Production planning- Improvement - 2016
- 7 Day rolling plan introduced where there is no rigid planning pattern earlier
M T W T F S S M T W T F S S M T W T F S S M T W T F S S
PLND
Plan entry on Thu
+ Supplier stocking policy changed from
Plan entry on Fri MTS to MTO
+ Dynamic plan changed form 8th day
Plan entry on Sat onwards .
+ Material requirement generated Manually
PLan entry on mon on day to day basis
Slide 2
Material Execution & Planning- Daily Activities
Monday Tuesday Wednesday Thursday Friday
Supplier delivery
confirmation and Risk identification
Slide 3
Production planning-Scope of improvement-2017 -Heijunka
- Currently the DTA production is based on the Batch Qty , resulting in cycle time loss
- Level loading opportunity is identified and working towards to implement it in mid of 2017.
- Targeted to save cycle time by 2.5 mins for Frontier units.