Demolition and Its Method: Seminar (2730001)
Demolition and Its Method: Seminar (2730001)
Demolition and Its Method: Seminar (2730001)
& MANAGEMENT
(BRANCH CODE - 14)
Semester-III
Seminar(2730001)
GUJARAT TECHNOLOGICAL
UNIVERSITY
SNPIT&RC, UMRAKH
PREPARED BY:
DESAI KEVIN U.
150490714005
M.E. (CEM),
S.N.P.I.T.&R.C.,UMRAKH.
GUIDE:
Mrs. NEETU YADAV
M.E. (CEM),Assistant Professor,
Civil Engineering Department,
S.N.P.I.T.&R.C., UMRAKH.
CONTENT
2
INTRODUCTION
STEPS BEFORE DEMOLITION
DEMOLITION METHOD
CASE STUDY
CONCLUSION
REFERENCES
WHAT IS DEMOLITION?
Demolition means dismantling, razing, destroying or wrecking any
WHY DEMOLITION?
The structures which have already passed their design life need to be
DEMOLITION METHODS
6
cost of demolition.
MANUAL METHOD
7
Manual methods are carried out top down, proceeding, in general, from the roof
to ground.
The sequence of demolition may vary, depending on
1.
site conditions and
2. structural elements to be demolished.
DEMOLITION BY MACHINES
9
10
Adequate propping shall be installed at floor levels below the working floor to
11
12
DEMOLITION BY HYDRAULIC
RUSHERS
The crusher attachment breaks the concrete
13
The balling of each section of the structure shall proceed from top to bottom.
Recommended techniques for the wrecking ball operations include (1) Vertical Drop
-free falling of the wrecking ball onto the structure and (2) Swing in line - swinging
15
of the ball in-line with the jib.
A second dragline will normally connect to the ball horizontally to control the ball
motion.
The ball shall be swung into the building and shall strike at the top of the member so
as to avoid the member from falling outside the building.
The jib or boom shall be operated with no less than 3 m above the portion of the
structure being demolished.
Clear space for operation between the crane and the structure being demolished
shall be of the height of structure, with additional distance between crane and
boundary wall for maneuverability.
High strength wire shall be used to allow pullout of the wrecking ball from
potential traps.
To minimize the dust impact on the surrounding area, the structure to be
demolished shall be pre-soaked with water before demolition. Water spraying shall
continue on the structure during demolition.
The operation shall not be performed adjacent to overhead power lines. The site
shall be entirely fenced off to forbid public access.
DEMOLITION BY EXPLOSIVES
16
IMPLOSION
17
18
The explosives are just the trigger for the demolition. It's gravity that brings
falls. Ideally, a blasting crew will be able to tumble the building over on one
19
side, into a parking lot or other open area. This sort of blast is the easiest to
execute, and it is generally the safest way to go.
Tipping a building over is something like felling a tree.
To topple the building to the north, the blasters detonate explosives on the north
side of the building first, in the same way a tree would be chopped into from the
north side if it is to fall in that direction. Blasters may also secure steel cables to
support columns in the building, so that they are pulled a certain way as they
crumble.
Sometimes, a building is surrounded by structures that must be preserved. In
this case, the blasters proceed with a true implosion, demolishing the building
so that it collapses straight down into its own footprint (the total area at the base
of the building).
The basic idea in implosion is to think of the building as a collection of separate
towers.
The blasters set the explosives so that each "tower" falls toward the centre of
the building.
20
When they are detonated in the right order, the toppling towers crash against each
other and all of the rubble collects at the centre of the building.
Another option is to detonate the columns at the centre of the building before the
other columns so that the building's sides fall inward.
Generally speaking, blasters will explode the major support columns on the lower
floors first and then a few upper stories.
In a 20-story building, for example, the blasters might blow the columns on the
first and second floor, as well as the 12th and 15 th floors.
In most cases, blowing the support structures on the lower floors is sufficient for
collapsing the building, but loading columns on upper floors helps break the
building material into smaller pieces as it falls. This makes for easier cleanup
following the blast.
ADVANCED TECHNIQUES
USING ROBOTIC MACHINES
21
22
CASE STUDY
23
A Frontier Hotel is one of the oldest hotel on the streets of Las Vegas, its owner
has decided to demolish it and make a new hotel on it.
The demolition work was given to the most reputed Demolition Expert from Marry
land, USA.
24
For plan to work, Mark planned to use Dynamite for Demolition and planned to
demolish from North to South.
First, they removed the Interior walls, but not fully removed, the have removed
30% of wall area in center, so that whole structure will not collapse suddenly.
The team has done the Test Slot so that they came to know that how much of
Explosive required to demolish whole structure.
They have removed all the Fixtures, and done test of demolition.
On a Ground floor on the foot of wall, the team found major setback, the steel
Rebar, which is very strong and large around 19mm diameter bars, so that they
worry that it cannot be affected by Dynamite.
The Drilling of Holes was started, according to design they have to drill more than
5000 Holes in whole building, and each hole have specific diameter and Depth.
25
The team has tighten the building with the Steel rope, to ensure the collapse
within the blue print.
Mark has calculated that Cables needs to be on just Two floors, 4th and 8th
When the planned to remove side wings, there was a problem, the walls are
wrapped with Asbestos
Super tough steel Container loaded on site to store dynamite, which is placed in
the empty swimming pool of hotel.
All the walls and Columns are wrapped with the wire mash to control the
Derbies, and all the holes are cleaned to place the dynamite.
On the other hand one more team came with huge amount of Explosive, and that
are Pyro technicians.
They have started to lay Dynamite in the holes around 300 holes per day.
Finally the moment has come, and mark has triggered the Explosion, the building
started collapsing from north to south.
After two days, all the debris was settle down and there was no damage to the
surrounding buildings.
The Implosion was the Successful IPLOSION if the History of Las Vegas.
26
CONCLUSION
27
Leads to a safe and controlled demolition for the occupants and neighbourhood.
REFERENCES
28
http://www.implosionworld.com/history.html
www.wikipedia.com
29
THANK YOU