CPM & Pert
CPM & Pert
1.
2.
3.
4.
5.
6.
Path
Activities Length
1-2-5-7-8
ADIK
13
1-3-5-7-8
BEIK
21
1-3-7-8
BGK
17
1-3-6-8
BFJ
22CRITICAL
PATH
1-4-6-8
CHJ
19
A2
I2
E6
B7
G4
C8
F 10
H6
K6
J5
Total float
= Latest finish time of the activity
Earliest finish time of the activity
Free float
= Earliest start time of the next
activity Earliest completion time of
the activity
Interfering float
= Total float Free float
lnF(
IF(L
TF
FF( Esn
F(LF- Esn ESn
-EF) LFp
EF)
)
-D)
i-j
ES
EF
LS
LF
1-2
11
1-3
1-4
11
2-5
11
14
3-5
13
14
3-6
10
17
17
3-7
11
12
16
4-6
14
11
17
5-7
13
15
14
16
6-8
17
22
17
22
7-8
15
21
16
22
Obtain
critical
path
using
expected times and identify
critical activities
Add
variances
for
critical
activities to get variance for
completion time and find its
square root to get standard
deviation
With expected duration and
Example
12.9
Activity
te
4/9*
15
25/9*
12
16/9
15
20
25
20
25/9
10
18
26
18
64/9*
16
10
16/9
12
16/9*
1/9
1/9*
Critical activities: A B E G I
Project duration = 6+8+18+8+7 =
47 days
Project variance = 4/9 + 25/9 + 64/9 + 16/9 + 1/9
= 110/9
Project Network
E
B
H
C
Involves
use
of
additional
resources with a view to reduce
the project duration
Crashing increases direct cost of
doing
activities
but
reduces
overhead, which is usually a
function of time
It needs information on cost of
reduction of every activity per unit
of time
In crashing, always consider the
critical path and choose the
activity that can be crashed at
least cost
In case of multiple critical paths,
all of them should be considered
for crashing simultaneously