Minnesota Department of Transportation

511 Travel Info

Hwy 23

Pipestone to Russell

About this project

Map of Hwy 23  project

Summary of work

  • Resurface (asphalt) Hwy 23 from Pipestone to Russell.
  • Culvert replacement near Florence.
  • Bridge deck replacement in Pipestone.
  • Culvert lining along the corridor.

Traffic impacts

  • Aug. 8-30: Hwy 23 down to one lane from 171st St (near Holland) to Hwy 14 (near Florence).
  • A flagging operation and pilot car will direct traffic through the work zone.
  • Allow extra travel time, use caution, expect delays.
  • Florence culvert detour: June 3-Aug. 23 - traffic detoured to Hwy 14 and Hwy 91
  • Pipestone bridge detour: Aug. 26-Nov. 1 - traffic detoured to Hwy 75, CR 8 and Hwy 23

Project update

Aug. 30, 2024

  • Culvert replacement in Florence is complete.
  • Backfilling of new culverts continues.
  • Paving between Florence and Pipestone began Aug. 12; road will be one lane, alternating traffic. Allow extra travel time.
  • Russell to Florence detour is anticipated to be removed Sep. 6 following installation of new guardrails; this timeline is weather dependent.