Time Schedule - A3
Time Schedule - A3
ish Predecessors24 Dec '23 31 Dec '23 07 Jan '24 14 Jan '24 21 Jan '24 28 Jan '24 04 Feb '24 11 Feb '24 18 Feb '24 25 Feb '24 03 Mar '24 10 Mar '24 17 Mar '24 24 Mar '24 31 Mar '24
Mode W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
0 time schedule 268 days Fri 19-01-24 Tue 26-11-24
8 prepare invert level for lean concrete 2 days Fri 23-02-24 Sat 24-02-24 7
12 seting out for mat foundation 1 day Tue 27-02-24 Tue 27-02-24 11
14 install footing and foundation coulumn rebar 10 days Sat 02-03-24 Wed 13-03-24 13SS+3 days,10
15 cast footing Pad 10 days Wed 06-03-24 Sat 16-03-24 14SS+3 days
17 cast foundation coulumn concrete 4 days Wed 20-03-24 Sat 23-03-24 16FS-2 days
18 construct masonary around building 5 days Sat 23-03-24 Thu 28-03-24 17FS-1 day
20 selected material fill around floundation 5 days Mon 01-04-24 Fri 05-04-24 19
21 place greade beam formwork 2 days Sat 06-04-24 Mon 08-04-24 20,19
22 Install grade beam rebar 2 days Wed 10-04-24 Thu 11-04-24 21FS+1 day
24 selected material fill under hardcore 2 days Sat 13-04-24 Mon 15-04-24 23
26 Prepare and Place rebar for basement slab 1 day Fri 19-04-24 Fri 19-04-24 25
28 install external formwork for periphery shear wall 7 days Mon 22-04-24 Mon 29-04-24 27
29 install rebar for vertical structures 8 days Thu 25-04-24 Fri 03-05-24 28SS+3 days
30 install internal formwork for vertical structures 10 days Sat 27-04-24 Wed 08-05-24 29SS+2 days
31 cast shearwall and column concrete 3 days Tue 07-05-24 Thu 09-05-24 30FS-2 days
33 install formwork in Ground floor slab 8 days Tue 14-05-24 Wed 22-05-24 31FS+3 days
35 Place rebar In Ground floor slab 4 days Thu 23-05-24 Mon 27-05-24 34,33
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: time schedule
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Thu 25-01-24
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
Page 1
ID Task Task Name Duration 31 Mar '24 07 Apr '24 14 Apr '24 21 Apr '24 28 Apr '24 05 May '24 12 May '24 19 May '24 26 May '24 02 Jun '24 09 Jun '24 16 Jun '24 23 Jun '24 30 Jun '24 07 Jul '24 14 Jul '24 21 Jul '24 28 Jul '24
Mode T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
0 time schedule 268 days
1 Mobilization 5 days
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: time schedule
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Thu 25-01-24
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
Page 4
ID Task Task Name Duration 31 Mar '24 07 Apr '24 14 Apr '24 21 Apr '24 28 Apr '24 05 May '24 12 May '24 19 May '24 26 May '24 02 Jun '24 09 Jun '24 16 Jun '24 23 Jun '24 30 Jun '24 07 Jul '24 14 Jul '24 21 Jul '24 28 Jul '24
Mode T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
36 EL. And SN work+Municipality check 1 day
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: time schedule
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Thu 25-01-24
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
Page 5
ID Task Task Name Duration28 Jul '24 04 Aug '24 11 Aug '24 18 Aug '24 25 Aug '24 01 Sep '24 08 Sep '24 15 Sep '24 22 Sep '24 29 Sep '24 06 Oct '24 13 Oct '24 20 Oct '24 27 Oct '24 03 Nov '24 10 Nov '24 17 Nov '24 24 Nov '24
Mode W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
36 EL. And SN work+Municipality check 1 day
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: time schedule
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Thu 25-01-24
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
Page 8
ID Task Task Name Duration28 Jul '24 04 Aug '24 11 Aug '24 18 Aug '24 25 Aug '24 01 Sep '24 08 Sep '24 15 Sep '24 22 Sep '24 29 Sep '24 06 Oct '24 13 Oct '24 20 Oct '24 27 Oct '24 03 Nov '24 10 Nov '24 17 Nov '24 24 Nov '24
Mode W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
72 place COL and SW formwork 6 days
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: time schedule
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Thu 25-01-24
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
Page 9