Written Arguments On Behalf of The Respondent (Nhai)
Written Arguments On Behalf of The Respondent (Nhai)
COMPRISING OF:
CLAIMANT RESPONDENT
“…it will be open to the respondent to prove the rebut of the affidavit
evidence of the claimant, and the admissibility of the documents accompanying
thereto, by the cross-examination as well as the liberty to them in accordance
with law to bring on record their evidence including documentary evidence…”
2. Claimant has failed to produce the Video recording of the Project as per
Article 13.6 of the Concession Agreement (CA) despite repeated reminders given
by Respondent during execution and also same has been specifically
asked/demanded during the Cross Examination of the Claimant’s witness.
4. Claimant has also not submitted the entire Audits and accounts as per
Article 33 of CA before the Hon’ble AT in order to suppress the real fact.
Claimant has purportedly not submitted the complete set of EPC Agreement,
and same has been admitted by the Claimant during the Cross-Examination of
the Claimant’s Witness. It is vehemently argued by the Claimant that the
Claimant is entitled to claim on behalf of its EPC contractor. It is to be noted
that in Mapex Infrastructure Pvt. Ltd v. NHAI; 2018 SCC OnLine Del 6664
relied upon by the Claimant, para 19 of the judgment itself states: “However,
for succeeding in the arbitration, it was for MAPEX to show whether under the
terms of the sub-contract/EPC contract, the EPC Contractor was entitled to raise
a claim of prolongation cost and if at all any such claim had been paid by
MAPEX to such EPC Contractor. The claim of prolongation cost was in the nature
of claim of damages for breach of contract under Section 73 of the Contract Act,
therefore, the quantum of loss had to be proved by MAPEX, being the claimant.
Principle of mitigation of loss would also apply to such situation.” It is needless
to mention that in the absence of any requisite proof thereof, the same cannot
be claimed by the Claimant.
5. That as the claimant had failed to furnish any corroborative documents
except to file few one pager statutory auditor certificate (devoid of any
supporting documents and making it per say objectionable/doubtful piece of
document), during the pendency of the arbitration proceedings. On the other
hand, the Respondent had appointed a special/additional auditor to conduct
the special/additional audit in accordance with provisions of the Concession
Agreement dated 03.09.2020. The said decision was also intimated to the
Claimant. The Special Auditor, conducted the audit and after giving ample
opportunity to the Claimant to assist during the audit, had submitted its
Report dated 27.02.2020. The said Special/Additional Audit Report dated
27.02.2020 was placed on record of this Hon’ble Arbitral Tribunal on the very
same day i.e., 27.02.2020 but the Hon’ble Arbitral Tribunal returned the said
Application and Special/Additional Audit Report containing 51 pages during
the arbitral proceedings dated 27.02.2020. Consideration of the above report
could have assisted a lot while doing fair adjudication of the sub-judice matter.
In the said Report, it is clearly mentioned that the Claimant has not
adhered to the financial discipline and failed to act in accordance with terms
and conditions of the Concession Agreement and other relevant agreements in
relation to the subject Project. The Claimant suppressed true facts from this
Hon’ble Tribunal.
7. That after perusal of the records of the subject matter and deposition of
the said Witnesses of the Claimant, it is amply clear that the Claimant is
heavily relying upon the Statutory Auditor Report and certificate issued by him
to the Concessionaire and Auditor of the EPC contractor. The EPC contractor is
nothing but promoters of the Claimant/ Concessionaire Company, a Special
Purpose Vehicle created for execution of the instant Project. The Claimant has
failed to file any authentic contemporaneous record to substantiate its claims
before the Hon’ble Arbitral Tribunal.
8. That the even otherwise, the said Statutory Auditor had no right to give
report after completion of five years from the date of preparing the mutually
agreed Panel of Chartered Accountants, or such earlier period as may be
agreed between the Authority and the Concessionaire.
10. That in order to verify the veracity and credibility of report given by
Statutory Auditor, Respondent even filed an application to summon the
auditor, whose report is the sole basis upon which claimant has wrongfully
quantified his claims, however Ld. AT vide order dated 03.10.19 dismissed the
application. Order dated 3.10.19 also reads that claimant had raised objection
that the Respondent NHAI could have appointed auditor as per Clause 33 of
CA. Surprisingly, when report under clause 33.5 of CA by Additional Auditors
(dated 27.02.2020) was tried to be placed before Ld. AT by moving appropriate
application, the same was rejected upon the vehement opposition of the
claimant. Whereas in the said report, it has already been highlighted and
reported about gross financial wrong doing have been committed by the
claimant.
