ID Task Task Name Duration Start Finish Predecessors24 Dec '23 31 Dec '23 07 Jan '24 14 Jan '24

ish Predecessors24 Dec '23 31 Dec '23 07 Jan '24 14 Jan '24 21 Jan '24 28 Jan '24 04 Feb '24 11 Feb '24 18 Feb '24 25 Feb '24 03 Mar '24 10 Mar '24 17 Mar '24 24 Mar '24 31 Mar '24
Mode W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
0 time schedule 268 days Fri 19-01-24 Tue 26-11-24

1 Mobilization 5 days Mon 05-02-24 Fri 09-02-24

2 Commencement Date 0 days Fri 09-02-24 Fri 09-02-24 1 09-02

3 site setting out 1 day Sat 10-02-24 Sat 10-02-24 2

4 municipality check point(masjemeriya) 1 day Mon 12-02-24 Mon 12-02-24 3

5 Excavation work 11 days Tue 13-02-24 Sat 24-02-24

6 Bulk excavation by excavator 4 days Tue 13-02-24 Fri 16-02-24 4

7 Pit Excavation work by labor 5 days Sat 17-02-24 Thu 22-02-24 6

8 prepare invert level for lean concrete 2 days Fri 23-02-24 Sat 24-02-24 7

9 Sub structur Activity 96 days Fri 19-01-24 Thu 09-05-24

10 Prepare rebar for foundation 4 days Fri 19-01-24 Tue 23-01-24

11 lean Concrete 1 day Mon 26-02-24 Mon 26-02-24 8

12 seting out for mat foundation 1 day Tue 27-02-24 Tue 27-02-24 11

13 Install footing pad formwork 10 days Wed 28-02-24 Sat 09-03-24 12

14 install footing and foundation coulumn rebar 10 days Sat 02-03-24 Wed 13-03-24 13SS+3 days,10

15 cast footing Pad 10 days Wed 06-03-24 Sat 16-03-24 14SS+3 days

16 install footing column formwork 4 days Mon 18-03-24 Thu 21-03-24 15

17 cast foundation coulumn concrete 4 days Wed 20-03-24 Sat 23-03-24 16FS-2 days

18 construct masonary around building 5 days Sat 23-03-24 Thu 28-03-24 17FS-1 day

19 Perforated pipe installation 2 days Fri 29-03-24 Sat 30-03-24 18

20 selected material fill around floundation 5 days Mon 01-04-24 Fri 05-04-24 19

21 place greade beam formwork 2 days Sat 06-04-24 Mon 08-04-24 20,19

22 Install grade beam rebar 2 days Wed 10-04-24 Thu 11-04-24 21FS+1 day

23 Cast grade Beam 1 day Fri 12-04-24 Fri 12-04-24 22

24 selected material fill under hardcore 2 days Sat 13-04-24 Mon 15-04-24 23

25 place hardcore 3 days Tue 16-04-24 Thu 18-04-24 24

26 Prepare and Place rebar for basement slab 1 day Fri 19-04-24 Fri 19-04-24 25

27 cast basement Floor slab 1 day Sat 20-04-24 Sat 20-04-24 26

28 install external formwork for periphery shear wall 7 days Mon 22-04-24 Mon 29-04-24 27

29 install rebar for vertical structures 8 days Thu 25-04-24 Fri 03-05-24 28SS+3 days

30 install internal formwork for vertical structures 10 days Sat 27-04-24 Wed 08-05-24 29SS+2 days

31 cast shearwall and column concrete 3 days Tue 07-05-24 Thu 09-05-24 30FS-2 days

32 Ground Floor Activities 23 days Sat 04-05-24 Thu 30-05-24

33 install formwork in Ground floor slab 8 days Tue 14-05-24 Wed 22-05-24 31FS+3 days

