rs)
Material 32
Conversion Cost 24
Dealers’ Margin 8 64
Profit 4,40,000
In both the proposed suggestions, the fixed costs remain unchanged. Therefore, the present profit of Rs 4,40,000 can be
maintained by maintaining the total contribution at the present level i.e. Rs 14,40,000.
New Variable Cost (Rs 32 + Rs 24 + Rs 9.60) = Rs 65.60 Contribution (Rs 80 − Rs 65.60) = Rs 14.40
Level of sales required for present level of Profits = Total Contribution Required / New Contribution per unit
= Rs 14,40,000 / Rs 14.40 = 1,00,000 units
Conclusion:
The second proposal, i.e., increasing the Dealer's Margin is recommended because:
1. The contribution per unit is higher which is Rs 14.40 in comparison to Rs 12.40 in the first proposal; and
2. The sales (in units) required to earn the same level of profit are lower. They are at 1,00,000 units as against 1,16,129
units in the first proposal. This means a lower sales effort and less finance would be required for implementing proposal
(ii) as against proposal (i).
Of course, under proposal (ii) the company can earn higher profits than at present level if it can increase its sales beyond
1,00,000 units.
Solution 6:
Workings:
(1) Contribution per unit = Selling price per unit – Variable cost per unit
= Rs 50 – {Rs (16,00,000 + 4,00,000 + 8,00,000) ÷ 80,000 units}
= Rs 50 – Rs 35 = Rs 15
(2) Profit-Volume (P/V) Ratio = (Contribution per unit / Selling price per unit) × 100 = Rs 15/ Rs 50 × 100 = 30%
Calculations:
(i) The number of units to be sold for neither loss nor gain i.e. Break-even units:
=Fixed Overheads / Contribution per unit = Rs 7,20,000 / Rs 15 = 48,000 units
(iii) Calculation of extra units to be sold to earn present profit of Rs 4,80,000 under the following proposed selling price:
When selling price is reduced by
20% (Rs) 25% (Rs)
Selling price per unit 40.00 37.50
(Rs 50 × 80%) (Rs 50 × 75%)
Less: Variable Cost per unit 35.00 35.00
Contribution per unit 5.00 2.50
Desired Contribution:
Fixed Overheads 7,20,000 7,20,000
Desired Profit 4,80,000 4,80,000
12,00,000 12,00,000
a. Sales unit for desired contribution 2,40,000 units 4,80,000 units
Desired Contribution Rs 12,00,000 Rs 12,00,000
Contribution per unit Rs 5 Rs 2.5
b. Units presently sold 80,000 units 80,000 units
c. Extra units to be sold {(a) – (b)} 1,60,000 units 4,00,000 units
(ii)
Particulars Jan. Feb. March April May June Total (Rs)
(Rs) (Rs) (Rs) (Rs) (Rs) (Rs)
Batch output (in pieces) 210 200 220 180 200 220 1,230
Sale value @ Rs 80 16,800 16,000 17,600 14,400 16,000 17,600 98,400
Material cost 6,500 6,400 6,800 6,300 7,000 7,200 40,200
Direct wages 1,200 1,400 1,500 1,400 1,500 1,600 8,600
Chargeable expenses* 6,000 6,720 6,720 6,210 7,800 8,000 41,450
Total cost 13,700 14,520 15,020 13,910 16,300 16,800 90,250
Profit per batch 3,100 1,480 2,580 490 (300) 800 8,150
Total cost per piece 65.2 72.6 68.3 77.3 81.5 76.4 73.4
Profit per piece 14.8 7.4 11.7 2.7 (1.5) 3.6 6.6
Solution 7:
Contribution to sales ratio (P/V ratio) = 37%
Variable cost ratio = 100% - 37% = 63%
Variable cost = Rs 10,00,000 x 63% = Rs 6,30,000
After decrease in selling price and fixed cost, sales quantity has not changed. Thus, variable cost is Rs 6,30,000.
Revised Contribution to sales = 30%
Thus, Variable cost ratio = 100% - 30% = 70%
Thus, Revised sales = Rs 6,30,000 / 70% = Rs 9,00,000
Revised, Break-even sales ratio = 100% - 40% (revised Margin of safety) = 60%
(i) Revised fixed cost = revised breakeven sales x revised contribution to sales ratio
= Rs 5,40,000 (Rs 9,00,000 x 60%) x 30% = Rs 1,62,000
(iii) Revised Break-even point = Revised sales x Revised break-even sales ratio
= Rs 9,00,000 x 60%
= Rs 5,40,000
Solution 8:
Workings:
1. Statement showing computation of Breakeven of merged plant and other required information
S.No. Particulars Plan A Plant B Merged Plant
Before After Before After (100%)
(90%) (100%) (60%) (100%) (Rs)
(Rs) (Rs) (Rs) (Rs)
(i) Sales 63,00,000 70,00,000 48,00,000 80,00,000 1,50,00,000
(ii) Variable cost 39,60,000 44,00,000 22,50,000 37,50,000 81,50,000
(iii) Contribution (i - ii) 23,40,000 26,00,000 25,50,000 42,50,000 68,50,000
(iv) Fixed Cost 13,00,000 13,00,000 15,00,000 15,00,000 28,00,000
(v) Profit (iii - iv) 10,40,000 13,00,000 10,50,000 27,50,000 40,50,000
Solution 9:
(i) Statement Showing “Calculation of Contribution/ unit”
Particulars X Y Z
(Rs) (Rs) (Rs)
Selling Price (A) 312 400 240
Variable Cost:
Direct Labour
Variable Overheads 8 20 12
Hours in Dept. A 6 10 5
Rank I II III
Existing Hours = 10,000 x 6hrs. + 12,000 x 10 hrs. + 20,000 x 5 hrs. = 2,80,000 hrs. Best possible product mix (Allocation of
Hours on the basis of ranking)
Produce ‘X’ = 12,000 units
X 12,000 72 8,64,000
Z 9,600 40 3,84,000
Total 28,48,000
Solution 10:
(i) Variable cost per unit = Change in Total cost / Change in units
= (Rs 3.50 × 5,000 units) - (Rs 3.75 × 4,000 units) / (5,000 × 4,000)
= (Rs 17,500 – Rs 15,000) / 1,000 = Rs 2,500/1000 = Rs 2.5
(ii) Fixed cost = Total Cost – Variable cost (at 5,000 units level)
= Rs 17,500 – Rs 2.5 × 5,000 = Rs 5,000
(iii) Contribution per unit = Fixed cost / BEP (in units) = Rs 5,000 / 6,000 units = 0.833
P/V Ratio = Contribution per unit / Sale price per unit = 0.833 / 2.5 + 0.833 = 25%
Solution 11:
Selling Price = Rs 500 Profit = Rs 125 No of Sticks = 5,000
Particular Current Year (Rs) Next Year (Rs)
Direct Material 150 157.50
(150 + 5%)
Direct Wages 50 60
(50+20%)
Works Overheads 62.50 62.5
(125 × 50%)
Selling Expenses 12.50 12.5
(50 × 25%)
Total Variable Cost 275 292.50
Fixed Cost (62.5 × 5,000) = 3,12,500; 5,00,000 5,50,000
(37.5 × 5,000) = 1,87,500
Let: Lowest Price Quoted = K
Now, Sales = Target Profit (5,000 units × Rs 125) + Variable Cost + Fixed Cost
Or, = (5,000 × 500) + (2,000 × K) = 6,25,000 + 20,47,500 + 5,50,000
Or, K = Rs 361.25
So, Lowest Price that can be quoted to earn the profit of Rs 6,25,000 (same as current year) is Rs 361.25
Solution 12:
Break- even point (in units) is 50% of sales i.e. 24,000 units.
Hence, Break- even point (in sales value) is 24,000 units × ₨ 400 = ₨ 96,00,000
(i) Break even sales = Fixed Cost / P/V Ratio
Or, ₨ 96,00,000 = Fixed Cost / 25%
(iv) Let desired total Sales (Number of units × Selling price) be x then desired profit is 25% on Cost or 20% on Sales
i.e. 0.2 x
Desired Sales = [Fixed cost + Desired Profit] / PV Ratio
(v) If Break- even point is to be brought down by 4,000 units then Break-even point will be 24,000 units – 4,000
units = 20,000 units
Let Selling price be ₨ x and fixed cost and variable cost per unit remain unchanged
i.e. ₨ 24,00,000 and ₨ 300 respectively.
Break- even point:
Sales revenue = Total cost
20,000 x = (20,000 × ₨ 300) + ₨ 24,00,000
Or, 20,000 x = ₨ 60,00,000 + ₨ 24,00,000
Or x = ₨ 84,00,000 / 20,000 = ₨ 420
Solution 13:
(i) Contribution = Rs 375 – Rs 175 = Rs 200 per unit
𝐅𝐢𝐱𝐞𝐝 𝐂𝐨𝐬𝐭 𝐑𝐬 𝟔𝟓,𝟎𝟎,𝟎𝟎𝟎
Break even Sales Quantity = = = 32,500 units
𝐂𝐨𝐧𝐭𝐫𝐢𝐛𝐮𝐭𝐢𝐨𝐧 𝐌𝐚𝐫𝐠𝐢𝐧 𝐩𝐞𝐫 𝐔𝐧𝐢𝐭 𝐑𝐬 𝟐𝟎𝟎
Solution 14:
(i) Fixed cost for the year
Total Sales (43,200 units x Rs 150 per unit) = Rs 64,80,000
Break Even Sales = Rs 64,80,000 x 25% = Rs 16,20,000
Fixed cost = Break Even Sales x P/V ratio
= Rs 16,20,000 x 20% = Rs 3,24,000
= Rs 3,24,000 + Rs 12,00,000
Rs 30
= 50,800 units
Solution 15:
(i) Variable cost in rupees for year 2019 and 2020
In 2019, PV ratio = 40%
Variable cost ratio = 100% - 40% = 60%
Variable cost in 2019 = Rs 5,00,000 x 60% = Rs 3,00,000
In 2020, sales quantity has not changed. Thus, variable cost in 2020 is Rs 3,00,000.
(ii) Sales for year 2020 in Rupees
In 2020, P/V ratio = 25%
Solution 16:
Working :
𝟔,𝟓𝟎𝟎 𝐮𝐧𝐢𝐭𝐬
Margin of Safety (%) =
𝟔,𝟓𝟎𝟎 𝐮𝐧𝐢𝐭𝐬+𝟑,𝟓𝟎𝟎 𝐮𝐧𝐢𝐭𝐬
= 0.65 or 65%
𝐑𝐬 𝟒𝟖,𝟏𝟖,𝟒𝟓𝟎
Total sales =
𝟎.𝟔𝟓
= Rs 74,13,000
(i) Profit = Total Sales – Total Cost
= Rs 74,13,000 - Rs 56,78,000
= Rs 17,35,000
𝐏𝐫𝐨𝐟𝐢𝐭
(ii) Profit Volume (P/V) Ratio = x 100
𝐌𝐚𝐫𝐠𝐢𝐧 𝐨𝐟 𝐒𝐚𝐟𝐞𝐭𝐲 𝐢𝐧 𝐫𝐮𝐩𝐞𝐞 𝐯𝐚𝐥𝐮𝐞
𝐑𝐬 𝟏𝟕,𝟑𝟓,𝟎𝟎𝟎
= x 100 = 36%
𝐑𝐬 𝟒𝟖,𝟏𝟖,𝟒𝟓𝟎
(iii) Break – even Sales (in Rs) = Total Sales x [100 – Margin of Safety %]
= Rs 74,13,000 x 0.35
= Rs 25,94,550
Or = BEP units x Selling Price per unit
= 3,500 units x Rs 741.30
= Rs 25,94,550
Solution 17:
Computation of Profit Volume Ratio
(Rs in ‘000)
Sales Profit P/V Ratio
Factory
= Rs 13,50,000
54%
= Rs 25,00,000
Solution 19:
(i) Computation of PV ratio, contribution, profit and break-even sales for existing product mix
Products
S T U Total
Selling Price (Rs) 600 800 400
Less: Variable Cost (Rs) 300 400 240
Contribution per unit (Rs) 300 400 160
P/V Ratio (Contribution/Selling price) 50% 50% 40%
Sales Mix 25% 35% 40%
Contribution per rupee of sales (P/V Ratio × Sales Mix) 12.5% 17.5% 16% 46%
Present Total Contribution (Rs 1,20,00,000 × 46%) Rs 55,20,000
Less: Fixed Costs Rs 36,00,000
Present Profit Rs 19,20,000
Present Break Even Sales (Rs 36,00,000/0.46) Rs 78,26,087
(ii) Computation of PV ratio, contribution, profit and break-even sale for proposed product mix
Products
S T M Total
Selling Price (Rs) 600 800 600
Less: Variable Cost (Rs) 300 400 300
Contribution per unit (Rs) 300 400 300
P/V Ratio (Contribution/Selling price) 50% 50% 50%
Sales Mix 40% 35% 25%
Contribution per rupee of sales (P/V Ratio x Sales Mix) 20% 17.5% 12.5%
50%
Proposed Total Contribution (Rs 1,28,00,000 x 50%) Rs 64,00,000
Less: Fixed Costs Rs 36,00,000
Proposed Profit Rs 28,00,000
Proposed Break- Even Sales (Rs 36,00,000/0.50) Rs 72,00,000
Solution 20:
Variable cost per Unit = Rs 16
Fixed Cost per unit = Rs 4, Total Fixed Cost = 2,00,000 units x Rs 4 = Rs 8,00,000
Total Cost per Unit = Rs 20
Selling price Per Unit = Total Cost + Profit = Rs 20 + Rs 4 = Rs 24
Contribution per unit = Rs 24 – Rs 16 = Rs 8
(i) Present Break-even Sales (Quantity) = Fixed Costs = Rs 8,00,000
Contribution margin per unit Rs 8
= 1,00,000 units
Present Break-even Sales (Rs) = 1,00,000 units x Rs 24 = Rs 24,00,000
(ii) Present P/V ratio = 8/24 x 100 = 33.33%
(iii) Revised Selling Price per unit = Rs 24 – 10% of Rs 24 = 21.60
Revised Contribution per Unit = Rs 21.60 – Rs 16 = Rs 5.60
Revised P/V ratio = 5.60 x 100 = 25.926%
21.60
Solution 21:
Working Notes:
(1) Calculation of Cost of Goods Sold (COGS):
COGS = DM + DL + FOH + AOH
COGS = {0.3 COGS + 0.15 COGS + (0.10 COGS + Rs 3,45,000) + (0.02 COGS + Rs 1,06,500)}
Or COGS = 0.57 COGS + Rs 4,51,500
Or COGS = Rs 4,51,500/0.43 = Rs 10,50,000
(2) Calculation of Cost of Sales (COS):
COS = COGS + S&DOH
COS = COGS + (0.04 COS + Rs 1,02,000)
Or COS = Rs 10,50,000 + (0.04 COS + Rs 1,02,000)
Or, COS = Rs 11,52,000/0.96 = Rs 12,00,000
(3) Calculation of variable costs:
Direct Material – (0.30 x Rs 10,50,000) Rs 3,15,000
Direct labour – (0.15 x Rs 10,50,000) Rs 1,57,500
Factory Overhead – (0.10 x Rs 10,50,000) Rs 1,05,000
Administration OH – (0.02 x Rs 10,50,000) Rs 21,000
Selling & Distribution OH – (0.04 x Rs 12,00,000) Rs 48,000
Rs 6,46,500
(4) Calculation of total fixed costs:
Factory Overheads Rs 3,45,000
Administration OH Rs 1,06,500
Selling & Distribution OH Rs 1,02,000
Rs 5,53,500
Solution 22:
(i) Computation of PV ratio, contribution and break-even sales for existing product mix
Products
Total
S T U
Selling Price (Rs) 600 800 400
Less: Variable Cost (Rs) 300 400 240
Contribution per unit (Rs) 300 400 160
Products
S T M Total
Selling Price (Rs) 600 800 600
Less: Variable Cost (Rs) 300 400 300
Contribution per unit (Rs) 300 400 300
I 30 94,500 2 1,89,000
(3,15,000 kg. × 30%)
II 50 1,57,500 3 4,72,500
(3,15,000 kg. × 50%)
III 20 63,000 4 2,52,000
(3,15,000 kg. × 20%)
Total 3,15,000 9,13,500
Solution 2:
Maximum Capacity in a budget period
= 50 Employees × 8 Hrs. × 5 Days × 4 Weeks = 8,000 Hrs.
Budgeted Hours
40 Employees × 8 Hrs. × 5 Days × 4 Weeks = 6,400 Hrs.
Actual Hrs. = 6,000 Hrs. (given)
Standard Hrs. for Actual Output = 7,000 Hrs.
Budget No. of Days = 20 Days = 20 Days (4 Weeks x 5 Days)
Actual No. of Days = 20 – 1 = 19 Days
𝐁𝐮𝐝𝐠𝐞𝐭𝐞𝐝 𝐡𝐨𝐮𝐫𝐬
4. Standard Capacity Usage Ratio = x 100
𝐌𝐚𝐱. 𝐩𝐨𝐬𝐬𝐢𝐛𝐥𝐞 𝐢𝐧 𝐭𝐡𝐞 𝐛𝐮𝐝𝐠𝐞𝐭𝐞𝐝 𝐩𝐞𝐫𝐢𝐨𝐝
𝟔,𝟒𝟎𝟎 𝐡𝐨𝐮𝐫𝐬
= x 100 = 80%
𝟖,𝟎𝟎𝟎 𝐡𝐨𝐮𝐫𝐬
𝟔,𝟎𝟎𝟎 𝐡𝐨𝐮𝐫𝐬
= x 100 = 75%
𝟔,𝟒𝟎𝟎 𝐡𝐨𝐮𝐫𝐬
Solution 3:
1. Statement Showing Sales Budget for 2020-21
Division Product X Product Y Total
Qty. Rate Amt. (Rs) Qty. Rate Amt. (Rs) Amt. (Rs)
(Rs) (Rs)
East 1,0201 20 20,400 8153 40 32,600 53,000
West 1,4302 20 28,600 1,2254 40 49,000 77,600
Total 1,200 49,000 1,000 81,600 1,30,600
Workings
1. 800 × 112.5% +120 = 1,020 units
2. 1,200 × 107.5% + 140 = 1,430 units
3. 600 × 122.5% + 80 = 815 units
4. 1,000 × 112.5% + 100 = 1,225 units
Solution 4:
(i) Calculation of Budgeted profit for the FY 2019-20
60,000 units
Per unit (Rs) Amount (Rs)
Sales 800.00 4,80,00,000
(A)
Variable Costs:
- Direct Material 300.00 1,80,00,000
- Direct Wages 100.00 60,00,000
- Variable Overheads 100.00 60,00,000
- Direct Expenses 60.00 36,00,000
- Variable factory expenses (75% of Rs 80 p.u.) 60.00 36,00,000
- Variable Selling & Dist. exp. (80% of Rs 40 32.00 19,20,000
p.u.)
(ii) Expense Budget of P Ltd. for the FY 2020-21 at 50% & 60% level
60,000 units 72,000 units
Per Amount Per unit Amount (Rs)
unit (Rs) (Rs)
(Rs)
Sales (A) 880.00 5,28,00,000 880.00 6,33,60,000
Variable Costs:
- Direct Material 360.00 2,16,00,000 360.00 2,59,20,000
- Direct Wages 120.00 72,00,000 120.00 86,40,000
- Variable Overheads 120.00 72,00,000 120.00 86,40,000
- Direct Expenses 72.00 43,20,000 72.00 51,84,000
- Variable factory expenses (75% of Rs 80 p.u.) 72.00 43,20,000 72.00 51,84,000
- Variable Selling & Dist. exp. (80% of Rs 40 p.u.) 38.40 23,04,000 38.40 27,64,800
Total Variable Cost (B) 782.40 4,69,44,000 782.40 5,63,32,800
Contribution (C) = (A – B) 97.60 58,56,000 97.60 70,27,200
Fixed Costs:
- Office and Admin. exp. (100%) -- 13,80,000 -- 13,80,000
- Fixed factory exp. (25%) -- 13,80,000 -- 13,80,000
- Fixed Selling & Dist. exp. (20%) -- 5,52,000 -- 5,52,000
Total Fixed Costs (D) -- 33,12,000 -- 33,12,000
Profit (C – D) -- 25,44,000 -- 37,15,200
Solution 5:
(i) Production Budget of ‘X’ for the Second Quarter
Particulars Bags (Nos.)
Budgeted Sales 1,50,000
Add: Desired Closing stock 33,000
Total Requirements 1,83,000
Less: Opening stock (45,000)
Required Production 1,38,000
(ii) Raw–Materials Purchase Budget in Quantity as well as in Rs for 1,38,000 Bags of ‘X’
Particulars ‘Y’ Mtr. ‘Z’ Mtr. Empty Bags Nos.
Production Requirements 2.5 7.5 1.0
Per bag of ‘X’ 3,45,000 10,35,000 1,38,000
Requirement for Production (1,38,000 × 2.5) (1,38,000 × 7.5) (1,38,000 × 1)
Add: Desired Closing Stock 78,000 1,41,000 84,000
Total Requirements 4,23,000 11,76,000 2,22,000
Less: Opening Stock (96,000) (1,71,000) (1,11,000)
Quantity to be purchased 3,27,000 10,05,000 1,11,000
Cost per mtr./Bag Rs 160 Rs 30 Rs 110
Cost of Purchase (Rs) 5,23,20,000 3,01,50,000 1,22,10,000
Solution 6:
Workings:
Direct Materials:
A: 6 Kg. @ Rs 160 per kg. 960
B: 3 Kg. @ Rs 100 per kg. 300
Labour Cost:
Machine Shop: 4 hrs. @ Rs 140 per hour 560
Assembly Shop: 2 hrs. @ Rs 70 per hour 140
Factory Overheads: 20% of (Rs 560 + Rs 140) 140
Variable Selling & Distribution Expenses 60
Total Variable Cost per unit 2,160
(i) Calculation of number of units of product proposed to be sold and selling price per unit:
Number of Units Sold = Total Variable Cost / Variable Cost per unit
= Rs 1,72,80,000 / Rs 2,160
= 8,000 units
Selling Price per unit = Total Sales Value / Number of Units Sold
= Rs 3,02,40,000 / 8,000 units
= Rs 3,780
Solution 7:
(i) Product-wise Profitability Statement for the FY 2019-20:
Particulars Product-X (Rs) Product-Y (Rs) Total (Rs)
Output (units) 8,000 4,000
Selling price per unit 600 550
Sales value 48,00,000 22,00,000 70,00,000
Direct material 11,20,000 6,30,000 17,50,000
(Rs 140×8,000) (Rs 157.50×4,000)
Solution 8:
(i) Preparation of Production Budget (in units)
October November December January
Demand for the month (Nos.) 40,000 35,000 45,000 60,000
Add: 20% of next month’s demand 7,000 9,000 12,000 13,000
Solution 9:
(i) Statement Showing “Flexible Budget for 3,200 units Activity Level”
Particulars Amount (Rs) Amount (Rs)
Solution 10:
(1) Statement of Cost
For first 6 For further For remaining Total
months 3 months 3 months
(2) (a) Company Should accept the offer as it is above its targeted sales price of Rs 128.45 per toy.
(b) Company Should accept the offer as it is above its targeted sales price of Rs 128.45 per toy.
Solution 11:
Flexible Budget
Activity Level 60% 80% 100%
Production (units) 6,000 8,000 10,000
(Rs) (Rs) (Rs)
Sales @ Rs 100 per unit 6,00,000 8,00,000 10,00,000
Variable Cost 2,10,000 2,80,000 3,50,000
(@ Rs 35 (Rs 30 + Rs 5) per unit)
Solution 12:
Expense Budget of KLM Ltd.
Particulars 50,000 Units 35,000 Units 70,000 Units
(Rs) (Rs) (Rs)
Direct Material 62,50,000 43,75,000 87,50,000
(50,000 x 125) (35,000 x 125) (70,000 x 125)
Direct Labour 25,00,000 17,50,000 35,00,000
(50,000 x 50) (35,000 x 50) (70,000 x 50)
Variable Overhead 20,00,000 14,00,000 28,00,000
(50,000 x 40) (35,000 x 40) (70,000 x 40)
Direct Expenses 7,50,000 5,25,000 10,50,000
(50,000 x 15) (35,000 x 15) (70,000 x 15)
Selling Expenses (Variable)* 10,00,000 7,00,000 14,00,000
(50,000 x 20) (35,000 x 20) (70,000 x 20)
Selling Expenses (Fixed)* (5 x 50,000) 2,50,000 2,50,000 2,50,000
Factory Expenses (Fixed) (15 x 50,000) 7,50,000 7,50,000 7,50,000
Administration Expenses (Fixed) (8 x 50,000) 4,00,000 4,00,000 4,00,000
Distribution Expenses (Variable)** 8,50,000 5,95,000 11,90,000
(17 x 50,000) (17 x 35,000) (17 x 70,000)
Distribution Expenses (Fixed)** (3 x 50,000) 1,50,000 1,50,000 1,50,000
1,49,00,000 1,08,95,000 2,02,40,000
*Selling Expenses: Fixed cost per unit = Rs 25 x 20% = Rs 5
Fixed Cost = Rs 5 x 50,000 units = Rs 2,50,000
Variable Cost Per unit = Rs 25 – Rs 5 = Rs 20
**Distribution Expenses: Fixed cost per unit = Rs 20 x 15% = Rs 3
Solution 13:
(i) Statement of Flexible Budget for the both the products:
Particulars Product X (Rs) Product Y (Rs)
Before new proposal After new proposal Before new proposal After new proposal
Sales unit 2,000 2,200 2,500 2,750
(110% of 2,000) (110% of 2,500)
Sales price per unit 140 140 200 200
Sales Value (A) 2,80,000 3,08,000 5,00,000 5,50,000
Variable cost:
Raw material 60,000 66,000 1,00,000 1,10,000
(30 x 2,000) (30 x 2,200) (40 x 2,500) (40 x 2,750)
Direct labour 40,000 44,000 35,000 38,500
(20 x 2,000) (20 x 2,200) (14 x 2,500) (14 x 2,750)
Variable overhead 30,000 39,600 25,000 30,250
(15 x 2,000) (15 x 120% x 2,200) (10 x 2,500) (10 x 110% x 2,750)
Total variable cost (B) 1,30,000 1,49,600 1,60,000 1,78,750
Fixed cost (C) 50,000 66,000 60,000 77,000
Profit (A - (B+C)) 1,00,000 92,400 2,80,000 2,94,250
(ii) Advise:
a) If both the products are independent then proposal for Product-Y is accepted as the profit for the Product-Y is
increased to Rs 2,94,250 from Rs 2,80,000.
b) If both the products are not independent then proposal for both the products is accepted as profit for both the
products will increase to Rs 3,86,650 from Rs 3,80,000.
Solution 14:
Budget Showing Current Position and Position for 2020-21
Position for 2019-20 Position for 2020-21
A B Total A B C Total
(A+B) (A+B+C)
Sales (units) 2,00,000 1,00,000 – 1,50,000 50,000 2,00,000 –
(Rs) (Rs) (Rs) (Rs) (Rs) (Rs) (Rs)
(A) Sales 64,00,000 56,00,000 1,20,00,00 48,00,000 28,00,000 56,00,000 1,32,00,000
0
Direct Material 16,00,000 12,00,000 28,00,000 12,00,000 6,00,000 12,80,000 30,80,000
Direct wages 8,00,000 8,00,000 16,00,000 6,00,000 4,00,000 8,00,000 18,00,000
Factory 8,00,000 8,00,000 16,00,000 6,00,000 4,00,000 8,00,000 18,00,000
overhea
d (variable)
Other variable costs 800,000 4,80,000 12,80,000 6,00,000 240,000 8,00,000 16,40,000
(B) Marginal Cost 40,00,000 32,80,000 72,80,000 30,00,000 16,40,000 36,80,000 83,20,000
(C) Contribution (A- 24,00,000 23,20,000 47,20,000 18,00,000 11,60,000 19,20,000 48,80,000
B)
Fixed costs
– Factory 16,00,000 16,00,000
– Others 12,80,000 12,80,000
(D) Total fixed cost 28,80,000 28,80,000
Profit (C – D) 18,40,000 20,00,000
Comments: Introduction of Product C is likely to increase profit by Rs 1,60,000 (i.e. from Rs 18,40,000 to Rs 20,00,000) in
2020-21 as compared to 2019-20 even if the demand for Product A & B falls. Therefore, introduction of product C is
recommended.
Solution 15:
Revenue Budget (Flexible Budget) of Maharatna Ltd. for the Year 2022
Particulars PY 2021 CY 2022
A Sales Volume (Tonnes) 4,20,000 4,70,400
[112%×4,20,000]
B Selling Price per tonne (Rs) 23,000 23,000
(Rs in lakh) (Rs in lakh)
C Sales value [A×B] 96,600 1,08,192
D Raw material Cost:
(i) Qty. of Material 9,66,000 10,81,920
[2.3 tonnes × A] (tonnes)
(ii) Price per tonne (Rs) 4,500 4,500
(iii) Total raw material cost (Rs in lakh) 43,470 48,686.40
[(i)×(ii)]
E Wages & Salary Cost:
(i) Wages to casual employees (15% 2,386.80 2,508.47
× 6,000 = 900 employees) [900 × 26 × 12 × Rs 850] [900 × 26 × 12 × Rs 893.33]
(ii) Salary to permanent employees (85% 47,736 51,316.20
× 6,000 = 5,100 employees) [5100 × 26 × 12 × Rs 3,000] [(5100 × 26 × 6 ×
Rs 3,000) + (5100 × 26 × 6
× Rs 3,450)]
(iii) Total wages & salary [(i)+(ii)] 50,122.80 53,824.67
F Power cost:
(i) For production (units) 4,20,000 4,70,400
[60% × 7,00,000] [112% × 4,20,000]
(ii) For employees & offices (units) [40% 2,80,000 2,80,000
× 7,00.000]
(iii) Total Power consumption (units) 7,00,000 7,50,400
[(i)+(ii)]
(iv) Power rate per unit (Rs) 6.00 6.00
[Rs42,00,000 ÷ 7,00,000]
(v) Total power cost [(iii)×(iv)] 42 45.024
G Safety and maintenance Cost 60 67.20
[112% × 60,00,000]
H Diesel cost 1.2 -
I Car Hire charge:
(i) Car hire charge 6 6
(ii) Fuel reimbursement cost - 1.38
[115% × 1.2]
(iii) GST@5% on RCM basis - 0.369
[5%×(i+ii)]
(iv) Total Car hire charge cost [(i)+(ii)+(iii)] 6 7.749
J Depreciation 8,040 6,834
[85% × 8040]
K Total Cost [Sum of D to J] 1,01,742 1,09,465.043
L Profit/ (Loss) [C-L] (5,142) (1273.043)
Solution 16:
Workings
= Rs 86,40,000 / Rs1,080
= Rs 8,000 units
Selling price per unit = Total Sales Value/ Number of Units Sold
= Rs 1,890
Particulars Units
Budgeted Sales 8,000
Add: Closing Stock 3,000
Total requirements 11,000
Less: Opening Stock (2,500)
Required Production 8,500
(b) Total Cost (of maintaining the inventories) when production run size (Q) are 3,600 and 6,000 bearings
respectively
Total cost = Total set-up cost + Total carrying cost.
When run size is 3,600 When run size is 6,000
bearings bearings
Total set up cost = 24,000 x Rs 324 = Rs 2,160 = 24,000 x Rs 324 = Rs 1,296
3,600 6,000
Or,
No. of setups = 6.67 (7 setups)
= 7 x 324 = Rs 2,268
Total Carrying cost ½ x 3,600 x 0.10P x 12 = Rs ½ x 6,000 x 0.10P x 12 = Rs
2,160 3,600
Total Cost Rs 4,320 / Rs 4,428 Rs 4,896
Rs 576/ Rs 468 is the excess cost borne by the firm due to run size not being economic batch quantity.
(c) Inventory holding cost at EBQ = 1/2 Q × C
(when Q = 3,600 bearings) = 1/2 × 3,600 bearings × 0.10P × 12
= Rs 2,160
Solution 2:
Factory Cost Statement of Completed Job
Month Job Materials Direct Factory Overheads Factory Cost
No. Labour (80% of direct
labour cost)
(Rs) (Rs) (Rs) (Rs) (Rs)
September 115 1,325 800 640 2,765
October 115 -- 125 100 225
Total 1,325 925 740 2,990
September 118 810 500 400 1,710
October 118 515 330 264 1,109
Total 1,325 830 664 2,819
September 120 765 475 380 1,620
October 120 665 245 196 1,106
Total 1,430 720 576 2,726
Assumption: - Indirect labour costs have been included in the factory overhead which has been recovered as 80% of the
labour cost.
Solution 3:
(i) Calculation of Overhead Recovery Rate:
Factory Overhead Recovery Rate = ( Factory Overhead 2019 -20 )/( Direct Labour Cost 2019 - 20 ) × 100
= (Rs 30,80,000 / Rs 90,50,000 ) × 100 = 34% of Direct labour
Working Note:
(i) Calculation of Factory Cost in 2019-20
Particulars Amount (Rs)
Opening Stock of Material 15,00,000
Add: Purchase of Material 1,80,50,000
Less: Closing Stock of Material (20,00,000)
Material Consumed 1,75,50,000
Direct Labour 90,50,000
Prime Cost 2,66,00,000
Factory Overhead 30,80,000
Factory Cost 2,96,80,000
Solution 4:
(i) Computation of optimum run size
𝟐×𝐃×𝐒
Optimum run size or Economic Batch Quantity (EBQ) =√
𝐂
Where, D = Annual demand i.e. 5.5% of 18,00,00,000 = 99,00,000 units
Solution 5:
(a) Calculation of Total Cost for the Job:
Particulars Amount (Rs) Amount (Rs)
Direct Material Cost:
-15mm GI Pipe (Working Note- 1) 11,051.28
-20mm GI Pipe (Working Note- 2) 2,588.28
-Other fitting materials (Working Note- 3) 3,866.07
-Stainless steel faucet 3,113.57
15 units × [(6× Rs 204 +15× Rs 209)/21 units)
-Valve 2,472.75 23,091.95
6 units × [(8× Rs 404 +10× Rs 402+ 14 × Rs 424 )] /21 units)
Direct Labour:
-Plumber 18,600.00
[(180 hours × Rs 100) + (12 hours ×
Rs 50)]
-Helper 14,280.00 32,880.00
[(192 hours × Rs 70) + (24 hours × Rs 35)]
-Overheads[Rs 26 × (180 + 192) hours] 9,672.00
Total Cost 65,643.95
Working Note:
1. Cost of 15mm GI Pipe
Date Amount (Rs)
17-08-2020 8 units × Rs 660 4,800.00
28-08-2020 10 units ×[(4×Rs 600+35× Rs 628)/39 units] 6,251.28
11,051.28
Solution 6:
(i) Production Statement
For the year ended 31st March, 2020
Amount (Rs)
Direct materials 18,00,000
Direct wages 15,00,000
Prime Cost 33,00,000
Factory overheads 9,00,000
Cost of Production 42,00,000
Administration overheads 8,40,000
Selling and distribution overheads 10,50,000
Cost of Sales 60,90,000
Profit 12,18,000
Sales value 73,08,000
Calculation of rates:
1) Percentage of factory overheads to direct wages = [Rs 9,00,000 / Rs 15,00,000] x 100 = 60%
2) Percentage of administration overheads to cost of production = [Rs 8,40,000 / Rs 42,00,000] x 100 = 20%
3) Selling & distribution overheads = Rs 10,50,000 x 115% = Rs 12,07,500
Selling & distribution overhead % to cost of production = [Rs 12,07,500 / Rs 42,00,000] x 100 = 28.75%
4) Percentage of profit to sales = [Rs 12,18,000 / Rs 73,08,000] x 100 = 16.67% or, 1/6
Solution 7:
(i) Computation of Optimum Run size of ‘Stents’ or Economic Batch Quantity (EBQ)
√𝟐𝐃𝐒
Economic Batch Quantity (EBQ) =
𝐂
Where, D = Annual demand for the Stents
= 4,00,00,000 × 2.5% = 10,00,000 units
S = Set- up cost per run = Rs 225
C = Carrying cost per unit per annum
= Rs 1.50 × 12 = Rs 18
𝟐 × 𝟏𝟎, 𝟎𝟎, 𝟎𝟎𝟎 × 𝑹𝒔 𝟐𝟐𝟓
EBQ = √
𝟏𝟖
= 5,000 units of Stents
Solution 8:
Job Cost Sheet
Customer Details ——— Job No._________________
Date of commencement —— Date of completion _________
Particulars Amount (Rs)
Direct materials 120
Direct wages:
Deptt. A Rs 4.00 × 4 hrs. Rs 16.00
Deptt. B Rs 4.00 × 7 hrs. Rs 28.00
Deptt. C Rs 4.00 × 2 hrs. Rs 8.00
Deptt. D Rs 4.00 × 2 hrs. Rs 8.00 60
Chargeable expenses 20
Prime cost 200
Overheads
Deptt. A = Rs 12,000 × 100 =100% of Rs 16 Rs 16
Rs 12,000
Deptt. B = Rs 6,000 × 100 = 75% of Rs 28 Rs 21
Rs 8,000
Deptt. C = Rs 9,000 × 100 = 90% of Rs 8 Rs 7.20
Rs 10,000
= Rs 9,000 × 100 = 90% of Rs 8 = Rs 7.20
Rs 10,000
Deptt. D = Rs 17,000 × 100 = 85% of Rs 8 Rs 6.80 51.00
Rs 20,000
Works cost 251.00
Selling expenses = Rs 90,000 ×100 = 30% of work cost 75.30
Rs 3,00,000
Total cost 326.30
Profit (20% profit on selling price i.e 25% of total cost) 81.58
Selling price 407.88
Solution 9:
𝟐𝐃𝐒
Economic Batch Quantity (EBQ) = √
𝐂
Solution 10:
Calculation of Job Price
Particulars Amount (Rs)
Direct materials 1,87,00,000
Direct wages (Rs 80 × 2,400 hours) 1,92,000
𝐑𝐬 𝟒𝟖,𝟎𝟎,𝟎𝟎𝟎 4,80,000
Production overheads ( x 𝟐, 𝟒𝟎𝟎 hrs. )
𝟐𝟒,𝟎𝟎𝟎 𝐡𝐫𝐬.
Production cost 1,93,72,000
Selling and administration overheads 96,860
𝐑𝐬 𝟏𝟖,𝟎𝟎,𝟎𝟎𝟎
( x 𝟏, 𝟗𝟑, 𝟕𝟐, 𝟎𝟎𝟎 )
𝟑𝟔,𝟎𝟎,𝟎𝟎,𝟎𝟎𝟎
Total cost of sales 1,94,68,860
Profit mark-up @ 20% 38,93,772
Price for the job 2,33,62,632
Solution 11:
(a) Optimum production run size (Q)
𝟐𝑫𝑺 √𝟐 × 𝟗𝟔, 𝟖𝟎𝟎 × 𝑹𝒔 𝟓𝟖𝟖
=√ = = 6,160 bearings .
𝑪 𝟎. 𝟐𝟓 × 𝟏𝟐
Rs 1,188/ Rs 1,020 is the extra cost incurred by the company due to run size not being optimum run size.
Solution 13:
(i) Computation of Optimum Run size of ‘Stents’ or Economic Batch Quantity (EBQ)
C
Where, D = Annual demand for the Stents
= 1,00,00,000 × 10% = 10,00,000 units
S = Set - up cost per run
= Rs 450
C = Carrying cost per unit per annum
= Rs 3 × 12 = Rs 36
𝟐 × 𝟏𝟎, 𝟎𝟎, 𝟎𝟎𝟎 × 𝐑𝐬 𝟒𝟓𝟎
EBQ =√
𝐑𝐬 𝟑𝟔
= 5,000 units of Stents
(ii) Minimum inventory holding cost
Minimum Inventory Cost = Average Inventory × Inventory Carrying Cost per unit per annum
= (5,000 ÷ 2) × Rs 36
= Rs 90,000
Solution 14:
(i) Calculation of Overhead Recovery Rate:
Factory Overhead Recovery rate = Factory Overhead in 2020-21 x 100
Rs 90,50,000
Rs 2,96,80,000
Solution 15:
𝟐 ×𝑫 ×𝑺
(i) Optimum run size or Economic Batch Quantity (EBQ) = √
𝑪
Where, D = Annual Demand i.e. 2.15% of 8,00,00,000 = 17,20,000 units
S = Set up cost per run = Rs 4500
C = Inventory holding cost per unit per annum
= Rs 2.5 x 12 months = Rs 30
𝟐 × 𝟏𝟕, 𝟐𝟎, 𝟎𝟎𝟎 𝒖𝒏𝒊𝒕𝒔 × 𝑹𝒔 𝟒, 𝟓𝟎𝟎
EBQ = √ = 22.716 units
𝑹𝒔 𝟑𝟎