"Construction of Residencial Building -Jana Residency,at Sanjayanagar,Bengaluru"

Client :
Mr.PradeepJana and Mrs.Vidya
Jana Residency
Sanjayanagara,Bengaluru
Contact:9632488011 /8699333022

Contractor:
Sri Vinayaka Constructions
#13/A pipeline road MSR nagar
Bangalore 560054
Contact: 6360976069

Abstract-RA Bill No.1 st & Part Date:24.07.2024


S. Rate Amount Upto previous Bill This Bill Upto date Bill
DESCRIPTION UNIT QTY
No. Rs. P. Rs. P. Qty Amount Qty Amount Qty Amount

A EARTHWORK

EARTHWORK EXCAVATION for foundations in all sorts of soils and depth with
necessary shorting etc., including filling back excavated earth to sides of foundations in
1
layers 150mm thick, carting away surplus earth/ stacking within the premises as directed.
Only PCC measurement shall be measured and paid for excavation.

a. From 0.00 to 2m depth for footings, sump tank, rainwater storage tank and rainwater
Cft 5408 10 54,075 12723.74 1,27,237 12723.74 1,27,237
harvesting pit

b. From 0.00 to 0.75m depth for compound wall SSM Cft 448 10 4,484 - 0 -

EARTH FILLING with available EXCAVATED EARTH inside plinth in layers of 150mm
2 Cft 3928 12 47,136 13907.48 1,66,890 13907.48 1,66,890
thick, consolidating each deposited layer by ramming, watering etc., complete

EARTHFILLING with approved EARTH brought from outside for inside plinth in layers of
3 Cft 4328 25 1,08,196 1276.61 31,915 1276.61 31,915
150mm thick consolidating each deposited layer by ramming, watering etc., complete

Providing and injecting chemical emulsion for pre-constructional ANTI TERMITE


TREATMENT by spraying chemicals as per IS:6313-1981 and in accordance with
manufacturer's specifications, creating a chemical barrier under and alround the columns
4 Sft 2131 10 21,310 1523.73 15,237 1523.73 15,237
pits, wall trenches, top surface of plinth filling, junction of wall and floor, along the external
perimeter of the building etc., complete and as directed. (Only Plinth Area of the Building
at Ground floor shall be measured)

1of3
S. Rate Amount Upto previous Bill This Bill Upto date Bill
DESCRIPTION UNIT QTY
No. Rs. P. Rs. P. Qty Amount Qty Amount Qty Amount

B PLAIN CEMENT CONCRETE

Providing and laying PCC 1:4:8 (1 cement: 4 coarse sand: 8 graded stone aggregate
1 40mm & down size) in FOUNDATIONS of walls, columns etc., including consolidation, Cft 250 125 31,268 238.08 29,760 238.08 29,760
necessary formwork, curing etc., complete

Providing and laying PCC 1:4:8 (1 cement: 4 coarse sand: 8 graded stone aggregate
2 40mm & down size) in BELOW FLOORS and other locations etc., including Cft 433 125 54,063 474.14 59,268 474.14 59,268
consolidation, necessary formwork, curing etc., complete

Providing and laying PCC 1:3:6 (1 cement: 3 coarse sand: 6 graded stone aggregate
20mm nominal size) for PLINTH PROTECTION/ PAVINGS all round building to an
3 average thickness of 75mm over a sub-base of well compacted earth including finishing Cft 326 125 40,700 138.83 17,354 138.83 17,354
the exposed surfaces in CM 1:4 (1 cement: 4 fine sand) 15mm thick with a floating coat
of neat cement, necessary formwork, consolidation, curing etc., complete

Providing and laying PCC 1:2:4 (1 cement: 2 coarse sand: 4 graded stone aggregate
20mm nominal size) for SILLS, COPINGS etc., with necessary centring and shuttering,
4 Cft 18 140 2,462 - 0 -
consolidation, curing etc., complete
a) SILLS, COPINGS,window etc.,

C REINFORCED CEMENT CONCRETE

Providing and laying Reinforced Cement Concrete of mix as specified with necessary
centring and shuttering, compacting with vibrators, curing excluding steel reinforcement
work etc., complete (Design mix to be approved by the Structural Consultants) for

1 RCC M25 Grade for Footings, Raft/ Combined footings Cft 858 210 1,80,114 1400.85 2,94,179 1400.85 2,94,179

2 RCC M25 Grade for Pedestals Cft 121 210 25,468 384.92 80,833 384.92 80,833

3 RCC M25 Grade for Columns

Ground Floor Cft 211 425 89,620 205.03 87,138 205.03 87,138

Mezzaine Cft 199 450 89,620 - 0 -

4 RCC M25 Grade for Plinth Beams Cft 356 415 1,47,762 317.96 1,31,953 317.96 1,31,953

D STEEL REINFORCEMENT

Providing T.M.T steel reinforcement for R.C.C work including straightening, cutting,
bending, hooking, placing in position, lapping and / or welding wherever required, tying
1 MT 36 82000 29,80,413 6.774 5,55,468 6.774 5,55,468
with binding wire and anchoring to the adjoining members wherever necessary complete
as per design specifications

M DEVELOPMENT WORKS: 0 -

2 Rainwater Harvesting pit with concrete rings and filling of sand and aggregates Nos 10000 2.65 26,500 6050 16,033 6050 16,033

2of3
S. Rate Amount Upto previous Bill This Bill Upto date Bill
DESCRIPTION UNIT QTY
No. Rs. P. Rs. P. Qty Amount Qty Amount Qty Amount

3 Providing and fixing of PVC rungs(ladder) for access,to the sump tank as per detail Nos 12 200 2,400 10.00 2,000 10 2,000

4 Providing and fixing of ladder for access,to the Overhead tank as per detail Ls 2 13,200 26,400 0 -

Providing and fixing in position two PVC OVER HEAD TANKS of 2000ltrs capacity each,
5 with RCC bottom slab, inlet and outlet connections, unions, etc., complete and as Ltrs 4000 8.50 34,000 0 -
directed.

Add items

1 Excavated soil disposed at the out side Load 5,500.00 12 66,000 12 66,000

SUB TOTAL 1,88,62,497 - 16,81,265 16,81,265

ELECTRICAL AT 10% 18,86,250

PLUMBING AT 10% 18,86,250

Steel GST Amount 78159 78159

TOTAL 2,26,34,997 17,59,424 17,59,424