34 Prepare rebar in GF slab,Col and Sw 5 days Sat 04-05-24 Thu 09-05-24 29

35 Place rebar In Ground floor slab 4 days Thu 23-05-24 Mon 27-05-24 34,33

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: time schedule
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Thu 25-01-24
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 1
ID Task Task Name Duration 31 Mar '24 07 Apr '24 14 Apr '24 21 Apr '24 28 Apr '24 05 May '24 12 May '24 19 May '24 26 May '24 02 Jun '24 09 Jun '24 16 Jun '24 23 Jun '24 30 Jun '24 07 Jul '24 14 Jul '24 21 Jul '24 28 Jul '24
Mode T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
0 time schedule 268 days

1 Mobilization 5 days

2 Commencement Date 0 days

3 site setting out 1 day

4 municipality check point(masjemeriya) 1 day

5 Excavation work 11 days

6 Bulk excavation by excavator 4 days

7 Pit Excavation work by labor 5 days

8 prepare invert level for lean concrete 2 days

9 Sub structur Activity 96 days

10 Prepare rebar for foundation 4 days

11 lean Concrete 1 day

12 seting out for mat foundation 1 day

13 Install footing pad formwork 10 days

14 install footing and foundation coulumn rebar 10 days

15 cast footing Pad 10 days

16 install footing column formwork 4 days

17 cast foundation coulumn concrete 4 days

18 construct masonary around building 5 days

19 Perforated pipe installation 2 days

20 selected material fill around floundation 5 days

21 place greade beam formwork 2 days

22 Install grade beam rebar 2 days

23 Cast grade Beam 1 day

24 selected material fill under hardcore 2 days

25 place hardcore 3 days

26 Prepare and Place rebar for basement slab 1 day

27 cast basement Floor slab 1 day

28 install external formwork for periphery shear wall 7 days

29 install rebar for vertical structures 8 days

30 install internal formwork for vertical structures 10 days

31 cast shearwall and column concrete 3 days

32 Ground Floor Activities 23 days

33 install formwork in Ground floor slab 8 days

34 Prepare rebar in GF slab,Col and Sw 5 days

35 Place rebar In Ground floor slab 4 days

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: time schedule
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Thu 25-01-24
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 4
ID Task Task Name Duration 31 Mar '24 07 Apr '24 14 Apr '24 21 Apr '24 28 Apr '24 05 May '24 12 May '24 19 May '24 26 May '24 02 Jun '24 09 Jun '24 16 Jun '24 23 Jun '24 30 Jun '24 07 Jul '24 14 Jul '24 21 Jul '24 28 Jul '24
Mode T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
36 EL. And SN work+Municipality check 1 day

