Suggested Meeting Protocol

1. Process flow for each project discussion


a. Project progress will be discussed
b. Following this, issues in the project will be discussed. Project Proponents may briefly
speak on issue clearly mentioning the hurdle faced - 1 min
c. Ministry to respond on the matter with reason for delay (if any) and target date of
completion - 2 min.
d. Project proponents should not mention issues which are not listed on PMG portal as
the Ministry would not be having any response on those issues
2. Please adhere to the above time limits
3. All speakers to keep their mic on mute unless they are speaking, or their project is being
discussed
 

1
PMG Review
PMG MoRTH Review meeting
21 June 2022
Project Order
Project Name
1. Rishikesh-Karnaprayag New Rail Line: 125 km
2. Gevra Road-Pendra Road New Railway Line (135 km)
3. Mau-Ghazipur-Tarighat New Railway Line
4. Char Dham Road Connectivity Improvement - 889 km
5. Four/Six laning of Aunta - Simaria (Ganga Bridge with approach roads) Section of NH -31 from km 197.900 to km
206.050 (Design Chainage) and (Existing Chainage km 204.741 to km 209.945
6. Delhi Mumbai Industrial Corridor (DMIC)
7. Comprehensive Scheme for Strengthening of Transmission and Distribution (T&D) Systems (CSST&DS) in
Arunachal Pradesh and Sikkim
8. BharatNet
9. Sardar Sarovar Project
10. Delhi-Ghaziabad-Meerut Regional Rapid Transit System (RRTS) corridor
11. Etalin Hydro Electric Project (HEP) - 3097 Megawatt (MW)
12. 4 Laning of NH-80 section of Mirza Chauki to Farakka from km. 215.00 to km. 260.00 in the state of Jharkhand
(Package-I) on Hybrid Annuity Mode
13. Balance work of Bareilly-Sitapur section of NH-24 from km .260.000 to km. 419.590

3
Summary of projects to be discussed
Across 4 sectors: Railways, Road & Transport, Real Estate, Power, Metro,
Telecommunications and Agriculture
Project  Number  of Projects Number of Issues Anticipated Investment     
(INR crores)
PRAGATI 7 9 88,072.65
NON-PRAGATI 6 12 1,50,373.64
Total 13 21 2,38,446.27

Time 10 projects 01 issue: Resolved


Overruns Max. at ~8 years 01 issue: Pending with M/o Railways

Cost Overruns 7 projects


Max. at INR 10,804 Cr. 19 issues to be discussed today

4
PRAGATI

5
M/o Railways

6
1. Rishikesh-Karnaprayag New Rail Line: 125 km (#1764)
RVNL - II | PUBLIC | PRAGATI (1/2)

Last PRAGATI Review 27-06-2018

Original Cost (₹ Crores) 16216.0

Revised Cost (₹ Crores) 24659.0 (not yet sanctioned)

Original TDC 31-12-2024

Revised TDC -

Physical Progress (%) 26.0%

Time Overrun (months) -

Cost Overrun (₹ Crores) 8443.0


1. Rishikesh-Karnaprayag New Rail Line: 125 km (#1764)
RVNL - II | PUBLIC | PRAGATI (2/2)

Milestone: Utility Shifting/License/Approval/NOCs


• Issue 7358: Pending diversion of Road (NH-58) at Sumerpur/Tilani in Uttarakhand for railways to start work on
new rail line with MoRTH (14-09-2021)
• Meeting minutes (03-03-2022): NHIDCL informed that work is in progress, and issue resolution will be expedited.

• Issue 7357: Pending diversion of Road (NH-58) at Narkota in Uttarakhand for railways to start work on new rail
line with MoRTH (14-09-2021)
• Meeting minutes (03-03-2022): M/o RTH informed that work is in progress, and issue resolution will be
expedited.
2. Gevra Road-Pendra Road New Railway Line (135 km) (#2095)
IRCON | PUBLIC | PRAGATI (1/2)

Last PRAGATI Review 25-08-2021

Original Cost (₹ Crores) 4970.0

Revised Cost (₹ Crores) 3220.0

Original TDC 31-03-2022

Revised TDC 30-06-2024

Physical Progress (%) 27.0%

Time Overrun (months) 27

Cost Overrun (₹ Crores) -


2. Gevra Road-Pendra Road New Railway Line (135 km) (#2095)
IRCON | PUBLIC | PRAGATI (2/2)

Milestone: Right of Use / Right of Way


• Issue 10128: NOC for Construction of RUB on National Highway at Bilaspur-Katghora Road (19-05-2022)
3. Mau-Ghazipur-Tarighat New Railway Line (#1801)
RVNL - II | PUBLIC | PRAGATI (1/2)

Last PRAGATI Review 26-09-2018

Original Cost (₹ Crores) 1766.0

Revised Cost (₹ Crores) 1766.0

Original TDC 31-03-2024

Revised TDC 31-03-2023

Physical Progress (%) 72.0%

Time Overrun (months) -

Cost Overrun (₹ Crores) -


3. Mau-Ghazipur-Tarighat New Railway Line (#1801)
RVNL - II | PUBLIC | PRAGATI (2/2)

Milestone: Execution
• Issue 8082: Pending finalization of executing agency for approach road (07-12-2021)
• Meeting minutes (03-03-2022): M/o RTH informed that NHAI has been finalized as the implementing agency for
the construction of approach road. The Chair advised RVNL and NHAI to closely coordinate and ensure
completion of the road as per the committed timelines.

• Issue 5095: Pending deposit of Rs 210 cr. for construction of Rail-cum-Road Bridge over Ganga River between
Ghazipur and Tarighat in Uttar Pradesh with MoRTH (13-12-2018)
• Meeting minutes (03-03-2022): M/o RTH informed that they have conveyed the financial sanction to RVNL
through a letter dated 01.02.2022. The Chair advised that project execution should not be affected as in-principle
approval has been given by M/o RTH.
M/o Road Transport and Highways

13
4. Char Dham Road Connectivity Improvement - 889 km (#1529)
MoRTH Dehradun | PUBLIC | PRAGATI (1/2)

Last PRAGATI Review 23-05-2018

Original Cost (₹ Crores) 12070.0

Revised Cost (₹ Crores) 12130.0

Original TDC 31-12-2023

Revised TDC 31-12-2024

Physical Progress (%) 88.25%

Time Overrun (months) 12

Cost Overrun (₹ Crores) 60.0


4. Char Dham Road Connectivity Improvement - 889 km (#1529)
MoRTH Dehradun | PUBLIC | PRAGATI (2/2)

Milestone: Under Litigation


• Issue 3835: Approval and awarding of balance 12 civil works under Char Dham Project pending with MoRTH (20-
09-2016)
• Meeting minutes (03-03-2022): M/o RTH informed that the 12 civil works were pending because of litigation.
Now that the Hon’ble Supreme Court has decided on the matter, M/o RTH has started DPR preparation for these
civil works.
5. Four/Six laning of Aunta - Simaria (Ganga Bridge with approach roads) Section of NH -31 from km
197.900 to km 206.050 (Design Chainage) and (Existing Chainage km 204.741 to km 209.945 o
(#2117)
PIU Begusarai | PPP | PRAGATI (1/2)

Last PRAGATI Review 22-01-2020

Original Cost (₹ Crores) 1161.0

Revised Cost (₹ Crores) 1168.33

Original TDC 07-02-2022

Revised TDC 21-08-2023

Physical Progress (%) 40.37%

Time Overrun (months) 18.66

Cost Overrun (₹ Crores) 7.33


5. Four/Six laning of Aunta - Simaria (Ganga Bridge with approach roads) Section
of NH -31 from km 197.900 to km 206.050 (Design Chainage) and (Existing
Chainage km 204.741 to km 209.945 o (#2117)
PIU Begusarai | PPP | PRAGATI (2/2)

Milestone: Land Acquisition


• Issue 6816: Pending transfer of 28.97 Ha Railway Land with ECR, Hazipur (04-03-2021) Physical possession given
DPIIT

18
6. Delhi Mumbai Industrial Corridor (DMIC) (#1528)
National Industrial Corridor Development Corporation Limited (NICDC) | PPP | PRAGATI (1/2)

Last PRAGATI Review 25-11-2020

Original Cost (₹ Crores) 36000.0

Revised Cost (₹ Crores) -

Original TDC 31-03-2021

Revised TDC 31-03-2022

Physical Progress (%) -

Time Overrun (months) 12

Cost Overrun (₹ Crores) -


6. Delhi Mumbai Industrial Corridor (DMIC) (#1528)
National Industrial Corridor Development Corporation Limited (NICDC) | PPP | PRAGATI (2/2)

Milestone: Utility Shifting/License/Approval/NOCs


• Issue 4026: Pending preparation and finalisation of Detailed Project Report (DPR) of Aurangabad - Paithan road
(50 km) in Maharashtra with NHAI, Aurangabad (29-12-2016)
• Meeting minutes (03-03-2022): It was informed that DPR has been prepared and land acquisition process will
start in March 2022. Further, the project would be awarded by FY 2022-23.
M/o Power

21
7. Comprehensive Scheme for Strengthening of Transmission and Distribution
(T&D) Systems (CSST&DS) in Arunachal Pradesh and Sikkim (#1648)
Power Grid Corporation of India Limited (POWERGRID) | PUBLIC | PRAGATI (1/2)

Last PRAGATI Review 25-08-2021

Original Cost (₹ Crores) 4754.0

Revised Cost (₹ Crores) 9129.32

Original TDC 31-12-2021

Revised TDC 31-03-2024

Physical Progress (%) 55.0%

Time Overrun (months) 27

Cost Overrun (₹ Crores) 4375.32


7. Comprehensive Scheme for Strengthening of Transmission and Distribution
(T&D) Systems (CSST&DS) in Arunachal Pradesh and Sikkim (#1648)
Power Grid Corporation of India Limited (POWERGRID) | PUBLIC | PRAGATI (2/2)

Milestone: Utility Shifting/License/Approval/NOCs


• Issue 9767: Repair of Damaged Rangpo Bridge (in East Sikkim district) by NHIDCL (29-03-2022)
Non-PRAGATI

24
M/o Communications

25
8. BharatNet (#3123)
Ministry of Communications | PPP | GatiShakti (1/2)

Original Cost (₹ Crores) 61109.0

Revised Cost (₹ Crores) -

Original TDC 31-08-2023

Revised TDC 31-12-2025

Physical Progress (%) 66.42%

Time Overrun (months) 28

Cost Overrun (₹ Crores) -


8. BharatNet (#3123)
Ministry of Communications | PPP | GatiShakti (2/2)

Milestone: Right of Use / Right of Way


• Issue 9402: ROW permission to lay 80.040 KMs OFC for BharatNet at Diglipur, Block- Diglipur, District- N&M
Andaman in Andaman & Nicobar to connect Ten GPs (Sitanagar, Nabagram, Kalighat, Ramnagar, aschim, Sagar,
Shibpur, Gandhinagar, Keralapuram, Ramakrishnapuram & Diglipur BHQ). (14-02-2022)
• Meeting minutes (22-04-2022): Special Secretary, DPIIT advised close coordination between all the stakeholders
to ensure issue resolution within 2 weeks (by 06.05.2022).
M/o Jal Shakti

28
9. Sardar Sarovar Project (#3326)
Narmada and Water Resources, Water Supply and Kalpsar Department-GJ | PUBLIC (1/4)

Original Cost (₹ Crores) 20718.17

Revised Cost (₹ Crores) 31522.3

Original TDC 31-12-2019

Revised TDC 31-12-2022

Physical Progress (%) 94.76%

Time Overrun (months) 36

Cost Overrun (₹ Crores) 10804.13


9. Sardar Sarovar Project (#3326)
Narmada and Water Resources, Water Supply and Kalpsar Department-GJ | PUBLIC (2/4)

Milestone: Utility Shifting/License/Approval/NOCs


• Issue 9887: Pending approval of NHAI crossing at Ch. 5332 m of Moti Chirai Mr. of Nani Chirai Distributory of KBC
(05-04-2022)

• Issue 9888: Pending approval of NHAI crossing at Ch. 4784 m of Mithi Rohar Mr. of Varsamedi Distributory
of KBC (05-04-2022)

• Issue 9889: Approval of NHAI crossing at Ch. 7795 m of Varsamedi Mr. of Motichirai Distributory of KBC
(05-04-2022)
9. Sardar Sarovar Project (#3326)
Narmada and Water Resources, Water Supply and Kalpsar Department-GJ | PUBLIC (3/4)

Milestone: Utility Shifting/License/Approval/NOCs


• Issue 9890: Pending approval of NHAI crossing at Ch. 8339 m of Modavadar Mr. of Motichirai Distributory
of KBC (05-04-2022)

• Issue 9891: Pending approval of NHAI crossing at Ch. 3082 m of Chudva Mr. of Motichirai Distributory of
KBC (05-04-2022)

• Issue 9893: Pending approval of NHAI crossing at Ch. 7963 m of Varsamedi Mr. of Moti Chirai Distributory
of KBC (05-04-2022)
9. Sardar Sarovar Project (#3326)
Narmada and Water Resources, Water Supply and Kalpsar Department-GJ | PUBLIC (4/4)

Milestone: Utility Shifting/License/Approval/NOCs


• Issue 9894: Pending approval of NHAI crossing at Ch. 5624 m of Bhimasar Mr.-1 of Moti Chirai Distributory of
KBC (05-04-2022)
M/o Housing and Urban Affairs

33
10. Delhi-Ghaziabad-Meerut Regional Rapid Transit System (RRTS) corridor
(#3143)
National Capital Region Transport Corporation (NCRTC) | PUBLIC (1/2)

Original Cost (₹ Crores) 30274.0

Revised Cost (₹ Crores) -

Original TDC 30-06-2025

Revised TDC -

Physical Progress (%) 30.1%

Time Overrun (months) -

Cost Overrun (₹ Crores) -


10. Delhi-Ghaziabad-Meerut Regional Rapid Transit System (RRTS)
corridor (#3143)
National Capital Region Transport Corporation (NCRTC) | PUBLIC (2/2)

Milestone: Right of Use / Right of Way


• Issue 9122: Pending waiver of maintenance charges asked by NHAI for highway crossing on Eastern Peripheral
Expressway (22-02-2022)
• Meeting minutes (15-03-2022): Regional Office NHAI informed that the issue being discussed with the Ministry
and resolution of same is expected soon. It was further informed that work on ground is not being hampered
which was agreed by NCTRC.
M/o Power

36
11. Etalin Hydro Electric Project (HEP) - 3097 Megawatt (MW) (#391)
Jindal Steel and Power | PRIVATE (1/2)

Original Cost (₹ Crores) 25296.0

Revised Cost (₹ Crores) -

Original TDC 01 October 2022​

Revised TDC 2029-2030​

Project still in clearance


Physical Progress (%)
stage​

Time Overrun (months) ~8 years

Cost Overrun (₹ Crores) -


11. Etalin Hydro Electric Project (HEP) - 3097 Megawatt (MW) (#391)
Jindal Steel and Power | PRIVATE (2/2)

Milestone: Utility Shifting/License/Approval/NOCs


• Issue 1941: Pending construction of Roing-Anini Road with NHIDCL (11-09-2014)
• Meeting minutes (03-03-2022): NHIDCL informed that construction of first 75 km will be completed by
31.03.2023.
M/o Road Transport and Highways

39
12. 4 Laning of NH-80 section of Mirza Chauki to Farakka from km. 215.00 to km.
260.00 in the state of Jharkhand (Package-I) on Hybrid Annuity Mode (#2993)
PIU Sahibganj | PPP (1/2)

Original Cost (₹ Crores) 904.63

Revised Cost (₹ Crores) 1302.72

Original TDC 19-05-2023

Revised TDC 04-07-2023

Physical Progress (%) 0.0%

Time Overrun (months) 1.53

Cost Overrun (₹ Crores) 398.09


12. 4 Laning of NH-80 section of Mirza Chauki to Farakka from km. 215.00 to km.
260.00 in the state of Jharkhand (Package-I) on Hybrid Annuity Mode (#2993)
PIU Sahibganj | PPP (2/2)

Milestone: Right of Use / Right of Way


• Issue 7839: 2.8097 Ha. land under jurisdiction of Sr. DEN -II, O/o DRM, Malda, PO- Jhaljhalia. (26-11-2021)
Pending with M/o Railways
13. Balance work of Bareilly-Sitapur section of NH-24 from km .260.000 to
km. 419.590 (#2755)
PIU Bareilly | PUBLIC (1/2)

Original Cost (₹ Crores) 697.42

Revised Cost (₹ Crores) 869.62

Original TDC 31-03-2021

Revised TDC 31-12-2022

Physical Progress (%) 65.0%

Time Overrun (months) 21

Cost Overrun (₹ Crores) 172.2


13. Balance work of Bareilly-Sitapur section of NH-24 from
km .260.000 to km. 419.590 (#2755)
PIU Bareilly | PUBLIC (2/2)

Milestone: Land Acquisition


• Issue 7773: Non-transfer of 2.2Ha vacant Railway Land at Rauza Bypass in Shahjahanpur District (26-11-2021)
Issue resolved

You might also like