15. The burden of proof is upon the Claimant to prove their alleged claims
during the arbitral proceedings but they have miserably failed to prove its
claims during the arbitral proceedings.
16. The alleged claims of the Claimant are barred by limitation as well on two
counts. (i) The Claimant neither raised its claims within stipulated period as
provided under the Concession Agreement dated 03.09.2010 (ii) nor followed
the manner in which such claims could have been raised within the stipulated
period of time.
17. No claims have been raised by the Claimant either during the
construction period or before the issuance of Provisional Commercial Operation
Date (PCOD) or before entering into the said Supplementary Agreements or
before taking benefits under the said Agreement. Further, the Claimant has not
followed the proper procedure of the Article 44 of the CA. Hence, no claims of
the Claimant are maintainable.
18. That the Claimant did not follow the procedure to the dispute resolution
as envisaged in Article 44 of the Concession/Contract Agreement (CA) dated
03.09.2010 and therefore, the present arbitration proceedings is not
maintainable.
19. The present claim of the Claimant is not maintainable as the Claimant
entered into settlement/supplementary agreement with the Respondent with
respect to certain issues crop up during execution of the project in accordance
with terms and conditions of the said CA. The parties to the present lis are
bound by the terms and conditions of the said settlement/supplementary
agreements. The alleged claims as raised by way of the present Statement of
Claim have no basis in view of the said settlement/supplementary agreements
signed/executed between the parties to the present lis as the Claimant has
admittedly benefited out of the said supplementary agreements. Therefore, no
cause of action arises to invoke the present arbitration. Further, In M/s.
Double Dot Finance Ltd. Vs. M/s. Goyal MG Gases Ltd. ILR (2005) I Delhi
161 the court has held that mere allegations of financial distress doesn’t
amount to duress and coercion. The court has further held that the contract
and agreement would only amount to duress or coercion if the party has no
other alternative or legal resource and had not taken any steps to avoid the
same.
21. That as per Article 48 of the Concession Agreement, the ‘appointed date’
means the date on which financial close is achieved or an earlier date that the
parties may by mutual consent determine and shall be deemed to be the date
of commencement of the Concession Period. It is pertinent to mention that
every Condition Precedent shall have been satisfied or waived prior to the
‘Appointed Date’ and in the event all Conditions Precedent are not satisfied or
waived, as the case may be, the ‘Appointed Date’ shall be deemed to occur only
when each and every Condition Precedent is either satisfied or waived, as the
case may be.
22. As per the relevant terms and conditions of the contract agreement there
is no word signifying the substantial completion of the Conditions Precedent as
pleaded by the Claimant in SOC. Therefore, the Claimant has not achieved the
Conditions Precedent under the Concession Agreement within the time line as
mentioned in the said contract.
23. The delay occurred in the project due to several breaches, non-
compliance of the terms and conditions of the Concession Agreement by the
Claimant. The Respondent fulfilled its obligations under the Concession
Agreement within feasible timeline as provided therein subject to force majeure
and other prevailing conditions beyond the control of the Respondent. The
requisite land was provided to the Claimant as and when required for smooth
execution of the work assigned under the Concession Agreement. However, it is
the Claimant who had miserably failed to execute its own part of obligations
under the Concession Agreement, and therefore, in order to escape its liability,
started writing unwanted and meritless letters to the Respondent.
24. The Respondent had initiated the due process for selection of the
Independent Engineer within due time. In the meanwhile, the Respondent was
fulfilling its obligations under the Concession Agreement as envisaged for the
Independent Engineer. The Project Director, PIU-Muzaffarpur had been acting
as Independent Engineer with effect from 29.03.2011. With effect from
30.08.2011, M/s. Intercontinental Consultants and Technocrats Pvt. Ltd.
(hereinafter referred to as ‘ICT’) appointed to work as an Independent Engineer
during the Concession Period as per the provisions of Concession Agreement
dated 03.09.2010. Moreover, the Claimant never objected to the Project-
Director acting as an Independent Engineer for the interregnum period till
appointment of ICT as an Independent Engineer. It is pertinent to mention that
the commencement of the work by the Claimant had not been started till the
appointment of Project Director as an Independent Engineer. Therefore, the
alleged delay in appointment of the Independent Engineer has no material
impact on the progress of the Project. The Claimant failed to establish, that
how they suffered due to nominal delay in appointment of Independent
Engineer.
25. Without prejudice to the above, the Claimant had explicitly waived off all
its objections regarding timely execution of conditions precedent as per
Concession Agreement. Now, this objection is only an afterthought and barred
by principle of estoppels and limitation.
26. Without prejudice to the above, it is submitted that the Claimant could
raise its claims/disputes only in accordance with provisions of Concession/
Contract Agreement dated 03.09.2010 especially in accordance with Article 35,
Article 33 and Article 44 of the said CA. It is submitted that the present Claims
of the Claimant are not in accordance with the provisions of Article 35 read
with Article 33 and Article 44 of the Concession Agreement.
27. The requisite RoW had been provided to the Claimant to execute the
work assigned under the contract. The Respondent always tried its best to
comply with the obligations under the Concession Agreement in true letter and
spirit in accordance with the facts and circumstances of the relevant time
period keeping in view prevailing force majeure conditions. The letters had
been written by the Claimant to save its own skin from the liability arisen due
to its non-compliance with the Conditions Precedent in timeline manner. Since
the Claimant did not fulfil/perform its obligations under the contract and
therefore, unnecessarily started blaming the Respondent for their own default
during execution of the project. It is submitted that the Hon’ble Supreme Court
in CIVIL APPEAL NOS. 39763977 OF 2020 in Project Director, Project
Implementation Unit Vs. P.V Krishnamoorthy and ors. decided on
08.12.2020, has specifically observed that “the available ROW in existing lane
road varies between 12 mtrs. to 24 mtrs. maximum.” And the required ROW for
4/6/8 lanes is required to be 40-60 mtrs. minimum. It is submitted that the
Claimant has been misleading the Ld. Tribunal with time and again misguiding
the Ld. AT by saying that for making 2 lane roads in the instant project, the
requirement was of 40/60 Mtr. ROW under the contract.
28. The Respondent never been silent on any genuine request of the
Claimant for smooth execution of the project. The Claimant had been only
interested in writing repeated letters without any cause to write the same. The
Respondent had done its obligations of inspection under the contract. The
requisite land was handed over to the Claimant within time frame and the work
was never stopped due to non-handing over of the requisite stretch of land to
the Claimant. The project was primarily delayed due to inaction on the part of
the Claimant and force majeure conditions prevalent at the relevant time and
not otherwise. The dispute with the land owners had no direct bearings on the
smooth execution of the project as the length upon which the work had to be
executed was an operational highway and enough land was available to execute
the scope of work given under the Concession Agreement. The Claimant herein
is only trying to hide its own lapses in execution of the project in a timeline
manner. The project was delayed due to inaction on the part of the Claimant
and not otherwise. The dispute with the land owners had no direct bearings on
the smooth execution of the project as the length upon which the work had to
be executed was an operational highway and enough land was available to
execute the scope of work given under the Concession Agreement. The
Claimant herein is only trying to hide its own lapses in execution of the project
in a timeline manner.
29. The Claimant neither pleaded what steps they took to mitigate the
alleged losses while executing the work nor the same are supported by any
cogent evidence during the arbitral proceedings.
30. The alleged Claims of the Claimant are bogus as the basis of such claims
are not pleaded in the Statement of Claim, the details of quantification and
arriving of such claims are not mentioned in the pleadings of the Claimant and
also the same are not supported by any contemporaneous records as well as
any cogent evidence. The alleged statutory/audit reports were only filed at the
stage of evidence without following the due process of law that too when
respondent’s interest was badly affected and no opportunity was there to revert
the same. Most of the claims of the Claimant are overlapping/duplicate in
nature. Even during the cross-examination, the Claimants witness failed to
provide any answer to specific questions pertaining to the contemporaneous
and other relevant records pertaining to its alleged claims and why they opted
not to produce any contemporaneous and relevant documents during the
arbitral proceedings.
32. It is submitted that the Claimant had not placed any authentic
document as a proof of claim at the time of filing of statement of claim,
rejoinder or even till the date of admission and denial of documents.
Claimant’s failure can also be assessed by merely observing that following
documents pertaining various claims which are very vital to ascertain the
quantification are missing especially:
PART-I:
Claim A1.1 which reads Costs and losses arising out of the additional
interest during the construction:
To prove the calculation of the interest under this head, the Claimant
has filed merely a single page false and fabricated Statutory Auditor’s Report
dated 03.05.2017 along with the affidavit of evidence marked as annexure
CW 1/8. It is needless to mention that despite the same is of dated
03.05.2017, the Claimant has consciously opted to submit along with
evidence and not along with any documents running in more than several
thousand pages at the time of pleadings. The same was placed solely due to
the fact that Statutory Auditor’s Report dated 03.05.2017 is false, fabricated
and bereft of any reliable value and in accordance with CA. The document is
mischievously placed as an afterthought. In addition to the above, the
Claimant has miserable failed to produce the following documents as well in
support of the claim such as:
Complete bank statement of Escrow Account Number SBI-
00000031640558160 and ICICI Bank Account No. 000805016433 of NBHL
which could easily reflect their alleged inflow, outflow and/or interest liability
by giving accompanying detailed report on that.
Details of alleged loan such as how much amount of loan taken, statement of
loan account, Name of the bank, Outstanding loan amount on which the
interest is charged upon, Rate of interest charged on the said outstanding
loan amount (annex C-16) along with the sanction letter of the bank etc.
Details of interest debited from the escrow accounts.
Fabrication of fabricated of Statutory Auditor’s Report dated 03.05.2017 can
also be ascertained by perusing on its face value. For the sake of argument,
even if assume that there was delay than also, it is also important to note
that in Financial model provided at the time of concession agreement signed
on 03rd September 2010, Schedule III. Project cost and Financial Plan,
Interest During Construction had been shown Rs. 56 Crores for 910 days. If
we assume and calculate the interest for the delayed days of 582 days on the
basis of calculation provided by the concessionaire, it comes to merely 35.82
Crores instead of 105 Crores.
Claim A.2.1, Cost towards overstay of plant and machinery during extended
period:
Any details about date of Acquisition of equipment, plant and machinery are
not given, Date of Put to use of the equipment is not given; Salvage value of
equipment not provided; Life of equipment of equipment is not mentioned.
tax invoice of the equipment has not been provided
While going through the Annexure C-19 Page 2748 CD-15, it is observed that a
list of plant and machinery has been attached. In column number –D, Capital
cost of equipment is shown but tax invoice of the equipment has not been
provided. Only excel sheet is attached. Calculation of Per unit cost is based
on IS: 11590 which is Guidelines for working out unit rate cost of the
construction equipment used for river valley projects. Since the project
working site was at field/Road, then how this guideline will be applicable to
Road construction projects.
Since EPC contractor is Limited Company, The companies Act, 2013 specify
the rate of depreciation and useful life as per Schedule-II read with Section
123 of The Companies Act, 2013. As per sheet it is observed that depreciation
is charged on original cost while these machines or equipment will be
deployed from the starting of this project and the depreciation must be
charged in earlier period also. As per Schedule II read with section 123 of
Companies Act, 2013, the WDV value of the machine used for the Road
Construction project should be replaced for the depreciation purpose. In view
of this case, the depreciation charged to the respondent is not appropriate
and it should not be charged.
Since repair cost has been taken upto 200% of the Average cost employed of
the equipment which is very fictitious.
When depreciation is charged on the basis of New equipment cost basis then in
the case of new assets, in the early years repairs cost is very minimum or it is
covered in guarantee or in warrantee period which cost nothing to company.
If it is said that project is delayed and upto 2-08-2014, as per BOD reports,
project is completed 95% of its project length, then equipment shall be idle for
some time which cost nothing or very minimum cost of maintenance only.
Repair cost is taken on the basis of running hours of equipment which is on
very higher side. Similarly, the cost of supplies used for the purpose of repairs
also not justified at the rate of 10% of repair & maintenance cost.
Claim A.2.2 Cost towards overhead incurred by the EPC contractor Rs. 23.32
Crores:
The claimant has not provided anything including the Financial statements,
vouchers or ledger along with Balance Sheet of EPC contractor.
Claim A.2.3 Cost towards inflation of the cost of materials for the period of
overstay:
The claimant has not provided anything including detailed data of purchase
of HSD and other material.
Claimant has claimed loss of profit to the EPC contractor but when claimant
is asking for the all expenses from the respondent then how it is loss to the
EPC contractor.
Claim A.2.5 Cost and losses incurred during the period 30.06.2015 to
31.07.2018:
The claimant has not provided any documents pertaining to Cost and losses
incurred during the period 30.06.2015 to 31.07.2018.
PART-II:
It is further submitted that the Claimant has further mischievously
magnified its baseless frivolous claim with heavy rates of interest contrary to
the stipulations of the concession agreement which are mentioned hereinbelow:
Claim A1.1 which reads Costs and losses arising out of the additional interest
during the construction:
Claimant cannot give material advance to the EPC contractor, but claimant
had given 51.81 Crores which carries interest to the claimant.
Claim A.1.3 Loss of interest due to the delay in release of Annuities caused
due to prolongation:
Claim A.2.1, Cost towards overstay of plant and machinery during extended
period:
In the case of daily interest on capital cost, interest had been charged on the
assumption basis @ 15%. However, the base rate of SBI in 2013 was around
9.00% to 10.00%.
Claim A.2.2 Cost towards overhead incurred by the EPC contractor Rs. 23.32
Crores:
Massive financial irregularities have been committed in arriving the fictitious
claims such as, entry shown in C-20 on serial No. 38 in CD-15 filed by the
claimant for this claim for example: Sales Tax Expenses is shown amounting
to Rs. 6,87,06,110.00. Whereas, as per accounting purposes Sales Tax is
not an expense. Sales tax is duty which is adjusted against sale and
purchase.
33. It is undisputed that the claim has been brought by the Claimant and
the Respondent has not made any counter claim. It is a settled position of law
that it is the duty of the Claimant to prove its claim with support of evidence
and necessary documents. In State of Rajasthan v. Ferro Concrete
Construction (P) Ltd. 2009 12 SCC 1, the Hon’ble Supreme Court has
observed that merely giving figures of claim amount for plant/machinery etc.
doesn’t suffice as a proof of claim. The court has held that if the claim made by
the contractor is equated with proof of claim then the same is to be considered
as legal misconduct and error apparent on the face of award.
In case titled “Geo Pictures Ltd. v. Neelakandru Gopalakrishnan; 1970
SCC ONLINE KER 52, the Hon’ble Kerala High Court has also observed that
the burden is always on the plaintiff to prove the extent of damages.
In case titled “Pradyuman Kumar Sharma Vs. Shri Jaysagar M. Sancheti ;
Bombay High Court in Arb Petition No. 300-303 Of 2012” Hon’ble Bombay
high court has held that if a document produced before the arbitral tribunal is
not proved, the same cannot be considered as a piece of evidence.
2. The initial project cost was calculated to be Rs. 512 cr however as per
the financial plan the estimated cost of the project was raised to Rs. 656 cr.
(@pg 802 CD-5)
3. The financing plan was divided into two sources of funds, the first project
equity capital amounting to Rs. 181 cr. Wherein sponsor equity contributions
amounted to Rs. 131 crores along with a short-term loan of rupees 50 crore.
The second source was categorised as loan of Rs. 475 crores from consortium
of banks where SBI was the senior lender. (@pg 814 of CD 5)
4. It is submitted that since the inception of the project itself, the Claimant
was very much aware about the conditions at the ground level and the
Claimant had every opportunity to step out/ opt out from the contract at the
initial stage itself as there had been no financial implications upon the
Claimant since there was no drawdown from the lenders till the appointed date
i.e., commencement of construction work. It is also submitted that with effect
to such termination, the Claimant had every opportunity to recover damages/
compensation in consonance with Article 35 and Article 37 of the Concession
Agreement for incurrence of any initial costs if any. It is submitted that the
only responsibility of the Respondent, apart from damages if any, claimed by
the Claimant with due procedure, was to give the annuity as per the schedule
G of the Concession Agreement. it is further submitted that on bare perusal of
Letter Comprising Bid (which is part of concession agreement) (@page 295
CD3, para 26) it is abundantly clear that the Claimant was fully aware about
all the ground realities of the project and the annuity amount was quoted by
the Claimant itself after taking into consideration all the terms and
conditions stated in the RFP (request for proposal), draft concession
agreement, Claimant’s own estimates of costs and traffic and “Careful
Assessment Of The Site And All The Conditions That May Affect The
Project Cost And Implementation Of The Project”. It is submitted that all
the activities were carefully examined by the Claimant before entering into the
contract.
2. It is submitted that under Article 7.1 (C) and (f) (@page 63 of CD 2) the
Claimant had warranted that it has the financial standing and capacity to
undertake the project in accordance to the terms of the Agreement and the
information furnished in the bid is updated till the date of this agreement and
are true and accurate in all respects. However, it is already represented
hereinabove that the Claimant has violated the terms and conditions of the
Agreement by not providing true and correct information with regards to
following the financial package, maintaining debt equity ratio before
commencement of the construction work under the project.
8. The Claimant has relied upon two case laws i.e., SREI Infrastructure
Finance Ltd. V. Tuff Drilling Private Limited 2018 11 SCC 470 and ITI v.
Siemens Public Communication Network 2020 5 SCC 510 that the Ld.
Tribunal is bound by the basic fundamental principles of CPC and Evidence
law. However it is need less to mention that in para 17,26 and 27 of SREI
Infrastructure Finance Ltd. V. Tuff Drilling Private Limited itself observed by
the Hon’ble Court that the arbitral tribunal need not to apply CPC and
Evidence in its complete rigour and has the power to travel beyond the above
laws in the interest of equity and justice and/or in the event of agreement
between the parties. It is pertinent to mention that the tribunal had itself
modified the procedure vide its order dated 07.02.2019 under which the
Respondent had conducted its pleadings, evidence and cross examination etc.
D. Financial Close:
3. It is also to be noted that in the instant case, despite of the fact that not
even single penny was to be spent on the project before the appointed date, the
Claimant had already advanced Rs. 42.8 Crores to the EPC Contractor (@page
707 CD 5) above that before the appointed date the Claimant has The same
has been brought out in the cross examination of CW1 RM Agarwal(Question
no. 335- 340) (@page 1148 CD8 dated 29th April 2011). It is further
pertinent to note that even the short-term loan of Rs. 50 Cr which was
raised by Claimant NBHL at initial stages as a drawdown on 24.05.2011
(@pg 705,706 CD-5) even before the appointed date however it was to be taken
in the Year 2014 (@page 814) i.e., projection of cash flow. Further, the same
has been brought out in the cross examination of CW1 RM Agarwal (@question
336, 338). It is to be remembered as mention earlier that any deviation from
the financial package and financial model should only be done with the
approval of Respondent, however no such approval was taken.
6. It is submitted that vide letter of the Senior Lender (@page 627 CD5) the
approval of financial close deemed to be given subject to the obligations of the
condition precedents fulfilled by the Respondent. Though the financial close
was not achieved by this letter as already explained earlier, it is imperative to
note that if the ROW with respect to two laning of the project would have been
an issue to such an extent that a huge claim is brought out by the Claimant on
the same, the Claimant would not have represented the availability of land
@page 1560, the appointed date would not have been achieved, the Claimant
would not have been able to proceed with work, achieve milestones etc. Further
as per letter of Claimant dated 11.07.2011 (@page 1211 CD8) it is to be noted
that express waiver has been granted to the Respondent with respect to
conditions precedent and based on the same letter, the Respondent vide letter
dated 17.08.2011 the appointed date was agreed upon along with the mutual
waiver of NHAI. Therefore, it can also be said that even the financial closure
was subjected to condition precedent and that is why mututal waiver was
agreed upon by the partied in order to achieve financial close and appointed
date.
F. TREE CUTTING-
5. It is submitted that the punch list items which were put into the
supplementary agreement wherein the Claimant was not able to complete the
work, the same were to be governed by Article 14.4 of the Concession
Agreement (@page 84 CD2). It is submitted that the Claimant further failed to
complete the punch list items due to which damages were deducted by the
Respondent from the annuities paid to the Claimant under Article 14.4.1 of the
Concession Agreement.
8. The Claimant didn’t make any punch list so the Independent Engineer
vide letter dated 11.05.2015 sent the list of punch list work. It is submitted
that the IE deviated from the requirement of 14.3.1 and granted of PCOD
merely showing the physical progress on authority of some letter of NHAI which
is not there on record (@page 2418).
In view of the above, it is amply clear that the Claimant have placed
highly concocted, non-substantiated and fictitious claims which are bereft from
any supportive documents. No claims have been proved during the instant
arbitral proceedings and therefore, liable to be rejected with exemplary cost.
Respondent expenses:
1. The respondent has suffered huge legal expenses in pursuing the above
titled arbitration proceeding. Expenses of the respondents are as follow:
a) Arbitrators fee:
b) Lawyer’s fee: -
c) Venue booking for Ld. AT’s hearing and steno charges:
d) Other miscellaneous expenses: -
PRAYER
It is therefore most respectfully prayed that this Hon’ble Tribunal may be
pleased to reject all claims of the Claimant and refund the legal expenses of
NHAI amounting Rs. ……….; and imposed cost upon the Claimant for raising of
unsubstantiated/bogus claims
RESPONDENT
THROUGH
(BALENDU SHEKHAR)
Counsel for Respondent (NHAI)
Office: - LB-17, Gauri Sadan, Plot No.5,
Hailey Road, New Delhi-110001
Place: New Delhi
Date: 08.01.2021