37 Cast Ground floor slab concrete 2 days

38 1F floor Activities 21 days

39 Seting out for elevation column 1 day

40 Install COL and SW rebar 3 days

41 Prepare Col&SW Formwork 3 days

42 place COL and SW formwork 6 days

43 Install Slab formwork 8 days

44 Prepare floor slab rebar rebar 5 days

45 Install rebar in slab 4 days

46 EL. And SN work+Municipality check 1 day

47 Cast slab and column concrete 1 day

48 2F floor Activities 21 days

49 Seting out for elevation column 1 day

50 Install COL and SW rebar 3 days

51 Prepare Col&SW Formwork 3 days

52 place COL and SW formwork 6 days

53 Install Slab formwork 8 days

54 Prepare floor slab rebar rebar 5 days

55 Install rebar in slab 4 days

56 EL. And SN work+Municipality check 1 day

57 Cast slab and column concrete 1 day

58 3F floor Activities 21 days

59 Seting out for elevation column 1 day

60 Install COL and SW rebar 3 days

61 Prepare Col&SW Formwork 3 days

62 place COL and SW formwork 6 days

63 Install Slab formwork 8 days

64 Prepare floor slab rebar rebar 5 days

65 Install rebar in slab 4 days

66 EL. And SN work+Municipality check 1 day

67 Cast slab and column concrete 1 day

68 4F floor Activities 21 days

69 Seting out for elevation column 1 day

70 Install COL and SW rebar 3 days

71 Prepare Col&SW Formwork 3 days

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: time schedule
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Thu 25-01-24
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 5
ID Task Task Name Duration28 Jul '24 04 Aug '24 11 Aug '24 18 Aug '24 25 Aug '24 01 Sep '24 08 Sep '24 15 Sep '24 22 Sep '24 29 Sep '24 06 Oct '24 13 Oct '24 20 Oct '24 27 Oct '24 03 Nov '24 10 Nov '24 17 Nov '24 24 Nov '24
Mode W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
36 EL. And SN work+Municipality check 1 day

37 Cast Ground floor slab concrete 2 days

38 1F floor Activities 21 days

39 Seting out for elevation column 1 day

40 Install COL and SW rebar 3 days

41 Prepare Col&SW Formwork 3 days

42 place COL and SW formwork 6 days

43 Install Slab formwork 8 days

44 Prepare floor slab rebar rebar 5 days

45 Install rebar in slab 4 days

46 EL. And SN work+Municipality check 1 day

47 Cast slab and column concrete 1 day

48 2F floor Activities 21 days

49 Seting out for elevation column 1 day

50 Install COL and SW rebar 3 days

51 Prepare Col&SW Formwork 3 days

52 place COL and SW formwork 6 days

53 Install Slab formwork 8 days

54 Prepare floor slab rebar rebar 5 days

55 Install rebar in slab 4 days

56 EL. And SN work+Municipality check 1 day

57 Cast slab and column concrete 1 day

58 3F floor Activities 21 days

59 Seting out for elevation column 1 day

60 Install COL and SW rebar 3 days

61 Prepare Col&SW Formwork 3 days

62 place COL and SW formwork 6 days

63 Install Slab formwork 8 days

64 Prepare floor slab rebar rebar 5 days

65 Install rebar in slab 4 days

66 EL. And SN work+Municipality check 1 day

67 Cast slab and column concrete 1 day

68 4F floor Activities 21 days

69 Seting out for elevation column 1 day

70 Install COL and SW rebar 3 days

71 Prepare Col&SW Formwork 3 days

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: time schedule
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Thu 25-01-24
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 8
ID Task Task Name Duration28 Jul '24 04 Aug '24 11 Aug '24 18 Aug '24 25 Aug '24 01 Sep '24 08 Sep '24 15 Sep '24 22 Sep '24 29 Sep '24 06 Oct '24 13 Oct '24 20 Oct '24 27 Oct '24 03 Nov '24 10 Nov '24 17 Nov '24 24 Nov '24
Mode W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
72 place COL and SW formwork 6 days

73 Install Slab formwork 8 days

74 Prepare floor slab rebar rebar 5 days

75 Install rebar in slab 4 days

76 EL. And SN work+Municipality check 1 day

77 Cast slab and column concrete 1 day

78 Roof slab Activities 21 days

79 Seting out for elevation column 1 day

80 Install COL and SW rebar 3 days

81 Prepare Col&SW Formwork 3 days

82 place COL and SW formwork 6 days

83 Install Slab formwork 8 days

84 Prepare floor slab rebar rebar 5 days

85 Install rebar in slab 4 days

86 EL. And SN work+Municipality check 1 day

87 Cast slab and column concrete 1 day

88 Water Tanker Slab activities 42 days

89 Seting out for elevation column 1 day

90 Install COL and SW rebar 3 days

91 Prepare Col&SW Formwork 3 days

92 place COL and SW formwork 6 days

93 Install Slab formwork 8 days

94 Prepare floor slab rebar rebar 5 days

95 Install rebar in slab 4 days

96 EL. And SN work+Municipality check 1 day

97 Cast slab and column concrete 1 day

98 dismantle formwork 21 days

99 BLOCK WORK 100 days

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: time schedule
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Thu 25-01-24
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress